CN105000811B - A CO2 enrichment-based parallel flow regenerative lime kiln production process - Google Patents
A CO2 enrichment-based parallel flow regenerative lime kiln production process Download PDFInfo
- Publication number
- CN105000811B CN105000811B CN201510444135.1A CN201510444135A CN105000811B CN 105000811 B CN105000811 B CN 105000811B CN 201510444135 A CN201510444135 A CN 201510444135A CN 105000811 B CN105000811 B CN 105000811B
- Authority
- CN
- China
- Prior art keywords
- gas
- kiln
- combustion
- limestone
- parallel flow
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02P—CLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
- Y02P40/00—Technologies relating to the processing of minerals
- Y02P40/40—Production or processing of lime, e.g. limestone regeneration of lime in pulp and sugar mills
Landscapes
- Carbon And Carbon Compounds (AREA)
- Muffle Furnaces And Rotary Kilns (AREA)
- Furnace Details (AREA)
Abstract
Description
技术领域technical field
本发明涉及石灰窑生产工艺方法,特别涉及一种基于CO2富集的并流蓄热式石灰窑生产工艺方法。The invention relates to a production process of a lime kiln, in particular to a production process of a parallel flow regenerative lime kiln based on CO2 enrichment.
背景技术Background technique
冶金工业中,在生产造渣材料生石灰时会产生大量的CO2。实际生产中,生产1吨生石灰就产生超过1吨的CO2,而熔炼1吨钢约需70 kg的生石灰。2014年中国粗钢产量约为8.2亿吨,则约需生石灰5700万吨,产生大于6000万吨的CO2。目前大多使用石灰窑来生产生石灰,但石灰窑排出来的废气中CO2的含量很低,如果要将CO2富集再循环利用,则还需花费很大一部分能源和资金,所以大多数企业选择直接排放,这就造成了一个很严重的环境问题。In the metallurgical industry, a large amount of CO 2 is produced during the production of slagging material quicklime. In actual production, producing 1 ton of quicklime produces more than 1 ton of CO 2 , and smelting 1 ton of steel requires about 70 kg of quicklime. In 2014, China's crude steel output was about 820 million tons, and about 57 million tons of quicklime was needed, which produced more than 60 million tons of CO 2 . At present, lime kilns are mostly used to produce quicklime, but the CO 2 content in the exhaust gas discharged from the lime kilns is very low. If CO 2 is to be enriched and recycled, it will cost a large part of energy and capital, so most enterprises Choose direct discharge, which has caused a very serious environmental problem.
目前国内并流蓄热式石灰窑生产大多使用压缩空气输送煤粉、助燃和产品冷却,产生的烟气中CO2浓度低(体积浓度10~14%)且烟气量大。由于回收烟气后分离低CO2含量的废气成本较高,所以大多企业将烟气直接排入大气,造成严重的大气污染和资源浪费。At present, most domestic co-current regenerative lime kilns use compressed air to transport pulverized coal, support combustion and cool products. The CO 2 concentration in the generated flue gas is low (volume concentration 10-14%) and the flue gas volume is large. Due to the high cost of separating the waste gas with low CO2 content after recovering the flue gas, most enterprises directly discharge the flue gas into the atmosphere, causing serious air pollution and waste of resources.
发明内容Contents of the invention
针对现有工艺方法存在的问题,本发明提供一种基于CO2富集的并流蓄热式石灰窑生产工艺方法。Aiming at the problems existing in the existing process, the present invention provides a co-current regenerative lime kiln production process based on CO2 enrichment.
本发明的技术方案是:Technical scheme of the present invention is:
一种基于CO2富集的并流蓄热式石灰窑生产工艺方法,包括以下步骤:A kind of parallel flow regenerative lime kiln production process method based on CO enrichment, comprising the following steps:
(1)在第一个燃烧周期,将石灰石原料从窑前石料仓输送至称量斗,石灰石原料经称量斗称量后装入料车内运至并流蓄热式石灰窑窑顶,进入并流蓄热式石灰窑的两个窑膛内;(1) In the first combustion cycle, the limestone raw material is transported from the stone silo in front of the kiln to the weighing hopper, and the limestone raw material is weighed by the weighing hopper and then loaded into the feed truck and transported to the roof of the parallel flow regenerative lime kiln. Enter the two kiln chambers of the co-current regenerative lime kiln;
(2)并流蓄热式石灰窑的一个窑膛内的燃料喷枪插入到石灰石料柱内,载气载着燃料由燃料喷枪喷入窑膛内;(2) The fuel spray gun in a kiln chamber of the co-current regenerative lime kiln is inserted into the limestone column, and the carrier gas carries the fuel and is sprayed into the kiln chamber by the fuel spray gun;
(3)通过助燃风机将助燃气体由并流蓄热式石灰窑窑顶供入,在助燃风机的抽力下助燃气体向下流动到燃烧带与燃料相遇,使燃料在燃料喷枪的喷口下方燃烧;(3) The combustion-supporting gas is supplied from the top of the co-current regenerative lime kiln through the combustion-supporting fan, and under the suction of the combustion-supporting fan, the combustion-supporting gas flows downward to the combustion zone and meets the fuel, so that the fuel burns under the nozzle of the fuel spray gun ;
(4)在当前窑膛的燃烧带,石灰石吸收燃料燃烧产生的热量,分解生成生石灰和CO2气体;(4) In the combustion zone of the current kiln, limestone absorbs the heat generated by fuel combustion and decomposes to produce quicklime and CO2 gas;
(5)在当前窑膛的燃烧带产生的生石灰由冷却风机供入的冷却气体进行冷却至80℃~100℃后出料;(5) The quicklime produced in the combustion zone of the current kiln is cooled to 80°C~100°C by the cooling gas supplied by the cooling fan before being discharged;
(6)冷却气体被生石灰加热后上升到连接通道处,与石灰石分解生成的CO2气体和燃料燃烧产生的CO2气体混合通过连接通道进入另一窑膛并上升,经过燃烧带进入预热带对石灰石进行预热;(6) The cooling gas rises to the connecting channel after being heated by quicklime, mixes with the CO 2 gas generated by the decomposition of limestone and the CO 2 gas generated by fuel combustion, enters another kiln through the connecting channel and rises, passes through the combustion zone and enters the preheating zone Preheating the limestone;
(7)预热产生的烟气将热量释放给石灰石后温度降低并排出,通过除尘净化,产生体积浓度大于95%的CO2气体,该CO2气体的一部分作为输送燃料的载气,另一部分作为由冷却风机供入冷却带的冷却气体,其余直接储存或制成干冰产品;(7) The flue gas produced by preheating releases heat to the limestone and then the temperature is lowered and discharged. After dust removal and purification, CO 2 gas with a volume concentration greater than 95% is produced. Part of the CO 2 gas is used as the carrier gas for fuel delivery, and the other part is As the cooling gas fed into the cooling zone by the cooling fan, the rest is directly stored or made into dry ice products;
(8)第一个煅烧周期完成,并流蓄热式石灰窑内各种气流停止流动,并流蓄热式石灰窑开始换向工作,换向时间40 s ~50s,生石灰从并流蓄热式石灰窑的窑膛底部卸出。(8) After the first calcination cycle is completed, the various airflows in the parallel flow regenerative lime kiln stop flowing, and the parallel flow regenerative lime kiln starts to reverse. The kiln bottom of the type lime kiln is unloaded.
步骤(3)所述助燃气体为氧气浓度>95%的富氧。The combustion-supporting gas in step (3) is oxygen-enriched with an oxygen concentration >95%.
所述步骤(7)中所述的体积浓度大于95%的CO2气体中30%~35%的CO2气体直接储存或制成干冰产品。30%-35% of the CO 2 gas in the volume concentration greater than 95% of the CO 2 gas in the step (7) is directly stored or made into a dry ice product.
所述步骤(7)中所述的体积浓度大于95%的CO2气体中5%~10%作为输送燃料的载气。5%-10% of the CO 2 gas with a volume concentration greater than 95% in the step (7) is used as the carrier gas for transporting fuel.
所述步骤(7)中所述的体积浓度大于95%的CO2气体中55%~65%作为由冷却风机供入燃烧带的冷却气体。55%-65% of the CO 2 gas whose volume concentration is greater than 95% in the step (7) is used as the cooling gas supplied to the combustion zone by the cooling fan.
有益效果:Beneficial effect:
本发明提供了基于CO2富集的并流蓄热式石灰窑生产工艺方法,这种具有富集CO2功能的并流蓄热式石灰窑生产工艺方法在制备高质量石灰的同时也得到高纯度的CO2气体。与现有的工艺方法相比,消除了N2在系统内的循环,节省了用于加热N2的能量,并将烟气循环利用以达到提高产品附加值及节能降耗等目标。The present invention provides a CO 2 enrichment-based parallel flow regenerative lime kiln production process. This parallel flow regenerative lime kiln production process with the CO 2 enrichment function can produce high-quality lime while also producing high-quality lime. purity of CO2 gas. Compared with the existing process method, the circulation of N 2 in the system is eliminated, the energy for heating N 2 is saved, and the flue gas is recycled to achieve the goals of increasing product added value, saving energy and reducing consumption.
附图说明Description of drawings
图1为本发明实施例中采用的基于CO2富集的并流蓄热式石灰窑系统结构示意图。Fig. 1 is a schematic structural diagram of a co-current regenerative lime kiln system based on CO2 enrichment used in an embodiment of the present invention.
具体实施方式detailed description
下面结合附图对本发明的具体实施方式做详细说明。The specific implementation manners of the present invention will be described in detail below in conjunction with the accompanying drawings.
实施例1Example 1
本实施例中基于CO2富集的并流蓄热式石灰窑系统结构如图1所示,系统中的采用的除尘装置为袋式除尘器,燃料为煤粉。从排气口排出的烟气的粉尘浓度≤50mg/Nm3。The structure of the co-current regenerative lime kiln system based on CO2 enrichment in this example is shown in Figure 1. The dust removal device used in the system is a bag filter, and the fuel is pulverized coal. The dust concentration of the flue gas discharged from the exhaust port is ≤50mg/Nm 3 .
采用上述并流蓄热式石灰窑系统生产生石灰(CaO),生石灰日产量450吨,每天80个生产周期,每生产周期煤粉量240 kg ~270kg,助燃风过剩系数1.1~1.4。The above-mentioned parallel flow regenerative lime kiln system is used to produce quicklime (CaO). The daily output of quicklime is 450 tons, 80 production cycles per day, the amount of pulverized coal per production cycle is 240 kg~270kg, and the excess coefficient of combustion air is 1.1~1.4.
基于CO2富集的并流蓄热式石灰窑生产工艺方法,包括以下步骤:The production process method of parallel flow regenerative lime kiln based on CO2 enrichment comprises the following steps:
(1)在第一个燃烧周期,将石灰石原料从窑前石料仓输送至称量斗,石灰石原料经称量斗称量后装入料车内运至并流蓄热式石灰窑窑顶,进入并流蓄热式石灰窑的两个窑膛(窑膛1和窑膛2)内;(1) In the first combustion cycle, the limestone raw material is transported from the stone silo in front of the kiln to the weighing hopper, and the limestone raw material is weighed by the weighing hopper and then loaded into the feed truck and transported to the roof of the parallel flow regenerative lime kiln. Enter the two kiln chambers (Kiln Chamber 1 and Kiln Chamber 2) of the co-current regenerative lime kiln;
具体上料工艺:石灰石由地下受料仓,经过电振给料机送至大角度皮带,由大角度皮带将石灰石运至单层石料振筛进行筛分,其中碎石筛除至废石仓作为它用,合格的石灰石则通过振筛由溜槽到中间皮带,再由中间皮带至窑前石料仓。窑前仓的合格石灰石,经过窑前称量斗称量后,送入卷扬提升机料斗,由卷扬机将石灰石送至窑顶石料称量斗,再由一台振动机和可逆皮带机将石灰石送入设在两个窑筒上的旋转布料器,最后由布料器将石灰石送入窑炉。Specific feeding process: Limestone is sent from the underground receiving bin to the large-angle belt through the electric vibrating feeder, and the limestone is transported to the single-layer stone vibrating screen by the large-angle belt for screening, and the crushed stone is screened to the waste rock bin For other purposes, qualified limestone passes through the vibrating screen from the chute to the middle belt, and then from the middle belt to the stone silo in front of the kiln. The qualified limestone in the kiln front warehouse is sent to the hopper of the winch hoist after being weighed by the weighing hopper in front of the kiln. The limestone is fed into the rotary distributor installed on the two kiln barrels, and finally the limestone is sent into the kiln by the distributor.
(2)并流蓄热式石灰窑的一个窑膛(窑膛1)内的燃料喷枪插入到石灰石料柱内,载气载着燃料由燃料喷枪喷入窑膛内;(2) The fuel spray gun in one kiln chamber (kiln chamber 1) of the co-current regenerative lime kiln is inserted into the limestone material column, and the carrier gas carries the fuel and is sprayed into the kiln chamber by the fuel spray gun;
(3)通过助燃风机将氧气浓度>95%的富氧作为助燃气体由并流蓄热式石灰窑窑顶供入,在助燃风机的抽力下助燃气体向下流动到燃烧带与燃料相遇,使燃料在燃料喷枪的喷口下方燃烧;(3) Through the combustion-supporting fan, the oxygen-enriched oxygen with an oxygen concentration > 95% is supplied as a combustion-supporting gas from the roof of the parallel-flow regenerative lime kiln. Under the suction of the combustion-supporting fan, the combustion-supporting gas flows downward to the combustion zone to meet the fuel. Burn the fuel below the nozzle of the fuel lance;
(4)在当前窑膛(窑膛1)的燃烧带,石灰石吸收燃料燃烧产生的热量,分解生成生石灰和CO2气体;(4) In the combustion zone of the current kiln chamber (Kiln Chamber 1), limestone absorbs the heat generated by fuel combustion and decomposes to produce quicklime and CO 2 gas;
(5)在当前窑膛(窑膛1)的燃烧带产生的生石灰由冷却风机供入的冷却气体进行冷却至80℃~100℃后出料;(5) The quicklime produced in the combustion zone of the current kiln chamber (kiln chamber 1) is cooled to 80°C~100°C by the cooling gas supplied by the cooling fan before being discharged;
窑膛1煅烧时,煤粉由燃料喷管喷入窑膛1内,CO2助燃气(输送燃料的载气)从窑顶喷入,两个窑膛的底部通入CO2冷却气(由冷却风机供入燃烧带的冷却气体),CO2冷却气将温度为1000℃~1150℃的高温CaO冷却至80℃~100℃。When kiln chamber 1 is calcined, pulverized coal is sprayed into kiln chamber 1 through fuel nozzle, CO 2 supporting gas (carrier gas for fuel delivery) is injected from kiln top, and CO 2 cooling gas (by The cooling fan feeds the cooling gas into the combustion zone), and the CO2 cooling gas cools the high-temperature CaO with a temperature of 1000°C to 1150°C to 80°C to 100°C.
(6)冷却气体被生石灰加热后上升到连接通道处,与石灰石分解生成的CO2气体和燃料燃烧产生的CO2气体混合通过连接通道进入另一窑膛(窑膛2)并上升,经过燃烧带进入预热带对石灰石进行预热;(6) The cooling gas rises to the connecting channel after being heated by quicklime, mixes with the CO 2 gas generated by the decomposition of limestone and the CO 2 gas generated by fuel combustion, enters another kiln chamber (kiln chamber 2) through the connecting channel and rises, after burning Take it into the preheating zone to preheat the limestone;
(7)预热产生的烟气将热量释放给石灰石后温度降低并排出,通过除尘净化,产生体积浓度大于95%的CO2气体,该CO2气体的5%作为输送燃料的载气,65%作为由冷却风机供入冷却带的冷却气体,其余30%直接储存或制成干冰产品;(7) The flue gas generated by preheating releases heat to the limestone and then the temperature is lowered and discharged. After dust removal and purification, CO 2 gas with a volume concentration greater than 95% is produced, and 5% of the CO 2 gas is used as the carrier gas for transporting fuel, 65 % as the cooling gas supplied by the cooling fan to the cooling zone, and the remaining 30% is directly stored or made into dry ice products;
(8)第一个煅烧周期完成,并流蓄热式石灰窑内各种气流停止流动,并流蓄热式石灰窑开始换向工作,换向时间45s,生石灰从并流蓄热式石灰窑的窑膛底部卸出。(8) After the first calcination cycle is completed, the various airflows in the parallel flow regenerative lime kiln stop flowing, and the parallel flow regenerative lime kiln starts to reverse. The bottom of the kiln chamber is unloaded.
换向工作:助燃空气换向阀门改变位置,助燃空气释放阀门打开,冷却空气释放阀门打开,卸料闸板打开。Reversing work: the position of the combustion air reversing valve is changed, the combustion air release valve is opened, the cooling air release valve is opened, and the discharge gate is opened.
原日石灰450吨的并流蓄热式石灰窑每天排放的CO2量为385~415吨,经本发明方法后,进入空气压缩机的部分的循环使用的烟气量为231~270吨,存储的烟气量164~184吨,降低了烟气排放,减少了环境污染。The amount of CO discharged by the parallel flow regenerative lime kiln with 450 tons of daily lime per day is 385-415 tons. After the method of the present invention, the amount of flue gas that enters the part of the air compressor for recycling is 231-270 tons. The stored flue gas volume is 164~184 tons, which reduces flue gas emissions and environmental pollution.
实施例2Example 2
本实施例中基于CO2富集的并流蓄热式石灰窑系统结构如图1所示,系统中的采用的除尘装置为袋式除尘器,燃料为煤粉。从排气口排出的烟气的粉尘浓度≤50mg/Nm3。The structure of the co-current regenerative lime kiln system based on CO2 enrichment in this example is shown in Figure 1. The dust removal device used in the system is a bag filter, and the fuel is pulverized coal. The dust concentration of the flue gas discharged from the exhaust port is ≤50mg/Nm 3 .
采用上述并流蓄热式石灰窑系统生产生石灰(CaO),生石灰日产量500吨,每天80个生产周期,每生产周期煤粉量265kg ~300kg,助燃风过剩系数1.1~1.4。The above parallel flow regenerative lime kiln system is used to produce quicklime (CaO). The daily output of quicklime is 500 tons, 80 production cycles per day, the amount of pulverized coal per production cycle is 265kg~300kg, and the excess coefficient of combustion air is 1.1~1.4.
基于CO2富集的并流蓄热式石灰窑生产工艺方法,包括以下步骤:The production process method of parallel flow regenerative lime kiln based on CO2 enrichment comprises the following steps:
(1)在第一个燃烧周期,将石灰石原料从窑前石料仓输送至称量斗,石灰石原料经称量斗称量后装入料车内运至并流蓄热式石灰窑窑顶,进入并流蓄热式石灰窑的两个窑膛(窑膛1和窑膛2)内;(1) In the first combustion cycle, the limestone raw material is transported from the stone silo in front of the kiln to the weighing hopper, and the limestone raw material is weighed by the weighing hopper and then loaded into the feed truck and transported to the roof of the parallel flow regenerative lime kiln. Enter the two kiln chambers (Kiln Chamber 1 and Kiln Chamber 2) of the co-current regenerative lime kiln;
(2)并流蓄热式石灰窑的一个窑膛(窑膛1)内的燃料喷枪插入到石灰石料柱内,载气载着燃料由燃料喷枪喷入窑膛内;(2) The fuel spray gun in one kiln chamber (kiln chamber 1) of the co-current regenerative lime kiln is inserted into the limestone material column, and the carrier gas carries the fuel and is sprayed into the kiln chamber by the fuel spray gun;
(3)通过助燃风机将助燃气体由并流蓄热式石灰窑窑顶供入,在助燃风机的抽力下助燃气体向下流动到燃烧带与燃料相遇,使燃料在燃料喷枪的喷口下方燃烧;所述助燃气体为氧气浓度>95%的富氧;(3) The combustion-supporting gas is supplied from the top of the co-current regenerative lime kiln through the combustion-supporting fan, and under the suction of the combustion-supporting fan, the combustion-supporting gas flows downward to the combustion zone and meets the fuel, so that the fuel burns under the nozzle of the fuel spray gun ; The combustion-supporting gas is oxygen-enriched with an oxygen concentration>95%;
(4)在当前窑膛(窑膛1)的燃烧带,石灰石吸收燃料燃烧产生的热量,分解生成生石灰和CO2气体;(4) In the combustion zone of the current kiln chamber (Kiln Chamber 1), limestone absorbs the heat generated by fuel combustion and decomposes to produce quicklime and CO 2 gas;
(5)在当前窑膛(窑膛1)的燃烧带产生的生石灰由冷却风机供入的冷却气体进行冷却至80℃~100℃后出料;(5) The quicklime produced in the combustion zone of the current kiln chamber (kiln chamber 1) is cooled to 80°C~100°C by the cooling gas supplied by the cooling fan before being discharged;
窑膛1煅烧时,煤粉由燃料喷管喷入窑膛1内,CO2助燃气(输送燃料的载气)从窑顶喷入,两个窑膛的底部通入CO2冷却气(由冷却风机供入燃烧带的冷却气体),CO2冷却气将温度为1000℃~1150℃的高温CaO冷却至80℃~100℃。When kiln chamber 1 is calcined, pulverized coal is sprayed into kiln chamber 1 through fuel nozzle, CO 2 supporting gas (carrier gas for fuel delivery) is injected from kiln top, and CO 2 cooling gas (by The cooling fan feeds the cooling gas into the combustion zone), and the CO2 cooling gas cools the high-temperature CaO with a temperature of 1000°C to 1150°C to 80°C to 100°C.
(6)冷却气体被生石灰加热后上升到连接通道处,与石灰石分解生成的CO2气体和燃料燃烧产生的CO2气体混合通过连接通道进入另一窑膛(窑膛2)并上升,经过燃烧带进入预热带对石灰石进行预热;(6) The cooling gas rises to the connecting channel after being heated by quicklime, mixes with the CO 2 gas generated by the decomposition of limestone and the CO 2 gas generated by fuel combustion, enters another kiln chamber (kiln chamber 2) through the connecting channel and rises, after burning Take it into the preheating zone to preheat the limestone;
(7)预热产生的烟气将热量释放给石灰石后温度降低并排出,通过除尘净化,产生体积浓度大于95%的CO2气体,该CO2气体的10%作为输送燃料的载气,55%作为由冷却风机供入冷却带的冷却气体,其余35%直接储存或制成干冰产品;(7) The flue gas generated by preheating releases heat to the limestone and then the temperature is lowered and discharged. After dust removal and purification, CO 2 gas with a volume concentration greater than 95% is produced, and 10% of the CO 2 gas is used as the carrier gas for transporting fuel, 55 % as the cooling gas supplied by the cooling fan to the cooling zone, and the remaining 35% is directly stored or made into dry ice products;
(8)第一个煅烧周期完成,并流蓄热式石灰窑内各种气流停止流动,并流蓄热式石灰窑开始换向工作,换向时间50s,生石灰从并流蓄热式石灰窑的窑膛底部卸出。(8) After the first calcination cycle is completed, all kinds of air flow in the parallel flow regenerative lime kiln stop flowing, and the parallel flow regenerative lime kiln starts to reverse. The bottom of the kiln chamber is unloaded.
换向工作:助燃空气换向阀门改变位置,助燃空气释放阀门打开,冷却空气释放阀门打开,卸料闸板打开。Reversing work: the position of the combustion air reversing valve is changed, the combustion air release valve is opened, the cooling air release valve is opened, and the discharge gate is opened.
原日石灰500吨的并流蓄热式石灰窑每天排放的CO2量为425~460吨,经本发明方法后,进入空气压缩机的部分的循环使用的烟气量为255~276吨,存储的烟气量170~184吨,降低了烟气排放,减少了环境污染。The amount of CO discharged by the parallel flow regenerative lime kiln with 500 tons of daily lime per day is 425-460 tons. After the method of the present invention, the amount of flue gas recycled into the part of the air compressor is 255-276 tons. The stored flue gas volume is 170~184 tons, which reduces flue gas emissions and environmental pollution.
实施例3Example 3
本实施例中基于CO2富集的并流蓄热式石灰窑系统结构如图1所示,系统中的采用的除尘装置为袋式除尘器,燃料为煤粉。从排气口排出的烟气的粉尘浓度≤50mg/Nm3。The structure of the co-current regenerative lime kiln system based on CO2 enrichment in this example is shown in Figure 1. The dust removal device used in the system is a bag filter, and the fuel is pulverized coal. The dust concentration of the flue gas discharged from the exhaust port is ≤50mg/Nm 3 .
采用上述并流蓄热式石灰窑系统生产生石灰(CaO),生石灰日产量550吨,每天80个生产周期,每生产周期煤粉量290 kg ~330kg,助燃风过剩系数1.1~1.4。The above parallel flow regenerative lime kiln system is used to produce quicklime (CaO). The daily output of quicklime is 550 tons, 80 production cycles per day, the amount of pulverized coal per production cycle is 290 kg ~ 330 kg, and the excess coefficient of combustion air is 1.1 ~ 1.4.
基于CO2富集的并流蓄热式石灰窑生产工艺方法,包括以下步骤:The production process method of parallel flow regenerative lime kiln based on CO2 enrichment comprises the following steps:
(1)在第一个燃烧周期,将石灰石原料从窑前石料仓输送至称量斗,石灰石原料经称量斗称量后装入料车内运至并流蓄热式石灰窑窑顶,进入并流蓄热式石灰窑的两个窑膛(窑膛1和窑膛2)内;(1) In the first combustion cycle, the limestone raw material is transported from the stone silo in front of the kiln to the weighing hopper, and the limestone raw material is weighed by the weighing hopper and then loaded into the feed truck and transported to the roof of the parallel flow regenerative lime kiln. Enter the two kiln chambers (Kiln Chamber 1 and Kiln Chamber 2) of the co-current regenerative lime kiln;
(2)并流蓄热式石灰窑的一个窑膛(窑膛1)内的燃料喷枪插入到石灰石料柱内,载气载着燃料由燃料喷枪喷入窑膛内;(2) The fuel spray gun in one kiln chamber (kiln chamber 1) of the co-current regenerative lime kiln is inserted into the limestone material column, and the carrier gas carries the fuel and is sprayed into the kiln chamber by the fuel spray gun;
(3)通过助燃风机将助燃气体由并流蓄热式石灰窑窑顶供入,在助燃风机的抽力下助燃气体向下流动到燃烧带与燃料相遇,使燃料在燃料喷枪的喷口下方燃烧;所述助燃气体为氧气浓度>95%的富氧;(3) The combustion-supporting gas is supplied from the top of the co-current regenerative lime kiln through the combustion-supporting fan, and under the suction of the combustion-supporting fan, the combustion-supporting gas flows downward to the combustion zone and meets the fuel, so that the fuel burns under the nozzle of the fuel spray gun ; The combustion-supporting gas is oxygen-enriched with an oxygen concentration>95%;
(4)在当前窑膛(窑膛1)的燃烧带,石灰石吸收燃料燃烧产生的热量,分解生成生石灰和CO2气体;(4) In the combustion zone of the current kiln chamber (Kiln Chamber 1), limestone absorbs the heat generated by fuel combustion and decomposes to produce quicklime and CO 2 gas;
(5)在当前窑膛(窑膛1)的燃烧带产生的生石灰由冷却风机供入的冷却气体进行冷却至80℃~100℃后出料;(5) The quicklime produced in the combustion zone of the current kiln chamber (kiln chamber 1) is cooled to 80°C~100°C by the cooling gas supplied by the cooling fan before being discharged;
窑膛1煅烧时,煤粉由燃料喷管喷入窑膛1内,CO2助燃气(输送燃料的载气)从窑顶喷入,两个窑膛的底部通入CO2冷却气(由冷却风机供入燃烧带的冷却气体),CO2冷却气将温度为1000℃~1150℃的高温CaO冷却至80℃~100℃。When kiln chamber 1 is calcined, pulverized coal is sprayed into kiln chamber 1 through fuel nozzle, CO 2 supporting gas (carrier gas for fuel delivery) is injected from kiln top, and CO 2 cooling gas (by The cooling fan feeds the cooling gas into the combustion zone), and the CO2 cooling gas cools the high-temperature CaO with a temperature of 1000°C to 1150°C to 80°C to 100°C.
(6)冷却气体被生石灰加热后上升到连接通道处,与石灰石分解生成的CO2气体和燃料燃烧产生的CO2气体混合通过连接通道进入另一窑膛(窑膛2)并上升,经过燃烧带进入预热带对石灰石进行预热;(6) The cooling gas rises to the connecting channel after being heated by quicklime, mixes with the CO 2 gas generated by the decomposition of limestone and the CO 2 gas generated by fuel combustion, enters another kiln chamber (kiln chamber 2) through the connecting channel and rises, after burning Take it into the preheating zone to preheat the limestone;
(7)预热产生的烟气将热量释放给石灰石后温度降低并排出,通过除尘净化,产生体积浓度大于95%的CO2气体,该CO2气体的8%作为输送燃料的载气,60%作为由冷却风机供入冷却带的冷却气体,其余32%直接储存或制成干冰产品;(7) The flue gas generated by preheating releases heat to the limestone and then the temperature is lowered and discharged. After dust removal and purification, CO 2 gas with a volume concentration greater than 95% is produced, and 8% of the CO 2 gas is used as the carrier gas for transporting fuel, 60 % is used as the cooling gas supplied to the cooling zone by the cooling fan, and the remaining 32% is directly stored or made into dry ice products;
(8)第一个煅烧周期完成,并流蓄热式石灰窑内各种气流停止流动,并流蓄热式石灰窑开始换向工作,换向时间40 s,生石灰从并流蓄热式石灰窑的窑膛底部卸出。(8) After the first calcination cycle is completed, the various airflows in the parallel flow regenerative lime kiln stop flowing, and the parallel flow regenerative lime kiln starts to reverse. The kiln chamber bottom of the kiln is unloaded.
换向工作:助燃空气换向阀门改变位置,助燃空气释放阀门打开,冷却空气释放阀门打开,卸料闸板打开。Reversing work: the position of the combustion air reversing valve is changed, the combustion air release valve is opened, the cooling air release valve is opened, and the discharge gate is opened.
原日石灰450吨的并流蓄热式石灰窑每天排放的CO2量为470~510吨,经本发明方法后,进入空气压缩机的部分的循环使用的烟气量为282~306吨,存储的烟气量188~204吨,降低了烟气排放,减少了环境污染。The amount of CO discharged by the parallel flow regenerative lime kiln with 450 tons of daily lime per day is 470 to 510 tons. After the method of the present invention, the amount of flue gas recycled into the part of the air compressor is 282 to 306 tons. The stored flue gas volume is 188~204 tons, which reduces flue gas emissions and environmental pollution.
Claims (5)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201510444135.1A CN105000811B (en) | 2015-07-24 | 2015-07-24 | A CO2 enrichment-based parallel flow regenerative lime kiln production process |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201510444135.1A CN105000811B (en) | 2015-07-24 | 2015-07-24 | A CO2 enrichment-based parallel flow regenerative lime kiln production process |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN105000811A CN105000811A (en) | 2015-10-28 |
| CN105000811B true CN105000811B (en) | 2017-01-18 |
Family
ID=54373730
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201510444135.1A Active CN105000811B (en) | 2015-07-24 | 2015-07-24 | A CO2 enrichment-based parallel flow regenerative lime kiln production process |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN105000811B (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| EP4175920B1 (en) | 2020-07-03 | 2024-04-24 | S.A. Lhoist Recherche Et Developpement | Method for calcining mineral rock in a regenerative parallel-flow vertical shaft furnace, and furnace used |
Families Citing this family (21)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| DE102016104076A1 (en) | 2016-03-07 | 2017-09-07 | Maerz Ofenbau Ag | Plant with a furnace and method of operating such a plant |
| CN107755971B (en) * | 2016-08-18 | 2019-11-26 | 上海宝冶建设工业炉工程技术有限公司 | The nonstandard ash discharge system production method of double-hearth lime kiln |
| CN106892578B (en) * | 2017-04-17 | 2019-09-13 | 王长春 | A kind of full recycling CO2Lime kiln device |
| CN106989590B (en) * | 2017-04-20 | 2022-12-02 | 中钢集团鞍山热能研究院有限公司 | Double-ring-chamber alternate heat supply self-dust-filtering intelligent calcining device and calcining method |
| CN108006688A (en) * | 2017-11-13 | 2018-05-08 | 遵义市贵科科技有限公司 | A kind of flue heat sink |
| CN108504814B (en) * | 2018-05-09 | 2019-08-02 | 东北大学 | A gas-based shaft furnace direct reduced iron cooling system |
| CN108314336A (en) * | 2018-05-09 | 2018-07-24 | 王长春 | A kind of lime kiln device using circulating air |
| WO2022111817A1 (en) | 2020-11-27 | 2022-06-02 | S.A. Lhoist Recherche Et Developpement | Method for calcining mineral rock in a parallel-flow regenerative kiln, and kiln used |
| CN112919468A (en) * | 2021-03-10 | 2021-06-08 | 广西大学 | Method for recovering carbon dioxide by calcining limestone with oxygen-enriched combustion-supporting effect |
| BR112023023565A2 (en) | 2021-05-11 | 2024-03-12 | Tecforlime | DECARBONATION PROCESS OF CARBONATE MATERIALS, MULTI-AXIS VERTICAL FURNACE AND SYSTEM FOR CARBON CAPTURE AND USE OR CARBON CAPTURE AND STORAGE APPLICATION |
| EP4337620A1 (en) | 2021-05-11 | 2024-03-20 | TECforLime | Decarbonation process of carbonated materials in a multi-shaft vertical kiln |
| CA3218534A1 (en) | 2021-05-11 | 2022-11-17 | Tecforlime | Decarbonation process of carbonated materials in a multi-shaft vertical kiln |
| CN116589204B (en) * | 2023-05-16 | 2025-08-29 | 中冶长天国际工程有限责任公司 | A lime production process for CO2 recovery and utilization |
| CN116477854B (en) * | 2023-05-16 | 2024-09-17 | 中冶长天国际工程有限责任公司 | A lime kiln equipment based on carbon emission reduction and control method thereof |
| CN116628576B (en) * | 2023-07-26 | 2023-10-13 | 中南大学 | Intelligent production yield monitoring method for heat carrier lime kiln |
| WO2025196221A1 (en) | 2024-03-20 | 2025-09-25 | S.A. Lhoist Recherche Et Developpement | Method for calcining carbonate mineral stones in a parallel flow regenerative kiln and implemented kiln |
| WO2025195612A1 (en) | 2024-03-20 | 2025-09-25 | S.A. Lhoist Recherche Et Developpement | Method for calcining carbonate mineral stones in a parallel flow regenerative kiln and implemented kiln |
| WO2025242286A1 (en) | 2024-05-21 | 2025-11-27 | S.A. Lhoist Recherche Et Developpement | Method and kiln for calcining carbonate mineral stones in a parallel flow regenerative kiln (pfrk) |
| WO2025242287A1 (en) | 2024-05-21 | 2025-11-27 | S.A. Lhoist Recherche Et Developpement | Method and kiln for calcining carbonate mineral stones in a parallel flow regenerative kiln (pfrk) with rectangular shaft |
| CN118637843B (en) * | 2024-06-27 | 2026-01-27 | 东北大学 | CO reduction2Suspension calcination system with partial pressure function and method for preparing high-activity lime by suspension calcination system |
| CN118702418A (en) * | 2024-06-27 | 2024-09-27 | 东北大学 | A powdered limestone suspension calcination system with waste gas treatment function |
Family Cites Families (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN102649627A (en) * | 2012-06-08 | 2012-08-29 | 河北联合大学 | Method for preparing active lime by calcining limestone |
| CN102786236B (en) * | 2012-08-17 | 2014-05-07 | 西安瑞驰节能工程有限责任公司 | Device and method for capturing carbon dioxide in lime production process |
| CN104176757B (en) * | 2014-08-08 | 2016-05-04 | 石棉县亿欣钙业有限责任公司 | Precipitated calcium carbonate suspension calcining technique |
-
2015
- 2015-07-24 CN CN201510444135.1A patent/CN105000811B/en active Active
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| EP4175920B1 (en) | 2020-07-03 | 2024-04-24 | S.A. Lhoist Recherche Et Developpement | Method for calcining mineral rock in a regenerative parallel-flow vertical shaft furnace, and furnace used |
| EP4324799B1 (en) | 2020-07-03 | 2025-01-15 | S.A. Lhoist Recherche Et Developpement | Method for calcining mineral rock in a vertical right furnace with regenerative parallel flow and furnace used |
Also Published As
| Publication number | Publication date |
|---|---|
| CN105000811A (en) | 2015-10-28 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN105000811B (en) | A CO2 enrichment-based parallel flow regenerative lime kiln production process | |
| CN103304168B (en) | Method for producing cement clinker by using dry-process predecomposition kiln | |
| CN109813129B (en) | A pellet production process and preparation system based on tail gas circulation O2-CO2 combustion support | |
| KR101304686B1 (en) | Part reduced iron for blast furnace and method thereof | |
| CN102296138B (en) | Method for preparing vanadium-iron intermetallic compound and titanium slag using linear moving bed pre-reduction-shaft furnace melting process | |
| CN102348816B (en) | Method for producing sintered ore | |
| CN103131816B (en) | Method for producing spongy iron through dual-based reduction and special chamber type smelting vertical furnace therefor | |
| CN211813457U (en) | System for catching and purifying carbon dioxide in cement clinker production line | |
| CN108504414A (en) | A kind of combustion adjuvant and application method and device improving blast furnace injection rate of pulverized coal combustion | |
| CN113387605B (en) | Method for preparing lightweight aggregate by low-temperature self-heating sintering of multiple kinds of coal gangue | |
| CN101575668A (en) | Method for recovering iron in melting waste slag through flash boiling magnetizing roasting | |
| CN113087002A (en) | Method and system for preparing calcium oxide balls from carbide slag | |
| JP5194378B2 (en) | Method for producing sintered ore | |
| CN110921667A (en) | System for capturing and purifying carbon dioxide in cement clinker production line and implementation method | |
| CN103043930B (en) | A method and equipment for producing cement and capturing CO2 using a closed annular calciner | |
| CN114409290B (en) | Device and method for heating and modifying desulfurized ash based on blast furnace gas | |
| CN104291337B (en) | Melt waste heat is utilized to carry out the method and system of carbon thermal reduction | |
| CN111763019B (en) | A carbon capture lime calcination system and its application method | |
| RU2005118993A (en) | INSTALLATION FOR THE PRODUCTION OF MELTED CAST IRON WITH DRYING AND TRANSPORT OF IRON ORES AND ADDITIVES AND METHOD OF PRODUCTION WITH ITS USE | |
| CN103805729B (en) | A kind of method adopting rotary hearth furnace to produce low-sulfur conversion pig | |
| CN102183142B (en) | Semi-heat accumulating type rotating bed equipment and process for producing large-size high-activity lime | |
| CN206457532U (en) | A kind of vacuum microwave magnesium smelting device | |
| CN203095880U (en) | Equipment for producing cement and trapping CO2 by using airtight annular calcining furnace | |
| CN114990336A (en) | Preheating reduction device and preheating reduction method | |
| CN115583652B (en) | CO (carbon monoxide) 2 Clean zero release's carbide production system |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C06 | Publication | ||
| PB01 | Publication | ||
| C10 | Entry into substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| C14 | Grant of patent or utility model | ||
| GR01 | Patent grant |