CN104812964A - Boom assembly for construction machines - Google Patents
Boom assembly for construction machines Download PDFInfo
- Publication number
- CN104812964A CN104812964A CN201280077380.8A CN201280077380A CN104812964A CN 104812964 A CN104812964 A CN 104812964A CN 201280077380 A CN201280077380 A CN 201280077380A CN 104812964 A CN104812964 A CN 104812964A
- Authority
- CN
- China
- Prior art keywords
- mounting
- boom
- pin
- pin receiving
- cantilever
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02F—DREDGING; SOIL-SHIFTING
- E02F3/00—Dredgers; Soil-shifting machines
- E02F3/04—Dredgers; Soil-shifting machines mechanically-driven
- E02F3/28—Dredgers; Soil-shifting machines mechanically-driven with digging tools mounted on a dipper- or bucket-arm, i.e. there is either one arm or a pair of arms, e.g. dippers, buckets
- E02F3/36—Component parts
- E02F3/38—Cantilever beams, i.e. booms;, e.g. manufacturing processes, forms, geometry or materials used for booms; Dipper-arms, e.g. manufacturing processes, forms, geometry or materials used for dipper-arms; Bucket-arms
- E02F3/382—Connections to the frame; Supports for booms or arms
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02F—DREDGING; SOIL-SHIFTING
- E02F9/00—Component parts of dredgers or soil-shifting machines, not restricted to one of the kinds covered by groups E02F3/00 - E02F7/00
- E02F9/006—Pivot joint assemblies
Landscapes
- Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Mining & Mineral Resources (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Component Parts Of Construction Machinery (AREA)
- Shovels (AREA)
Abstract
Description
技术领域technical field
本发明一般涉及一种施工机械的悬臂组件以及一种用于将悬臂安装到施工机械的方法。The present invention generally relates to a boom assembly for a construction machine and a method for mounting the boom to the construction machine.
背景技术Background technique
施工机械(比如,轮式或履带式挖掘机、轮式装载机、反铲挖土机等等)可设置有悬臂和用于容纳作业工具(如铲斗)的杆件,以便执行特定操作。Construction machines (eg, wheel or track excavators, wheel loaders, backhoes, etc.) may be provided with booms and bars for receiving work tools, such as buckets, in order to perform certain operations.
通常是通过悬臂安装销将悬臂可操作地安装到施工机械上,所述悬臂安装销延伸穿过施工机械底盘上的对应孔以及悬臂。The boom is typically operably mounted to the construction machine by boom mounting pins that extend through corresponding holes in the chassis of the construction machine and through the boom.
US 2006/0275074 A1公开了一种连杆销,其包含机械变形以形成接头,其中,各部件沿着特定的方向布置,以便提供最佳的耐用性。US 2006/0275074 A1 discloses a link pin that incorporates mechanical deformation to form a joint, wherein the parts are arranged in a specific direction in order to provide optimum durability.
由US 6 694 571 B2已知了一种装载机附接枢轴销组件。所述枢轴销组件是通过提供在一端上具有凸台的圆柱销部分而形成,所述圆柱销部分具有平坦的台肩表面,使得其外缘便呈非圆形。A loader attachment pivot pin assembly is known from US 6 694 571 B2. The pivot pin assembly is formed by providing a cylindrical pin portion having a boss on one end, the cylindrical pin portion having a flat shoulder surface so that its outer edge is non-circular.
US 5 630 673 A公开了一种枢轴关节组件,其将第一构件安装到第二构件上,以实现其间的相对转动。第一构件位于由第二构件所限定的一对支架之间,并且,所述两个构件限定在公共轴线上对齐的多个孔。US 5 630 673 A discloses a pivot joint assembly which mounts a first member to a second member for relative rotation therebetween. The first member is positioned between a pair of brackets defined by the second member, and the two members define a plurality of apertures aligned on a common axis.
本发明至少部分地旨在改善或克服先前系统的一个或多个方面。The present invention aims, at least in part, to improve or overcome one or more aspects of previous systems.
发明内容Contents of the invention
根据本发明的一个方面,一种用于施工机械的悬臂组件可包括包含第一销收纳槽的第一侧屏障以及与第一侧屏障间隔开以用于在其间限定悬臂安装部分的第二侧屏障。第二侧屏障包含第二销收纳槽。悬臂可包括销收纳孔,并且可设置在悬臂安装部分内,使得销收纳孔可以与第一销收纳槽和第二销收纳槽对齐。悬臂安装销可延伸穿过销收纳孔、第一销收纳槽以及第二销收纳槽。第一安装构件可在第一销收纳槽处安装在悬臂安装销上,并且可以可拆卸地附接到第一侧屏障上,而第二安装构件可在第二销收纳槽处安装在悬臂安装销上,并且可以可拆卸地附接到第二侧屏障上。According to an aspect of the present invention, a boom assembly for a construction machine may include a first side barrier including a first pin receiving slot and a second side spaced from the first side barrier for defining a boom mounting portion therebetween barrier. The second side barrier includes a second pin receiving slot. The boom may include pin receiving holes and may be disposed within the boom mounting portion such that the pin receiving holes may be aligned with the first pin receiving slot and the second pin receiving slot. The cantilever mounting pin can extend through the pin receiving hole, the first pin receiving slot, and the second pin receiving slot. The first mounting member is mountable on the cantilever mounting pin at the first pin receiving slot and can be removably attached to the first side barrier, while the second mounting member is mountable on the cantilever mounting at the second pin receiving slot pins and can be detachably attached to the second side barrier.
根据本发明的另一方面,公开了一种用于装配悬臂组件的方法。所述悬臂组件可包括包含第一销收纳槽的第一侧屏障以及与所述第一侧屏障间隔开以用于在其间限定悬臂安装部分的第二侧屏障,其中所述第二侧屏障可包含与所述第一销收纳槽对齐的第二销收纳槽。公开的示范性方法可包括:将悬臂安装销插入悬臂的销收纳孔中,使得悬臂安装销至少部分地在两侧从销收纳孔伸出;将悬臂定位在悬臂安装部分内,使得悬臂安装销至少部分地由第一销收纳槽容纳并至少部分地由第二销收纳槽容纳。所述方法可进一步包括:将第一安装构件在第一销收纳槽处安装在悬臂安装销上,并将所述第一安装构件可拆卸地附接到第一侧屏障上;以及将第二安装构件在第二销收纳槽处安装在悬臂安装销上,并将第二安装构件可拆卸地附接到第二侧屏障上。According to another aspect of the invention, a method for assembling a boom assembly is disclosed. The boom assembly may include a first side barrier including a first pin receiving slot and a second side barrier spaced from the first side barrier for defining a boom mounting portion therebetween, wherein the second side barrier may A second pin receiving slot aligned with the first pin receiving slot is included. The disclosed exemplary method may include: inserting a boom mounting pin into a pin receiving hole of the boom such that the boom mounting pin protrudes at least partially from the pin receiving hole on both sides; positioning the boom within the boom mounting portion such that the boom mounting pin At least partially received by the first pin receiving slot and at least partially received by the second pin receiving slot. The method may further include: mounting a first mounting member on the cantilever mounting pin at the first pin receiving slot, and removably attaching the first mounting member to the first side barrier; and attaching the second mounting member to the first side barrier. The mounting member is mounted on the cantilever mounting pin at the second pin receiving slot and removably attaches the second mounting member to the second side barrier.
根据本发明的另一方面,悬臂组件可包括:第一侧屏障;第二侧屏障,其与所述第一侧屏障间隔开以用于在其间限定悬臂安装部分;悬臂,其包括销收纳孔并设置在悬臂安装部分内;悬臂安装销,其延伸穿过销收纳孔并配置为至少部分地在两侧从销收纳孔伸出;第一安装构件,其安装在悬臂安装销的第一伸出侧处;以及第二安装构件,其安装在悬臂安装销的与第一伸出侧相对的第二伸出侧处。所述第一安装构件可以可拆卸地附接到第一侧屏障,并且所述第二安装构件可以可拆卸地附接到第二侧屏障。According to another aspect of the present invention, a boom assembly may include: a first side barrier; a second side barrier spaced apart from said first side barrier for defining a boom mounting portion therebetween; a boom including a pin receiving hole and be arranged in the cantilever mounting part; the cantilever mounting pin, which extends through the pin receiving hole and is configured to protrude from the pin receiving hole at least partially on both sides; the first mounting member, which is installed on the first extension of the cantilever mounting pin and a second mounting member mounted on a second protruding side of the cantilever mounting pin opposite to the first protruding side. The first mounting member may be detachably attached to the first side screen, and the second mounting member may be detachably attached to the second side screen.
根据本发明的另一方面,悬臂组件可包括:包含第一销收纳孔的第一侧屏障;第二侧屏障,其与所述第一侧屏障间隔开以用于在其间限定悬臂安装部分,并且其包含与所述第一销收纳孔对齐的第二销收纳孔;悬臂,其设置在悬臂安装部分内并包括与第一销收纳孔和第二销收纳孔对齐的悬臂收纳槽;悬臂安装销,其延伸穿过第一销收纳孔、第二销收纳孔和销收纳槽;以及悬臂安装构件,其在销收纳槽处安装在悬臂安装销上并可拆卸地附接到悬臂上。According to another aspect of the present invention, the boom assembly may include: a first side barrier including a first pin receiving aperture; a second side barrier spaced apart from said first side barrier for defining a boom mounting portion therebetween, and comprising a second pin receiving hole aligned with said first pin receiving hole; a cantilever arm disposed within the cantilever mounting portion and comprising a cantilever receiving slot aligned with the first pin receiving hole and the second pin receiving hole; the cantilever mounted a pin extending through the first pin receiving hole, the second pin receiving hole and the pin receiving slot; and a boom mounting member mounted on the boom mounting pin at the pin receiving slot and detachably attached to the boom.
根据本发明的另一方面,施工机械的上部结构可包括根据本发明所述的悬臂组件。According to another aspect of the invention, a superstructure of a construction machine may comprise a boom assembly according to the invention.
在一些实施例中,所述第二安装构件可在第二销收纳槽处与第二侧屏障一体形成,从而形成销收纳孔。在这些实施例中,所述悬臂安装销可延伸穿过第一安装槽、悬臂的销收纳孔以及第二侧屏障的销收纳孔。In some embodiments, the second mounting member may be integrally formed with the second side barrier at the second pin receiving slot, thereby forming a pin receiving hole. In these embodiments, the cantilever mounting pin may extend through the first mounting slot, the pin receiving hole of the cantilever, and the pin receiving hole of the second side barrier.
通过以下的说明和附图,本发明的其它特征和方面将变得清晰可见。Other features and aspects of the invention will become apparent from the following description and accompanying drawings.
附图说明Description of drawings
图1是包括悬臂的施工机械的侧视图;Figure 1 is a side view of a construction machine including a boom;
图2是无悬臂的图1施工机械的俯视图;Fig. 2 is a top view of the construction machine in Fig. 1 without a cantilever;
图3是根据第一实施例的悬臂组件的分解图;Figure 3 is an exploded view of the boom assembly according to the first embodiment;
图4是根据第二实施例的悬臂组件的分解图;Figure 4 is an exploded view of a boom assembly according to a second embodiment;
图5是根据第三实施例的悬臂组件的分解图;Figure 5 is an exploded view of a boom assembly according to a third embodiment;
图6是根据第四实施例的悬臂组件的分解图;Figure 6 is an exploded view of a boom assembly according to a fourth embodiment;
图7是悬臂安装销的实施例的前视图;以及Figure 7 is a front view of an embodiment of a cantilever mounting pin; and
图8是悬臂安装销的另一实施例的透视图。Figure 8 is a perspective view of another embodiment of a cantilever mounting pin.
具体实施方式Detailed ways
以下是本发明的示范性实施例的详细描述。其中所描述的并在附图中所示的示范性实施例旨在教导本发明的原理,使本领域普通技术人员能够在许多不同的环境并且针对许多不同应用实施并使用本发明。因此,所述示范性实施例并非旨在并且不应该解释成是对保护范围的限制性描述。而是,专利保护的范围应当由所附的权利要求书限定。The following is a detailed description of exemplary embodiments of the present invention. The exemplary embodiments described therein and shown in the drawings are intended to teach the principles of the invention and enable one of ordinary skill in the art to make and use the invention in many different environments and for many different applications. Accordingly, the exemplary embodiments are not intended and should not be construed as a limiting description of the scope of protection. Rather, the scope of patent protection shall be defined by the appended claims.
本发明可以部分地基于如下实现:将悬臂安装销插入悬臂中,并且随后,将具有预装配的悬臂安装销的悬臂安置到施工机械的悬臂安装部分中,所述悬臂安装部分提供相对应的销收纳槽,可有助于将悬臂附接到施工机械。特别地,悬臂的销收纳孔和施工机械底盘的销收纳孔的对齐可以至少部分地消失。The invention may be based in part on the insertion of a boom mounting pin into a boom, and subsequently, placing the boom with the pre-assembled boom mounting pin into a boom mounting part of a construction machine that provides a corresponding Pin storage slots to aid in attaching the boom to construction machinery. In particular, the alignment of the pin-receiving holes of the boom and the pin-receiving holes of the chassis of the construction machine can at least partially disappear.
参照图1,示出了施工机械10,例如轮式挖掘机。所述施工机械10包含动力源,比如内燃机12。所述施工机械10进一步包含上部结构14,其通过转体15可旋转地附接到底架16。替代地,所述上部结构14可以固定地安装到底架16上或用任何合适的方式或配置安装。Referring to FIG. 1 , a construction machine 10 , such as a wheeled excavator, is shown. The construction machine 10 includes a power source, such as an internal combustion engine 12 . The construction machine 10 further comprises a superstructure 14 which is rotatably attached to an undercarriage 16 via a swivel 15 . Alternatively, the superstructure 14 may be fixedly mounted to the chassis 16 or in any suitable manner or configuration.
所述施工机械10还包含牵引系统18,例如多组车轮24、26,其可操作地附接到底架16。至少一组车轮是可转向的。The construction machine 10 also includes a traction system 18 , such as sets of wheels 24 , 26 , operatively attached to the chassis 16 . At least one set of wheels is steerable.
虽然已将牵引系统18示出为包含车轮,但是本发明也可应用于具有一或多条环形履带和/或皮带的施工机械或车辆,或任何其它类型的牵引装置。此外,本发明可应用于改变一或多个牵引装置的转向角的转向系统,以及滑移转向装置和差速转向系统。此外,这些系统均可应用于具有各种类型的履带和装置的作业机械。例如,虽然履带式作业机械通常配置有滑移转向装置或差速转向系统,但是其可自动地或额外地配置有改变一或多条履带的转向角的转向系统。类似地,轮式作业机械或车辆可通过可变转向角系统、滑移转向装置和/或差速转向系统来转向。While the traction system 18 has been shown as including wheels, the invention is also applicable to construction machines or vehicles having one or more endless tracks and/or belts, or any other type of traction device. Furthermore, the invention is applicable to steering systems that vary the steering angle of one or more traction devices, as well as skid steer and differential steering systems. Furthermore, these systems are applicable to work machines with various types of tracks and devices. For example, while track-type work machines are typically configured with a skid steer or differential steering system, they may be automatically or additionally configured with a steering system that changes the steering angle of one or more tracks. Similarly, wheeled work machines or vehicles may be steered via variable steering angle systems, skid steering, and/or differential steering systems.
图1示出为轮式挖掘机的施工机械10可以是任何类型的具有操作员控制的转向和行进的作业机械。例如,施工机械10可包含轮式装载机、机动平地机、反铲装载机、滑移转向装置、履带式拖拉机、履带式挖掘机、材料搬运机、起重机以及任何其它类型的具有操作员控制的转向和行进的作业机械。Construction machine 10 , shown in FIG. 1 as a wheeled excavator, may be any type of work machine with operator-controlled steering and travel. For example, construction machine 10 may include wheel loaders, motor graders, backhoe loaders, skid steers, track tractors, track excavators, material handlers, cranes, and any other type of machine with operator controls. Steering and traveling work machinery.
在一些实施例中,施工机械10可包含驾驶室提升功能,通过所述功能,可相对于底架16升高和降低操作者站14。替代地或额外地,驾驶室提升功能可导致相对于上部结构14升高和降低操作者站22。可液压地致动驾驶室提升功能。In some embodiments, construction machine 10 may include a cab lift function by which operator station 14 may be raised and lowered relative to underframe 16 . Alternatively or additionally, the cab lift function may cause the operator station 22 to be raised and lowered relative to the superstructure 14 . The cab lift function is hydraulically actuatable.
施工机械10进一步包含作业机具20和操作者站22,从操作者站22控制作业机具20。作业机具20可以是任何类型的作业机具,并可包含任何类型的作业工具,例如,铲斗、刀片、抓斗、手提钻剪切机、等等。The construction machine 10 further includes a work tool 20 and an operator station 22 from which the work tool 20 is controlled. Work tool 20 may be any type of work tool and may include any type of work implement, eg, buckets, blades, grapples, jackhammers, shears, and the like.
如图1所示,作业机具20包含悬臂28、杆件30以及附接到杆件30的端部的作业工具32。悬臂28枢转地附接到上部结构14。至少一个悬臂致动器34附接到上部结构14和悬臂28,使得通过悬臂致动器34的致动来升高和降低悬臂28的远端36。As shown in FIG. 1 , work tool 20 includes a boom 28 , a rod 30 , and a work tool 32 attached to an end of rod 30 . The boom 28 is pivotally attached to the superstructure 14 . At least one boom actuator 34 is attached to the superstructure 14 and the boom 28 such that actuation of the boom actuator 34 raises and lowers the distal end 36 of the boom 28 .
还使悬臂28的远端36左右移动。在所示示范性实施例中,通过使上部结构14在箭头40指示的方向上围绕轴线38相对于底架16旋转来使悬臂28左右移动。施工机械10还可包含偏移悬臂功能,通过所述功能,可使悬臂28相对于上部结构14左右枢转。The distal end 36 of the boom 28 is also moved side to side. In the exemplary embodiment shown, boom 28 is moved side to side by rotating superstructure 14 about axis 38 relative to chassis 16 in the direction indicated by arrow 40 . The construction machine 10 may also include an offset boom feature by which the boom 28 may be pivoted side to side relative to the superstructure 14 .
杆件30可枢转地附接到悬臂28的近端42处。杆件致动器44附接到悬臂28和杆件30,使得杆件致动器44的致动导致杆件30以折叠刀的方式相对于悬臂28延伸及缩回。也就是说,使杆件30的远端46进一步远离底架12地延伸,并通过致动杆件致动器44来更靠近底架16地缩回。Rod 30 is pivotally attached to proximal end 42 of boom 28 . A lever actuator 44 is attached to the boom 28 and the lever 30 such that actuation of the lever actuator 44 causes the lever 30 to extend and retract relative to the boom 28 in a jackknife manner. That is, the distal end 46 of the rod 30 is extended further away from the chassis 12 and retracted closer to the chassis 16 by actuating the rod actuator 44 .
作业工具32附接到杆件30的远端46。虽然在图1中已将作业工具32示出为铲斗48,但是作业工具32可以是任何类型的作业工具。作业工具32枢转地附接到杆件30的远端46。作业工具枢转致动器50附接到杆件30和作业工具32,使得作业工具枢转致动器50的致动导致作业工具32相对于杆件30枢转。Work tool 32 is attached to distal end 46 of rod 30 . Although work tool 32 has been shown in FIG. 1 as a bucket 48 , work tool 32 may be any type of work tool. Work tool 32 is pivotally attached to distal end 46 of rod 30 . Work tool pivot actuator 50 is attached to lever 30 and work tool 32 such that actuation of work tool pivot actuator 50 causes work tool 32 to pivot relative to lever 30 .
悬臂致动器34、杆件致动器44和作业工具枢转致动器50可以是任何类型的致动器,比如液压缸,如图1所示。每个液压缸可与其自己的液压回路相关联,以便能够独立控制。某些作业工具(比如铲斗48)可具有单个致动器,因此可由单个液压回路控制。其它类型的作业工具(比如抓斗)可包含不止一个致动器,因此可由不止一个液压回路控制。例如,抓斗可由两个或两个以上液压回路控制。一个回路可控制作业工具枢转致动器50,其可使抓斗以与铲斗48相同的方式枢转。另外,第二回路可控制辅助功能,比如抓斗的旋转。Boom actuator 34 , rod actuator 44 and work tool pivot actuator 50 may be any type of actuator, such as a hydraulic cylinder, as shown in FIG. 1 . Each hydraulic cylinder can be associated with its own hydraulic circuit so that it can be controlled independently. Certain work tools, such as bucket 48 , may have a single actuator and thus be controlled by a single hydraulic circuit. Other types of work tools, such as grapples, may contain more than one actuator and thus be controlled by more than one hydraulic circuit. For example, a grab can be controlled by two or more hydraulic circuits. One circuit controls work tool pivot actuator 50 which pivots the grapple in the same manner as bucket 48 . In addition, a second loop can control auxiliary functions, such as the rotation of the grapple.
现参照图2,示出了图1的施工机械的顶视图。特别地,示出了没有附接悬臂的上部结构14的顶视图。描绘了操作者站22,操作者能够从所述操作者站控制施工机械10的操作。Referring now to FIG. 2 , a top view of the construction machine of FIG. 1 is shown. In particular, a top view of the superstructure 14 is shown without booms attached. An operator station 22 is depicted from which an operator can control operation of the construction machine 10 .
施工机械10设置有悬臂安装部分60,其配置成收纳悬臂(未在图2中明确示出)并提供用于使悬臂相对于上部结构14移动的空间。Construction machine 10 is provided with a boom mounting portion 60 configured to receive a boom (not explicitly shown in FIG. 2 ) and provide space for movement of the boom relative to superstructure 14 .
上部结构14可包括基架,其包含第一侧屏障70和第二侧屏障80,以用于容纳悬臂28和至少一个悬臂致动器34(见图1)。如虚线所指示,第一和第二侧屏障70、80可从施工机械10的背侧延伸到前侧。The superstructure 14 may include a base frame including a first side barrier 70 and a second side barrier 80 for housing the boom 28 and at least one boom actuator 34 (see FIG. 1 ). As indicated by the dashed lines, the first and second side barriers 70 , 80 may extend from the back side to the front side of the construction machine 10 .
在图2所示的实施例中,第一侧屏障70包括销收纳槽72,并且第二侧屏障80包括由虚线指示的销收纳孔82。销收纳槽72和屏障孔82彼此对齐(由轴线62指示),并配置成容纳悬臂安装销94(例如,见图3),以用于将悬臂28安装到上部结构14的基架。In the embodiment shown in FIG. 2 , the first side barrier 70 includes pin receiving slots 72 and the second side barrier 80 includes pin receiving holes 82 indicated by dashed lines. Pin receiving slots 72 and barrier holes 82 are aligned with one another (indicated by axis 62 ) and are configured to receive boom mounting pins 94 (see, eg, FIG. 3 ) for mounting boom 28 to the base frame of superstructure 14 .
参照图3,示出了悬臂组件90的第一实施例的分解图。第一侧屏障70提供两个安装表面73、74,其配置成收纳安装构件78。特别地,两个安装表面73、74均包括配置成收纳例如螺钉的至少一个孔75、76,所述螺钉配置成使安装构件78可拆卸地附接到第一侧屏障70。因此,安装构件78包括对应于所述至少两个孔75、76的至少两个孔。Referring to FIG. 3 , an exploded view of a first embodiment of the boom assembly 90 is shown. The first side barrier 70 provides two mounting surfaces 73 , 74 configured to receive a mounting member 78 . In particular, both mounting surfaces 73 , 74 include at least one aperture 75 , 76 configured to receive, for example, a screw configured to removably attach a mounting member 78 to the first side barrier 70 . Accordingly, the mounting member 78 comprises at least two holes corresponding to said at least two holes 75 , 76 .
在一些实施例中,可借助于例如焊接、钎焊、铆接、粘接或本领域已知的任何其它合适的手段,将安装构件78固定地附接到第一侧屏障70In some embodiments, the mounting member 78 may be fixedly attached to the first side barrier 70 by, for example, welding, brazing, riveting, bonding, or any other suitable means known in the art.
如在图3中进一步示出的,安装构件78还可包括对应于第一侧屏障70的销收纳槽72的销收纳槽79。应当理解的是,销收纳槽72和销收纳槽79一起形成用于容纳悬臂安装销94的圆柱形开口。As further shown in FIG. 3 , the mounting member 78 may also include a pin receiving slot 79 corresponding to the pin receiving slot 72 of the first side barrier 70 . It should be appreciated that pin receiving slot 72 and pin receiving slot 79 together form a cylindrical opening for receiving cantilever mounting pin 94 .
悬臂28在其端部包括销收纳孔92,将悬臂92在所述端部安装至上部结构14(见图1)。销收纳孔92配置成经过轴线64收纳悬臂安装销94。销收纳孔92可包括与悬臂安装销94的直径实质上对应的直径。The boom 28 includes pin receiving holes 92 at the ends thereof at which the boom 92 is mounted to the superstructure 14 (see FIG. 1 ). The pin receiving aperture 92 is configured to receive a cantilever mounting pin 94 through the axis 64 . The pin receiving aperture 92 may include a diameter substantially corresponding to the diameter of the cantilever mounting pin 94 .
悬臂安装销94进一步配置成设置在销收纳槽72和销收纳孔82内,将在下面更详细地说明所述情况。悬臂安装销94包括一定的长度,其至少是第一侧屏障70与第二侧屏障80之间的距离。优选地,悬臂安装销94包括一定的长度,使得悬臂安装销94越过悬臂安装部分60从销收纳槽72伸入销收纳孔82。The cantilever mounting pin 94 is further configured to be disposed within the pin receiving slot 72 and the pin receiving hole 82 , as will be described in more detail below. The cantilever mounting pin 94 includes a length that is at least the distance between the first side barrier 70 and the second side barrier 80 . Preferably, the cantilever mounting pin 94 includes a length such that the cantilever mounting pin 94 extends beyond the cantilever mounting portion 60 from the pin receiving slot 72 into the pin receiving hole 82 .
参照图4,示出了悬臂组件90的第二实施例的分解图。第二实施例的第一侧屏障170与第一实施例的第一侧屏障70相同。第一侧构件170的元件由与第一侧屏障70相同的参考标记来标识,但是具有前缀“1”。Referring to FIG. 4 , an exploded view of a second embodiment of the boom assembly 90 is shown. The first side barrier 170 of the second embodiment is the same as the first side barrier 70 of the first embodiment. Elements of the first side member 170 are identified by the same reference numerals as the first side screen 70, but with the prefix "1".
根据第二实施例,第二侧屏障180与第一侧屏障170类似,使得第二侧屏障180包括配置成收纳安装构件188的两个安装表面183、184。特别地,两个安装表面183\184均包括配置成收纳例如螺钉的至少一个孔185、186,所述螺钉配置成使安装构件188可拆卸地附接到第二侧屏障180。According to the second embodiment, the second side screen 180 is similar to the first side screen 170 such that the second side screen 180 includes two mounting surfaces 183 , 184 configured to receive mounting members 188 . In particular, both mounting surfaces 183\184 include at least one aperture 185, 186 configured to receive, for example, a screw configured to removably attach a mounting member 188 to the second side barrier 180.
参照图5,示出了悬臂组件90的第三实施例的分解图。根据第三实施例,第一侧屏障270包括第一孔275和第二孔276。第一孔275和第二孔276配置成收纳(例如)螺钉,所述螺钉配置成使安装构件278固定地附接到第一侧屏障270。第二侧屏障280包括第一孔285和第二孔286。第一孔285和第二孔286配置成收纳(例如)螺钉,所述螺钉配置成使安装构件288可拆卸地附接到第一侧屏障280。Referring to FIG. 5 , an exploded view of a third embodiment of a boom assembly 90 is shown. According to the third embodiment, the first side barrier 270 includes a first hole 275 and a second hole 276 . The first hole 275 and the second hole 276 are configured to receive, for example, screws configured to fixedly attach the mounting member 278 to the first side barrier 270 . The second side barrier 280 includes a first hole 285 and a second hole 286 . The first hole 285 and the second hole 286 are configured to receive, for example, screws configured to removably attach the mounting member 288 to the first side barrier 280 .
每个安装构件278、288分别包含一个销收纳孔272、282。销收纳孔272、282彼此对齐(由轴线62指示),并配置成安装在悬臂安装销94上。Each mounting member 278, 288 includes a pin receiving aperture 272, 282, respectively. Pin receiving apertures 272 , 282 are aligned with each other (indicated by axis 62 ) and are configured to mount on cantilever mounting pin 94 .
参照图6,示出了悬臂组件190的第四实施例的分解图。第二侧屏障380与图3所示的第一实施例的第二侧屏障80相同。因此,第二侧构件380的元件由与第二侧屏障80相同的参考标记来标识,但是具有前缀“3”。Referring to FIG. 6 , an exploded view of a fourth embodiment of a boom assembly 190 is shown. The second side barrier 380 is the same as the second side barrier 80 of the first embodiment shown in FIG. 3 . Accordingly, elements of the second side member 380 are identified by the same reference numerals as the second side screen 80, but with the prefix "3".
根据第四实施例,第一侧屏障370包括屏障孔372,其配置成与第二侧屏障380的销收纳孔382对齐(由轴线62指示)并收纳悬臂安装销94。According to the fourth embodiment, the first side shield 370 includes a shield aperture 372 configured to align with the pin receiving aperture 382 of the second side shield 380 (indicated by axis 62 ) and receive the cantilever mounting pin 94 .
第四实施例的悬臂328包括配置成容纳悬臂安装销94的销收纳槽192。包括对应于销收纳槽192的销收纳槽393的悬臂安装构件395配置成安装在悬臂安装销94上,并通过(例如)由对应孔396、397、398和399收纳的四个螺钉可拆卸地附接到悬臂328。在一些实施例中,可通过多于或少于四个螺钉将悬臂安装构件395可拆卸地附接到悬臂328。在一些其它实施例中,可借助于例如焊接、钎焊、铆接、粘接或本领域已知的任何其它合适的手段,将悬臂安装构件395固定地附接到悬臂328。The fourth embodiment boom 328 includes pin receiving slots 192 configured to receive boom mounting pins 94 . A cantilever mounting member 395 including a pin receiving slot 393 corresponding to the pin receiving slot 192 is configured to mount on the cantilever mounting pin 94 and is detachably connected by, for example, four screws received by corresponding holes 396, 397, 398 and 399. Attached to boom 328. In some embodiments, cantilever mounting member 395 may be removably attached to cantilever 328 by more or less than four screws. In some other embodiments, cantilever mounting member 395 may be fixedly attached to cantilever 328 by means of, for example, welding, brazing, riveting, adhesives, or any other suitable means known in the art.
如图3至图6所示,悬臂安装销94包括圆柱形形状,其对应于侧屏障、安装构件和/或悬臂处的相应销收纳槽和销收纳孔的形状。在一些实施例中,可在悬臂安装销94与悬臂28处的销收纳孔92之间设置轴承套(未示出),以提供悬臂28相对于悬臂安装销94的旋转运动。As shown in FIGS. 3-6 , the boom mounting pin 94 includes a cylindrical shape that corresponds to the shape of corresponding pin receiving slots and pin receiving holes at the side barrier, mounting member, and/or boom. In some embodiments, a bearing sleeve (not shown) may be provided between the boom mounting pin 94 and the pin receiving hole 92 at the boom 28 to provide rotational movement of the boom 28 relative to the boom mounting pin 94 .
参照图7,示出了悬臂安装销194的另一实施例。悬臂安装销194包括圆柱形部分195和扁平部分195。扁平部分195配置成在将悬臂28装配到侧屏障之后限制悬臂安装销194在悬臂28的运动期间旋转。因此,侧屏障、安装构件和/或悬臂处的相应销收纳槽和销收纳孔也可包括扁平部分,以用于完全对应于悬臂安装销194的形状,使得将悬臂安装销194固定地紧固到侧屏障。Referring to FIG. 7 , another embodiment of a cantilever mounting pin 194 is shown. Cantilever mounting pin 194 includes a cylindrical portion 195 and a flat portion 195 . The flat portion 195 is configured to limit the rotation of the boom mounting pin 194 during movement of the boom 28 after the boom 28 is assembled to the side barrier. Accordingly, corresponding pin-receiving slots and pin-receiving holes at the side barriers, mounting members, and/or booms may also include flattened portions for completely corresponding to the shape of the boom mounting pins 194 such that the boom mounting pins 194 are fixedly fastened. to the side barrier.
对于图8,描绘了悬臂安装销294的另一实施例。悬臂安装销294包括具有第一直径的第一部分295、具有第二直径的第二部分296以及具有第三直径的第三部分297。第一直径和第三直径可以是相等的,其中,第二直径可以大于第一和第三直径。因此,以阶梯形形状提供图9的悬臂安装销294。With respect to FIG. 8 , another embodiment of a cantilever mounting pin 294 is depicted. Cantilever mounting pin 294 includes a first portion 295 having a first diameter, a second portion 296 having a second diameter, and a third portion 297 having a third diameter. The first and third diameters may be equal, wherein the second diameter may be greater than the first and third diameters. Accordingly, the cantilever mounting pin 294 of FIG. 9 is provided in a stepped shape.
第一部分295和第三部分297包括一定的长度,其对应于销收纳槽和/或销收纳孔的长度,其中,第二部分296包括一定的长度,其实质上对应于第一侧屏障与第二侧屏障之间的距离。The first portion 295 and the third portion 297 include a length corresponding to the length of the pin receiving groove and/or the pin receiving hole, wherein the second portion 296 includes a length substantially corresponding to the length of the first side barrier and the second side barrier. The distance between the two side barriers.
在一些实施例中,悬臂安装销294可仅包括具有不相等直径的第一部分295和第二部分296。In some embodiments, the cantilever mounting pin 294 may only include a first portion 295 and a second portion 296 having unequal diameters.
工业实用性Industrial Applicability
在下面,可参照图1至图8描述用于将悬臂安装到施工机械(比如轮式挖掘机)的方法的示范性实施例In the following, an exemplary embodiment of a method for mounting a boom to a construction machine such as a wheeled excavator may be described with reference to FIGS. 1 to 8
参照图3描述用于将悬臂28安装到施工机械的底盘的第一实施例(比如第一侧屏障70和第二侧屏障80)。在第一装配步骤中,将悬臂安装销94插入悬臂28的销收纳孔92,使得悬臂安装销94的一个端面与面向第二侧屏障80的销收纳孔82的悬臂28的一个端侧面同平面。因此,悬臂安装销94在面向销收纳槽72的一侧从销收纳孔92至少部分地伸出。随后,将悬臂28定位于悬臂安装部分60内,使得至少部分地伸出的悬臂安装销容纳在销收纳槽72内,并使得悬臂28的销收纳孔92与第二侧屏障80的销收纳孔82对齐。A first embodiment for mounting the boom 28 to the chassis of a construction machine (such as the first side barrier 70 and the second side barrier 80 ) is described with reference to FIG. 3 . In a first assembly step, the cantilever mounting pin 94 is inserted into the pin receiving hole 92 of the cantilever 28 such that one end face of the cantilever mounting pin 94 is coplanar with one end face of the cantilever 28 facing the pin receiving hole 82 of the second side barrier 80 . Thus, the cantilever mounting pin 94 at least partially protrudes from the pin receiving aperture 92 on the side facing the pin receiving slot 72 . Subsequently, the cantilever 28 is positioned within the cantilever mounting portion 60 such that the at least partially protruding cantilever mounting pin is received in the pin receiving slot 72 and the pin receiving hole 92 of the cantilever 28 is aligned with the pin receiving hole of the second side barrier 80 82 aligned.
接下来,使悬臂安装销94从悬臂安装销94的伸出侧滑入销收纳孔82中,使得悬臂安装销94至少部分地布置在销收纳槽72内并至少部分地布置在销收纳孔82内。在一些实施例中,可使用至少一个开口销(未在图中示出),以用于防止悬臂安装销离开销收纳槽72和销收纳孔82。Next, the cantilever mounting pin 94 is slid into the pin receiving hole 82 from the protruding side of the cantilever mounting pin 94 such that the cantilever mounting pin 94 is at least partially disposed within the pin receiving slot 72 and at least partially disposed in the pin receiving hole 82 Inside. In some embodiments, at least one cotter pin (not shown in the figures) may be used for preventing the cantilever mounting pin from exiting the pin receiving slot 72 and the pin receiving hole 82 .
在最终步骤中,在销收纳槽72处将安装构件78安装在悬臂安装销94上,并通过(例如)两个螺钉将其可拆卸地附接到安装表面73、74。例如,为了保证悬臂28与施工机械10的刚性附接,所述螺钉可具有M36或更大的尺寸。In a final step, the mounting member 78 is mounted on the cantilever mounting pin 94 at the pin receiving slot 72 and removably attached to the mounting surfaces 73, 74 by, for example, two screws. For example, to ensure a rigid attachment of the boom 28 to the construction machine 10, the screws may have a size of M36 or larger.
关于图4,描述用于将悬臂28安装到施工机械的底盘的第二实施例(比如第一侧屏障170和第二侧屏障180)。首先,将悬臂安装销94插入悬臂28的销收纳孔92,使得悬臂安装销94从销收纳孔92的两侧至少部分地伸出。With respect to FIG. 4 , a second embodiment (such as first side barrier 170 and second side barrier 180 ) for mounting boom 28 to the chassis of a construction machine is described. First, the boom mounting pin 94 is inserted into the pin receiving hole 92 of the boom 28 such that the boom mounting pin 94 protrudes at least partially from both sides of the pin receiving hole 92 .
随后,将悬臂28定位于悬臂安装部分60内,使得悬臂安装销92的两个伸出端容纳在两个销收纳槽172、182内。然后,在最终步骤中,在销收纳槽172、182处将安装构件178、188分别安装在悬臂安装销94上,并通过螺钉将其分别可拆卸地附接到安装表面73、74和183、784。The boom 28 is then positioned within the boom mounting portion 60 such that the two projecting ends of the boom mounting pin 92 are received within the two pin receiving slots 172 , 182 . Then, in a final step, mounting members 178, 188 are mounted on cantilever mounting pins 94 at pin receiving slots 172, 182, respectively, and removably attached to mounting surfaces 73, 74, and 183, respectively, by screws. 784.
关于图5,说明用于将悬臂28安装到施工机械的底盘的第三实施例(比如第一侧屏障270和第二侧屏障280)。首先,将悬臂安装销94插入销收纳孔92,使得悬臂安装销94在两侧上从销收纳孔92至少部分地伸出。With respect to FIG. 5 , a third embodiment for mounting the boom 28 to the chassis of a construction machine (such as a first side barrier 270 and a second side barrier 280 ) is illustrated. First, the cantilever mounting pin 94 is inserted into the pin receiving hole 92 such that the cantilever mounting pin 94 at least partially protrudes from the pin receiving hole 92 on both sides.
随后,在悬臂安装销94的两个伸出端处将两个安装构件278、288安装在悬臂安装销92上,即,将悬臂安装销94进一步容纳在销收纳孔272、282内。Subsequently, the two mounting members 278 , 288 are mounted on the boom mounting pin 92 at both projecting ends of the boom mounting pin 94 , ie, the boom mounting pin 94 is further received within the pin receiving holes 272 , 282 .
然后,将悬臂28定位于悬臂安装部分60内,使得安装构件278、288的附接孔与相应侧屏障270、280的孔275、276和285、286对齐。在最终步骤中,通过(例如)相应的螺钉将两个安装构件272、282紧固到侧屏障270、280。The boom 28 is then positioned within the boom mounting portion 60 such that the attachment holes of the mounting members 278 , 288 align with the holes 275 , 276 and 285 , 286 of the respective side barriers 270 , 280 . In a final step, the two mounting members 272, 282 are fastened to the side barriers 270, 280 by eg corresponding screws.
关于图6描述用于将悬臂28安装到施工机械的底盘的第四实施例(比如第一侧屏障370和第二侧屏障380)。首先,将悬臂安装销94插入第一侧屏障370的销收纳孔372并插入第二侧屏障380的销收纳孔382。然后,将悬臂28定位于悬臂安装部分60内,使得悬臂的销收纳槽192安装在悬臂安装销94上。然后,还将悬臂安装构件395设置在悬臂安装部分60内,使得销收纳槽393也在与安装销收纳槽92的一侧相对的一侧处安装在悬臂安装销94上。在最终步骤中,可通过(例如)螺钉将悬臂安装构件395可拆卸地附接到悬臂28。A fourth embodiment (eg, first side barrier 370 and second side barrier 380 ) for mounting boom 28 to the chassis of a construction machine is described with respect to FIG. 6 . First, the cantilever mounting pin 94 is inserted into the pin receiving hole 372 of the first side barrier 370 and into the pin receiving hole 382 of the second side barrier 380 . The boom 28 is then positioned within the boom mounting portion 60 such that the boom's pin receiving slot 192 fits over the boom mounting pin 94 . Then, the boom mounting member 395 is also provided in the boom mounting portion 60 so that the pin receiving groove 393 is also mounted on the boom mounting pin 94 at the side opposite to the side of the mounting pin receiving groove 92 . In a final step, the boom mounting member 395 may be removably attached to the boom 28 by, for example, screws.
在上述实施例中,可使用具有M36或更大的尺寸的螺钉,以用于将悬臂安装到施工机械的底盘。In the above-described embodiments, screws having a size of M36 or larger may be used for mounting the boom to the chassis of the construction machine.
应说明用于将悬臂安装到施工机械的上述方法不限于具有至少两个侧屏障的施工机械。在一些实施例中,所述两个侧屏障可与上部结构的底盘或施工机械的底盘整体地形成。因此,任何所述销收纳槽和销收纳孔也可设置在施工机械的底盘处,使得仍便于将悬臂安装到施工机械。It should be stated that the above-described method for mounting a boom to a construction machine is not limited to construction machines having at least two side barriers. In some embodiments, the two side barriers may be integrally formed with the chassis of the superstructure or the chassis of the construction machine. Thus, any of said pin receiving slots and pin receiving holes may also be provided at the chassis of the construction machine so that mounting the boom to the construction machine is still facilitated.
尽管本文中描述了本发明的优选实施例,但在不背离以下权利要求书的范围的情况下可以做出改进和修改。While preferred embodiments of the invention have been described herein, improvements and modifications can be made without departing from the scope of the following claims.
Claims (15)
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| PCT/IB2012/002960 WO2014087186A1 (en) | 2012-12-03 | 2012-12-03 | Boom assembly for construction machines |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN104812964A true CN104812964A (en) | 2015-07-29 |
Family
ID=47720541
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201280077380.8A Pending CN104812964A (en) | 2012-12-03 | 2012-12-03 | Boom assembly for construction machines |
Country Status (4)
| Country | Link |
|---|---|
| US (1) | US20150299979A1 (en) |
| CN (1) | CN104812964A (en) |
| DE (1) | DE112012007194T5 (en) |
| WO (1) | WO2014087186A1 (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN113431112A (en) * | 2021-05-28 | 2021-09-24 | 中联重科土方机械有限公司 | Bucket assembly method of excavator |
Families Citing this family (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| DE102020131617B4 (en) * | 2020-11-30 | 2022-06-23 | Liebherr-Werk Ehingen Gmbh | Mobile crane comprising an upper carriage with at least one bearing point for bolting on a boom |
Citations (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US3664436A (en) * | 1970-05-15 | 1972-05-23 | Michael A Beagan Jr | Adjustable mounting for rock drills |
| US3684324A (en) * | 1970-12-15 | 1972-08-15 | Grove Mfg Co | Pivot structure for cantilevered crane boom |
| US4607977A (en) * | 1985-08-05 | 1986-08-26 | Varnelis Edmund K | Pivot joint |
| US6533527B1 (en) * | 1999-08-16 | 2003-03-18 | Jrb Company, Inc. | Boom and boom cylinder quick coupler |
| US20060085116A1 (en) * | 2003-02-26 | 2006-04-20 | Shin Caterpillar Mitsubishi Ltd. | Arm sensor device in construction machine |
| CN101688382A (en) * | 2007-04-25 | 2010-03-31 | 株式会社小松制作所 | Work machine boom |
Family Cites Families (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US5630673A (en) | 1996-01-03 | 1997-05-20 | Caterpillar Inc. | Pivot joint assembly |
| US6694571B2 (en) | 2002-07-01 | 2004-02-24 | Clark Equipment Company | Loader attachment pivot pin assembly |
| US20060275074A1 (en) | 2005-06-03 | 2006-12-07 | Rene Guinard | Linkage pin and method of manufacturing the same |
-
2012
- 2012-12-03 DE DE112012007194.8T patent/DE112012007194T5/en not_active Withdrawn
- 2012-12-03 CN CN201280077380.8A patent/CN104812964A/en active Pending
- 2012-12-03 WO PCT/IB2012/002960 patent/WO2014087186A1/en not_active Ceased
- 2012-12-03 US US14/648,871 patent/US20150299979A1/en not_active Abandoned
Patent Citations (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US3664436A (en) * | 1970-05-15 | 1972-05-23 | Michael A Beagan Jr | Adjustable mounting for rock drills |
| US3684324A (en) * | 1970-12-15 | 1972-08-15 | Grove Mfg Co | Pivot structure for cantilevered crane boom |
| US4607977A (en) * | 1985-08-05 | 1986-08-26 | Varnelis Edmund K | Pivot joint |
| US6533527B1 (en) * | 1999-08-16 | 2003-03-18 | Jrb Company, Inc. | Boom and boom cylinder quick coupler |
| US20060085116A1 (en) * | 2003-02-26 | 2006-04-20 | Shin Caterpillar Mitsubishi Ltd. | Arm sensor device in construction machine |
| CN101688382A (en) * | 2007-04-25 | 2010-03-31 | 株式会社小松制作所 | Work machine boom |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN113431112A (en) * | 2021-05-28 | 2021-09-24 | 中联重科土方机械有限公司 | Bucket assembly method of excavator |
| CN113431112B (en) * | 2021-05-28 | 2022-02-18 | 中联重科土方机械有限公司 | Bucket assembly method of excavator |
Also Published As
| Publication number | Publication date |
|---|---|
| US20150299979A1 (en) | 2015-10-22 |
| WO2014087186A1 (en) | 2014-06-12 |
| DE112012007194T5 (en) | 2015-08-13 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN101225669B (en) | Common pivot and support member for attachment interface | |
| US6360459B1 (en) | Tiltable bucket assembly | |
| CN104136689B (en) | Facility carrier and facility | |
| CN114892740B (en) | Loader lift arm assemblies for power machines | |
| EP1124017B1 (en) | Hydraulically driven working machine | |
| KR100586087B1 (en) | Simple attachment and detachable arm of construction machine | |
| CN104812964A (en) | Boom assembly for construction machines | |
| US10975544B1 (en) | Work tool coupling assembly with locking wedge | |
| WO2007034577A1 (en) | Fixing structure of work machine | |
| CN101426980A (en) | Boom for excavation machine | |
| US20060254096A1 (en) | Quick attach coupling device | |
| JP3730551B2 (en) | Offset boom type construction machine | |
| JP2009036324A (en) | Bearing device | |
| CN113135220B (en) | Shaft assembly | |
| WO2019130819A1 (en) | Arm for working machine, bearing member, and method for manufacturing arm for working machine | |
| JP7734106B2 (en) | Work machine and cylinder cover | |
| JPH0324534B2 (en) | ||
| EP4053344B1 (en) | A coupling device for a work machine | |
| WO2014006992A1 (en) | Earth moving device for construction machine | |
| US10378174B2 (en) | Interface for coupling work tool to machine | |
| JP4648585B2 (en) | Link connection structure of tractor | |
| US10392773B2 (en) | Linkage assembly for machine | |
| JP2002322662A (en) | Hydraulic excavator | |
| JP2010059714A (en) | Structure for fixing lift arm | |
| CA2546034A1 (en) | Quick attach coupling device |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C06 | Publication | ||
| PB01 | Publication | ||
| C10 | Entry into substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| WD01 | Invention patent application deemed withdrawn after publication | ||
| WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20150729 |