[go: up one dir, main page]

CN104805814A - Self-elevating platform pile leg mounting method - Google Patents

Self-elevating platform pile leg mounting method Download PDF

Info

Publication number
CN104805814A
CN104805814A CN201410201333.0A CN201410201333A CN104805814A CN 104805814 A CN104805814 A CN 104805814A CN 201410201333 A CN201410201333 A CN 201410201333A CN 104805814 A CN104805814 A CN 104805814A
Authority
CN
China
Prior art keywords
spud leg
main hull
sea
dry dock
jack
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201410201333.0A
Other languages
Chinese (zh)
Inventor
赵晖
季春晓
于庆松
李天侠
未俊丰
尹岩太
史大虎
于效磊
张晓明
于正卿
耿卫东
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China International Marine Containers Group Co Ltd
Yantai CIMC Raffles Offshore Co Ltd
Longkou CIMC Raffles Offshore Co Ltd
Original Assignee
China International Marine Containers Group Co Ltd
Yantai CIMC Raffles Offshore Co Ltd
Longkou CIMC Raffles Offshore Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China International Marine Containers Group Co Ltd, Yantai CIMC Raffles Offshore Co Ltd, Longkou CIMC Raffles Offshore Co Ltd filed Critical China International Marine Containers Group Co Ltd
Priority to CN201410201333.0A priority Critical patent/CN104805814A/en
Publication of CN104805814A publication Critical patent/CN104805814A/en
Pending legal-status Critical Current

Links

Landscapes

  • Underground Or Underwater Handling Of Building Materials (AREA)

Abstract

本发明提供了一种自升式平台桩腿的安装方法,包括步骤:使已建立有基层桩腿段的主船体定位浮于干船坞内;保持基层桩腿段相对于主船体在竖直方向上的静止状态,利用海吊逐次将待安装的桩腿分段吊装至合拢口处,对桩腿分段进行定位焊接,直至主船体上的桩腿段达到预定的高度;其中,海吊定位于干船坞外海域的指定位置。本发明无需桩腿升降,无需站桩,缩短建造工期。由于主船体和海吊均在漂浮状态下,利于两者相对位置的调节,从而便于桩腿的合拢。

The invention provides a method for installing legs of a self-elevating platform, which includes the steps of: positioning and floating the main hull with base leg sections in a dry dock; keeping the base leg sections in a vertical direction relative to the main hull In the static state on the ship, use the sea crane to hoist the pile legs to be installed in sections to the closing opening one by one, and perform positioning welding on the pile leg sections until the pile leg sections on the main hull reach the predetermined height; among them, the sea crane positioning at a designated location in the sea outside the dry dock. The present invention does not need to lift legs, does not need to stand piles, and shortens the construction period. Since the main hull and the sea crane are all in a floating state, it is beneficial to adjust the relative positions of the two, thereby facilitating the closing of the pile legs.

Description

自升式平台桩腿的安装方法Installation method of jack-up platform legs

技术领域technical field

本发明涉及自升式平台的建造领域,特别涉及一种自升式平台桩腿的安装方法。The invention relates to the construction field of self-elevating platforms, in particular to a method for installing legs of self-elevating platforms.

背景技术Background technique

按照目前世界范围内自升式平台的发展趋势,自升式平台桩腿的建造高度将会越来越高,未来几年作业水深范围400英尺、500英尺的自升式平台将成为自升平台的主流产品。自升式平台一般包括主船体和可相对于主船体升降的三个桁架式桩腿,平台作业时,桩腿下伸到海底站立在海床上而支撑主船体,使主船体与海面具有一定的距离。According to the current development trend of jack-up platforms worldwide, the construction height of jack-up platform legs will be higher and higher. In the next few years, jack-up platforms with operating water depths of 400 feet and 500 feet will become jack-up platforms. mainstream products. Jack-up platforms generally include a main hull and three truss-type legs that can be raised and lowered relative to the main hull. When the platform is operating, the legs extend down to the seabed and stand on the seabed to support the main hull, so that the main hull and the sea surface have a certain distance. distance.

自升式平台在建造时,即需要将桩腿安装于主船体上,随着自升式平台的作业水深的增加,桩腿高度也随着增加。在自升式平台建造时,桩腿会分为多个分段,而后在高度方向上依次合拢各个桩腿分段,随着桩腿高度的升高,桩腿最上端摆幅就越大,给桩腿分段的安装带来了很大的难题。When the jack-up platform is built, the legs need to be installed on the main hull. As the working water depth of the jack-up platform increases, the height of the legs also increases. When the jack-up platform is built, the legs will be divided into multiple segments, and then each leg segment will be closed in turn in the height direction. As the height of the legs increases, the swing at the top of the legs will increase. The installation of pile leg segmentation has brought very big difficult problem.

目前,大型桁架式桩腿平台桩腿的安装方法主要有四种:At present, there are mainly four installation methods for the legs of large-scale truss-type leg platforms:

一、岸吊合拢法:如申请号为201010115089.8的中国发明专利公开了一种自升式钻井平台桁架式桩腿合拢方法,该方法的主要步骤如下:将多个桩腿分段竖直后在陆地上进行预合拢;将下水后的船体固定在码头、在码头上利用起重能力很强的岸吊将经过预合拢后的桩腿分段进行合拢。这种方法的优点是在码头进行合拢工作受海况影响较小,并且各桩腿合拢的步骤可并行进行。缺点是这种桩腿安装方法需要依靠起重能力很强的岸吊来完成,受资源限制太大,并且随着桩腿高度的升高,对吊车起重能力的要求也越来越大,例如目前400英尺平台桩腿高度167米,需要170米左右的岸吊完成吊装,而建造吊车花费的成本巨大,该方法不易通用。1. Shore crane closing method: For example, the Chinese invention patent with the application number 201010115089.8 discloses a method for closing the truss-type pile legs of a self-elevating drilling platform. Pre-close on land; fix the launched hull on the wharf, and use a shore crane with strong lifting capacity on the wharf to close the pre-closed pile legs in sections. The advantage of this method is that the closing work at the wharf is less affected by the sea conditions, and the steps of closing the legs can be performed in parallel. The disadvantage is that this method of leg installation needs to be completed by shore cranes with strong lifting capacity, which is too limited by resources, and as the height of the legs increases, the requirements for the lifting capacity of the crane are also increasing. For example, the leg height of a 400-foot platform is currently 167 meters, and a shore crane of about 170 meters is required to complete the hoisting. However, the cost of building a crane is huge, and this method is not easy to use universally.

二、水上拖移安装方法:如申请号为200710157586.2的中国发明专利公开了一种大型桁架式桩腿水上拖移安装方法,其安装方法的概况如下:预定海域插桩;安装拖移机构;吊车吊起桩腿分段至拖移机构,借助升降装置使平台升到指定高度;用拖移机构实现合拢;下降平台进行下一周期合拢。该水上拖移安装方法优点是:无需大型海吊即可完成桩腿分段的安装。缺点是需要主船体(即,平台)升降,在船体升降过程中平台上无法施工,人员上下不便,升桩后平台上不宜有过多的人员,而且平台升降次数极为有限,缩短了平台使用寿命。2. Water towing installation method: For example, the Chinese invention patent with the application number of 200710157586.2 discloses a large truss type pile leg water towing installation method. The overview of the installation method is as follows: predetermined sea area insertion; installation of towing mechanism; crane Lift the pile legs segmentally to the dragging mechanism, use the lifting device to raise the platform to the specified height; use the dragging mechanism to close up; lower the platform to close up in the next cycle. The advantage of this water towing installation method is that the segmental installation of pile legs can be completed without large sea cranes. The disadvantage is that the main hull (that is, the platform) needs to be lifted. During the lifting process of the hull, construction cannot be carried out on the platform, and it is inconvenient for personnel to go up and down. .

三、站桩合拢方法:这种方法的大致步骤为:主船体下水后先将桩腿升降系统调试完成;选择合拢的海床;平台在该海床上进行站桩;利用海吊将分段吊至桩腿合拢口处进行桩腿安装。3. Pile closing method: The general steps of this method are: after the main hull is launched, the lifting system of the pile legs is debugged first; the seabed to be closed is selected; the platform stands on the seabed; Install the legs at the closing opening of the legs.

四、深海合拢方法:这种方法的大致步骤为:建立基层桩腿分段,将平台驶入深海区域,运用驳船运送桩腿分段到合拢区域,使用导轨或者海吊将桩腿分段合拢到基层桩腿分段上,合拢完成后下降桩腿,进行下一个周期的合拢。这种方法虽说合拢时平台始终处于漂浮状态,但这种方法合拢由于要处于深海区,因此受风浪涌的条件限制,基本没有船厂采用。4. Deep-sea closing method: The general steps of this method are: establish base pile leg segments, drive the platform into the deep sea area, use barges to transport the pile leg segments to the closing area, and use guide rails or sea cranes to close the pile leg segments Go to the sub-sections of the pile legs at the base level, and after the closing is completed, lower the pile legs to carry out the next cycle of closing. Although this method means that the platform is always in a floating state when it is closed, it is basically not adopted by shipyards due to the limitation of wind and surge conditions because it must be closed in a deep sea area.

第二种和第三种方法是目前海洋工程行业普遍采用的桩腿安装方式,但均需要主船体进行站桩。而进行主船体站桩必须达到两个条件:1、压桩对海床的地质条件要求很严格,若海床地质处在“硬-软粘土层”(俗称鸡蛋壳底层)时,极易发生“压桩穿刺”,破坏桩腿结构,因此,需要寻找合适的海床进行站桩;2、站桩时由于桩腿需要下降,因此桩腿升降系统必须全部调试完成。按照施工工序,桩腿升降系统调试和桩腿合拢按照串联方式进行,这种方式使得平台的整个建造周期要延迟2个月左右。The second and third methods are the pile leg installation methods commonly used in the ocean engineering industry at present, but both require the main hull to stand. However, two conditions must be met to carry out the main hull station piling: 1. The geological conditions of the seabed are very strict for the pressure piling. Pile puncture” will destroy the leg structure. Therefore, it is necessary to find a suitable seabed for standing piles; 2. Since the pile legs need to be lowered when standing piles, the pile leg lifting system must be fully debugged. According to the construction process, the commissioning of the leg lifting system and the closing of the legs are carried out in series, which delays the entire construction period of the platform by about 2 months.

在目前各船厂均想方设法压缩建造周期的大趋势下,需要一种方法来避免升降系统调试无法按时完成、海床不适合站桩等因素对桩腿安装的制约,减少平台制作周期。Under the general trend that all shipyards are trying their best to shorten the construction period, a method is needed to avoid the restrictions on the installation of pile legs due to factors such as the failure to complete the commissioning of the lifting system on time, and the seabed is not suitable for standing piles, so as to reduce the platform production cycle.

发明内容Contents of the invention

基于上述背景技术的不足,本发明提供一种自升式平台桩腿的安装方法,以解决现有平台桩腿的合拢时间长、工作效率低、受海况影响严重等问题。Based on the shortcomings of the above-mentioned background technology, the present invention provides a method for installing the legs of a jack-up platform to solve the problems of long closing time, low work efficiency, and serious influence by sea conditions of the existing platform legs.

为解决上述技术问题,本发明采用如下技术方案:一种自升式平台桩腿的安装方法,包括步骤:In order to solve the above-mentioned technical problems, the present invention adopts the following technical solutions: a method for installing legs of a self-elevating platform, comprising steps:

使已建立有基层桩腿段的主船体定位浮于干船坞内;Position and float the main hull with base leg sections in dry dock;

保持基层桩腿段相对于主船体在竖直方向上的静止状态,利用海吊逐次将待安装的桩腿分段吊装至合拢口处,对桩腿分段进行定位焊接,直至主船体上的桩腿段达到预定的高度;其中,海吊定位于干船坞外海域的指定位置。Keep the static state of the base pile leg section relative to the main hull in the vertical direction, use the sea crane to hoist the pile leg sections to be installed to the closing mouth one by one, and carry out positioning welding on the pile leg sections until the The leg section reaches a predetermined height; wherein, the sea crane is positioned at a designated position in the sea area outside the dry dock.

优选地,所述使已建立有基层桩腿段的主船体定位浮于干船坞内的步骤具体为:Preferably, the step of positioning and floating the main hull with base pile leg sections in the dry dock is as follows:

使已建立有基层桩腿段的主船体下水;launching the main hull with base leg sections established;

将主船体移至干船坞内的预定位置,关闭干船坞的坞门,调节干船坞内水位至指定高度,对主船体系泊定位。Move the main hull to a predetermined position in the dry dock, close the dock door of the dry dock, adjust the water level in the dry dock to a specified height, and moor the main ship.

优选地,所述指定高度低于所述干船坞外海域的海平面高度。Preferably, the specified height is lower than the sea level of the sea area outside the dry dock.

优选地,所述主船体在所述干船坞内的吃水深度为一设定值。Preferably, the draft of the main hull in the dry dock is a set value.

优选地,所述利用海吊将桩腿分段吊装至合拢口处前还包括步骤:调节海吊与主船体上待安装桩腿分段处的相对位置。Preferably, before hoisting the leg segments to the closing opening by using the sea crane, the method further includes the step of: adjusting the relative position between the sea crane and the leg segments to be installed on the main hull.

优选地,所述调节海吊与主船体上待安装桩腿分段处的相对位置的步骤具体为:使主船体在干船坞内转动而调节待安装桩腿分段处与海吊之间的距离和角度。Preferably, the step of adjusting the relative position between the sea crane and the section of the legs to be installed on the main hull is specifically: rotating the main hull in the dry dock to adjust the distance between the sections of the legs to be installed and the sea crane. distance and angle.

优选地,一段桩腿分段合拢后至下一段桩腿分段合拢前,还包括步骤:调整主船体浮态使下一段桩腿分段安装位置处为水平状态。Preferably, after one leg segment is closed and before the next leg leg segment is closed, a step is further included: adjusting the floating state of the main hull so that the installation position of the next leg segment is in a horizontal state.

优选地,所述主船体浮态调整通过调节主船体内压载水而实现。Preferably, the adjustment of the floating state of the main hull is realized by adjusting the ballast water in the main hull.

优选地,所述桩腿分段截面呈等边三角形,所述海吊从所述等边三角形的顶点至重心方向的延长线一侧对桩腿分段进行吊装。Preferably, the segmental section of the pile legs is an equilateral triangle, and the sea crane hoistes the leg segments from the apex of the equilateral triangle to the side of the extension line in the direction of the center of gravity.

优选地,所述待安装的桩腿分段通过合拢工装定位至所述主船体的基层桩腿段上并定位焊接而合拢至基层桩腿段上。Preferably, the leg segments to be installed are positioned on the base leg segments of the main hull by means of closing tooling and fixed to the base leg segments by tack welding.

优选地,所述使已建立有基层桩腿段的主船体定位浮于干船坞内前,利用龙门吊或岸吊将桩腿分段安装于主船体上而形成所述基层桩腿段。Preferably, before positioning and floating the main hull with base leg sections in the dry dock, using a gantry crane or a shore crane to install the legs on the main hull in sections to form the base leg sections.

由上述技术方案可知,本发明的优点和积极效果在于:As can be seen from the foregoing technical solutions, the advantages and positive effects of the present invention are:

一、本发明的方法在进行桩腿的安装时无需使桩腿上下升降,这样保证了合拢时桩腿不需要反复升降,保护升降系统。1. The method of the present invention does not need to lift the legs up and down when installing the legs, which ensures that the legs do not need to be raised and lowered repeatedly when they are closed, and protects the lifting system.

二、本发明的方法不需要在桩腿升降系统调试完成的情况下进行,并且在桩腿安装过程中可以同时进行升降系统的预调试,对升降系统尤其是齿轮箱参数进行校核工作,并可以在桩腿安装的整个周期安装间隙中并行穿插升降系统尤其是齿轮箱的点动升降调试,缩短生产周期,提高生产效率。2. The method of the present invention does not need to be carried out under the condition that the commissioning of the leg lifting system is completed, and the pre-commissioning of the lifting system can be carried out simultaneously during the leg installation process, and the parameters of the lifting system, especially the gearbox, are checked, and The lifting system, especially the inching lifting and debugging of the gearbox, can be interspersed in parallel in the installation gap of the whole cycle of pile leg installation, shortening the production cycle and improving production efficiency.

三、本发明的方法中,主船体浮于干船坞内,海吊则位于干船坞外,两者均在漂浮的状态下,利用绞盘、缆绳等工具,可以轻松地调节主船体的位置从而调节桩腿相对于海吊的位置和角度,通过干船坞内水位的控制还可进一步调节主船体和海吊之间的高度差。3. In the method of the present invention, the main hull floats in the dry dock, and the sea crane is located outside the dry dock. Both of them are in a floating state, and the position of the main hull can be easily adjusted by using tools such as winches and cables. The position and angle of the pile legs relative to the sea crane can further adjust the height difference between the main hull and the sea crane through the control of the water level in the dry dock.

四、本发明的方法中不需站桩,避免了受海床地质调节的影响,避免桩腿受海床地质影响而破坏。Four, in the method of the present invention, do not need to stand pile, have avoided being subjected to the influence of seabed geological regulation, have avoided pile leg being destroyed by seabed geological influence.

附图说明Description of drawings

图1是本发明自升式平台桩腿安装方法一实施例的流程图。Fig. 1 is a flow chart of an embodiment of a method for installing legs of a self-elevating platform according to the present invention.

图2是本发明自升式平台桩腿安装方法在实施时海吊与自升式平台的平面布置示意图。Fig. 2 is a schematic diagram of the layout of the sea crane and the jack-up platform when the method for installing the legs of the jack-up platform according to the present invention is implemented.

图3是本发明自升式平台桩腿安装方法在实施时海吊与自升式平台桩腿的相对位置示意图。Fig. 3 is a schematic diagram of the relative positions of the sea crane and the jack-up platform legs during implementation of the method for installing the legs of the jack-up platform according to the present invention.

图4是本发明自升式平台桩腿安装方法中海吊吊装桩腿分段的俯视示意图。Fig. 4 is a top view schematic diagram of the sub-sections of the hoisting legs of the jack-up platform in the method for installing the legs of the jack-up platform according to the present invention.

图5是海吊从桩腿分段等边三角形重心至顶点方向的延长线一侧吊装桩腿分段的示意图。Fig. 5 is a schematic diagram of a sea crane hoisting a leg segment from one side of the extension line from the center of gravity of the leg segment equilateral triangle to the apex direction.

图6是海吊从桩腿分段等边三角形顶点至重心方向的延长线一侧吊装桩腿分段的示意图。Fig. 6 is a schematic diagram of a sea crane hoisting a leg segment from one side of the extension line from the apex of the equilateral triangle of the leg segment to the direction of the center of gravity.

标号说明:1、自升式平台;11、主船体;12、桩腿;120、桩靴;121、基层桩腿段;122、桩腿分段;2、海吊;21、船体;22、吊杆;3、干船坞;31、坞门。Explanation of symbols: 1. self-elevating platform; 11. main hull; 12. legs; 120. spud boots; 121. base leg section; 122. leg segment; 2. sea crane; Boom; 3, dry dock; 31, dock door.

具体实施方式Detailed ways

体现本发明特征与优点的典型实施方式将在以下的说明中详细叙述。应理解的是本发明能够在不同的实施方式上具有各种的变化,其皆不脱离本发明的范围,且其中的说明及图示在本质上是当作说明之用,而非用以限制本发明。Typical embodiments that embody the features and advantages of the present invention will be described in detail in the following description. It should be understood that the present invention is capable of various changes in different embodiments without departing from the scope of the present invention, and that the description and illustrations therein are illustrative in nature and not limiting. this invention.

本发明提供一种自升式平台桩腿的安装方法,其中,如图2所示,该自升式平台1包括主船体11和可相对于主船体11升降的桩腿12,与目前常见的自升式平台结构一样,该自升式平台1上具有三个桩腿12,桩腿12在主船体11上呈等边三角形排布。本发明的方法即解决桩腿12的安装问题,参阅图1,该方法主要包括步骤:The present invention provides a method for installing the legs of a self-elevating platform, wherein, as shown in Figure 2, the self-elevating platform 1 includes a main hull 11 and a leg 12 that can be raised and lowered relative to the main hull 11, which is different from the current common The self-elevating platform has the same structure, the self-elevating platform 1 has three legs 12, and the legs 12 are arranged in an equilateral triangle on the main hull 11. Method of the present invention promptly solves the installation problem of pile leg 12, referring to Fig. 1, this method mainly comprises steps:

S10:使已建立有基层桩腿段的主船体定位浮于干船坞内;S10: positioning and floating the main hull with base pile leg sections in the dry dock;

S20:保持基层桩腿段相对于主船体在竖直方向上的静止状态,利用海吊逐次将待安装的桩腿分段吊装至合拢口处,对桩腿分段进行定位焊接,直至主船体上的桩腿段达到预定的高度;其中,海吊定位于干船坞外海域的指定位置。“合拢口处”是指需要安装桩腿分段的位置,其是一个动态的位置。以一个桩腿的建造过程为例,桩腿的建造过程是在基层桩腿段的基础上逐次沿高度方向合拢桩腿分段,具体过程为依次在基层桩腿段上合拢第一段桩腿分段,而后在第一段桩腿分段上合拢第二段桩腿分段,再在第二段桩腿分段上合拢第三段桩腿分段,……,最后合拢顶层的桩腿分段;在这个过程中,“合拢口处”则依次指基层桩腿段上端面、第一段桩腿分段上端面、第二段桩腿分段上端面……。在桩腿的建造过程中,桩腿与主船体之间没有竖直方向上的相对位移,即桩腿没有上下升降的过程,不受桩腿升降系统的影响。S20: Keep the static state of the pile leg section of the base layer relative to the main hull in the vertical direction, hoist the pile leg sections to be installed to the closing opening one by one with a sea crane, and carry out positioning welding on the pile leg sections until the main hull The leg section on the top reaches a predetermined height; wherein, the sea crane is positioned at a designated position in the sea area outside the dry dock. "Closed mouth" refers to the position where the leg segments need to be installed, which is a dynamic position. Taking the construction process of a pile leg as an example, the construction process of the pile leg is to close the pile leg segments along the height direction successively on the basis of the base pile leg section, and the specific process is to close the first section of pile leg on the base pile leg section in sequence segment, then close the second leg segment on the first leg segment, then close the third leg segment on the second leg segment, ..., and finally close the top leg Segmentation; in this process, the "closed mouth" refers to the upper end surface of the base leg section, the upper end surface of the first leg section, the upper end surface of the second leg section... During the construction of the pile legs, there is no relative displacement in the vertical direction between the pile legs and the main hull, that is, the pile legs do not go up and down, and are not affected by the pile leg lifting system.

其中,在步骤S10前,船厂可根据本厂的起重能力将尽可能多的桩腿分段通过龙门吊、岸吊等一切可用资源安装于主船体上,从而在主船体上形成基层桩腿段。现有大型龙门吊的吊高一般在80米~90米,高于此高度的桩腿分段,可采用上述步骤S20中方式,利用海吊来进行安装。海吊是一种浮于海面上具有起重能力的起重船,其上安装吊机,而可进行起重作业,海吊分自航式和非自航式,非自航式的起重船整体需要由拖轮拖拽航行。目前大型的海吊只有几艘,船厂需使用时需要进行租赁,由于海吊的租赁成本较高,先利用龙门吊或岸吊完成具有一定高度的基层桩腿段的安装后,只需由海吊完成其余更高高度的桩腿分段的安装,可以尽可能地减少海吊作业工作量,节省租用成本。Among them, before step S10, the shipyard can install as many leg segments as possible on the main hull through all available resources such as gantry cranes and shore cranes according to the lifting capacity of the shipyard, thereby forming base leg segments on the main hull . The lifting height of the existing large-scale gantry crane is generally 80 meters to 90 meters, and the leg segments higher than this height can be installed by using the sea crane in the above step S20. The sea crane is a kind of crane ship with lifting capacity floating on the sea. A crane is installed on it to carry out lifting operations. The sea crane is divided into self-propelled type and non-self-propelled type. The ship as a whole needs to be towed by a tugboat. At present, there are only a few large-scale sea cranes, and the shipyard needs to lease them when they need to use them. Due to the high rental cost of sea cranes, first use gantry cranes or shore cranes to complete the installation of the base pile legs with a certain height, and then only need to use sea cranes. Completing the installation of the rest of the pile legs with a higher height can reduce the workload of the sea crane as much as possible and save the rental cost.

参阅图2和图3,本发明的方法中,步骤S10使主船体11定位浮于干船坞3内可方便主船体11的系泊定位。另外,干船坞3内受浪涌影响小,水面波动程度相对较小,使得主船体11定位于干船坞3内时可处于相对平稳的状态,方便将桩腿分段122安装于主船体11上。Referring to FIG. 2 and FIG. 3 , in the method of the present invention, in step S10 , the main hull 11 is positioned and floated in the dry dock 3 to facilitate the mooring positioning of the main hull 11 . In addition, the dry dock 3 is less affected by surges, and the water surface fluctuations are relatively small, so that the main hull 11 can be in a relatively stable state when positioned in the dry dock 3, and it is convenient to install the leg segments 122 on the main hull 11 .

干船坞3的选择可根据其深度和大小来决定,其大小应使主船体11在其内可以安全灵活移动,干船坞3坞底距离海平面的深度则越高越好。主船体11在干船坞3内定位的具体步骤为:The selection of dry dock 3 can be decided according to its depth and size, and its size should allow main hull 11 to move safely and flexibly therein, and the higher the depth of dry dock 3 docking distances from sea level, the better. The concrete steps that main hull 11 is positioned in dry dock 3 are:

S11:使已建立有基层桩腿段121的主船体11下水;S11: launching the main hull 11 with the foundation leg section 121 established;

S12:将主船体11移至干船坞3内的预定位置,关闭干船坞3的坞门31,调节干船坞3内水位至指定高度,对主船体11系泊定位。S12: Move the main hull 11 to a predetermined position in the dry dock 3, close the dock door 31 of the dry dock 3, adjust the water level in the dry dock 3 to a specified height, and moor the main hull 11 for positioning.

较优地,步骤S12中,所述指定高度低于干船坞3外海域的海平面高度,即在调节干船坞3内水位时具体是指降低干船坞3内的水位。如图3所示,干船坞3内的水位低于坞外的水位,形成一高度差H,这样主船体11的位置降低,对于海吊2来讲,其吊装桩腿分段122所需要达到的最高点也降低了该高度差H,这样降低了海吊2吊杆22的长度要求,可减少海吊2的租赁费用。Preferably, in step S12, the specified height is lower than the sea level of the sea area outside the dry dock 3, that is, when adjusting the water level in the dry dock 3, it specifically refers to lowering the water level in the dry dock 3. As shown in Figure 3, the water level in the dry dock 3 is lower than the water level outside the dock, forming a height difference H, so that the position of the main hull 11 is lowered. For the sea crane 2, the hoisting leg segment 122 needs to reach The height difference H is also reduced at the highest point, which reduces the length requirement of the sea crane 2 boom 22 and reduces the rental cost of the sea crane 2.

此外,在步骤S12中,主船体11在干船坞3内的吃水深度可根据需要调节为一设定值,该设定值在保证自升式平台1安全的前提下尽可能大。其中,保证自升式平台1安全的前提为:使自升式平台1的最低点(即桩腿12的桩靴120最低点)与干船坞3坞底的距离D1大于最小安全距离,以防止桩靴120与干船坞3底部碰撞。通过增加主船体11的吃水深度不仅能调节自升式平台1重心高度,提高平台稳定性,减小摆动幅度,并且在一定程度上还能降低桩腿12相对于海吊2的高度,也可以降低海吊2吊杆22的长度要求。In addition, in step S12, the draft of the main hull 11 in the dry dock 3 can be adjusted to a set value as required, and the set value is as large as possible on the premise of ensuring the safety of the self-elevating platform 1 . Among them, the prerequisite for ensuring the safety of the jack-up platform 1 is: the distance D1 between the lowest point of the jack-up platform 1 (i.e. the lowest point of the spud shoe 120 of the spud leg 12) and the bottom of the dry dock 3 is greater than the minimum safe distance, so as to prevent The spud shoe 120 collides with the bottom of the dry dock 3 . By increasing the draft of the main hull 11, not only can the height of the center of gravity of the self-elevating platform 1 be adjusted, the stability of the platform can be improved, the swing amplitude can be reduced, and the height of the legs 12 relative to the sea crane 2 can also be reduced to a certain extent. The length requirements of the boom 22 of the sea crane 2.

仍然参阅图2和图3,步骤S20海吊2作业时位于干船坞3外海域的指定位置,并系泊定位;海吊2的船体21与干船坞3的坞门31之间的距离D2(包括图2所示的船体21尾部与坞门31之间的水平距离和图3所示的船体21尾部底端与坞门31底部之间的距离)不小于安全距离,且海吊2的吊杆22作业范围需满足可将桩腿分段122吊至主船体11上基层桩腿段121上方的要求。Still refer to Fig. 2 and Fig. 3, step S20 sea crane 2 is positioned at the specified position of the sea area outside dry dock 3 during step S20 operation, and mooring location; The distance D2 between the hull 21 of sea crane 2 and the dock door 31 of dry dock 3 ( Including the horizontal distance between the tail of the hull 21 shown in Figure 2 and the dock door 31 and the distance between the bottom of the tail of the hull 21 shown in Figure 3 and the bottom of the dock door 31) is not less than the safety distance, and the crane 2 The operating range of the pole 22 needs to meet the requirement that the leg segment 122 can be hoisted above the base leg segment 121 on the main hull 11 .

桩腿分段122上设置吊耳(图中未示出),海吊2需吊起桩腿分段122时通过吊带或钢丝绳吊起吊耳,当桩腿分段122合拢至主船体11上后,再从桩腿分段122的吊耳上摘下吊带或钢丝绳的卸扣,海吊2再准备吊起下一段桩腿分段122。海吊2的吊钩连接于吊杆22上并可上下升降,吊带或钢丝绳连接于吊钩上,根据吊装规定,吊带/钢丝绳与水平面的夹角一般不能小于60度,在海吊2吊钩最高点确定后,可通过降低桩腿分段122吊耳高度,可使海吊2满足吊装要求。在满足桩腿分段吊装平衡的前提下,桩腿最上层的桩腿分段122中吊耳在该桩腿分段122上的位置可根据海吊2的能力下移一定距离,提高海吊2的吊装能力和安全性。Lifting lugs (not shown in the figure) are set on the leg segments 122. When the sea crane 2 needs to lift the leg segments 122, the lifting lugs are lifted by slings or wire ropes. When the leg segments 122 are closed to the main hull 11 , and then take off the shackle of suspenders or wire ropes from the lug of the leg segment 122, and the sea crane 2 is ready to lift the next segment of the leg segment 122 again. The hook of the sea crane 2 is connected to the boom 22 and can be lifted up and down. The sling or wire rope is connected to the hook. According to the hoisting regulations, the angle between the sling/wire rope and the horizontal plane is generally not less than 60 degrees. After the highest point is determined, the sea crane 2 can be made to meet the hoisting requirements by reducing the height of the lifting lugs of the leg segments 122. Under the premise of satisfying the lifting balance of the pile legs segmented, the position of the lifting lug in the leg segment 122 on the uppermost layer of the pile leg can be moved down a certain distance according to the capacity of the sea crane 2, and the sea crane can be improved. 2. The hoisting capacity and safety.

在一实施例中,步骤S20利用海吊2将待安装的桩腿分段122合拢至主船体11上的具体步骤为:In one embodiment, step S20 uses the sea crane 2 to close up the pile leg segment 122 to be installed on the main hull 11. The specific steps are:

S21:调节海吊2与主船体11上待安装桩腿分段122处的相对位置。S21: Adjust the relative position of the sea crane 2 and the leg segment 122 to be installed on the main hull 11 .

S22:海吊2将待安装的桩腿分段122吊至主船体11的基层桩腿段121上方。S22: The sea crane 2 lifts the leg segment 122 to be installed above the base leg segment 121 of the main hull 11 .

S23:通过合拢工装将待安装的桩腿分段122定位至主船体11的基层桩腿段121上并定位焊接而合拢至基层桩腿段121上。这一步骤中,可以采用常规的合拢工装进行定位焊接,也可以采用特制定位工装进行定位焊接。通过工装来进行定位克服主船体11和海吊2均处于漂浮状态受浪涌影响而导致的不稳定问题,使桩腿分段122的安装定位更可靠。S23: Position the leg segment 122 to be installed on the base leg segment 121 of the main hull 11 by closing the tooling and position welding to close it on the base leg segment 121 . In this step, conventional closing tooling can be used for positioning welding, or special positioning tooling can be used for positioning welding. Positioning by means of tooling overcomes the instability problem caused by both the main hull 11 and the sea crane 2 being in a floating state and being affected by surges, and makes the installation and positioning of the pile leg segments 122 more reliable.

通过步骤S21至步骤S23即可完成一段桩腿分段122的合拢,而在进行下一段桩腿分段122合拢前,较优地还进行如下步骤:Through step S21 to step S23, one section of leg segment 122 can be closed up, and before the next segment of leg segment 122 is closed, the following steps are preferably carried out:

S24:调整主船体11浮态使下一段桩腿分段安装位置处为水平状态,这样可便于下一段桩腿分段122的定位安装;另外,由于主船体11上一般具有三个桩腿12,而桩腿分段122一次只能向一个基层桩腿段121上安装,这样会导致自升式平台1重量分布不平衡而倾斜,通过调整主船体11浮态还可以防止桩靴120下降碰到干船坞3坞底而损毁。其中,调整主船体11浮态可采用调节主船体11内压载水而实现,方式简单,易于调节。S24: Adjust the floating state of the main hull 11 so that the installation position of the next leg segment is in a horizontal state, which can facilitate the positioning and installation of the next leg segment 122; in addition, since the main hull 11 generally has three legs 12 , and the leg segment 122 can only be installed on one base leg segment 121 at a time, which will cause the jack-up platform 1 to have an unbalanced weight distribution and tilt. By adjusting the floating state of the main hull 11, the spud can 120 can also be prevented from descending and colliding Destroyed at the bottom of Dry Dock 3. Wherein, adjusting the floating state of the main hull 11 can be realized by adjusting the ballast water in the main hull 11, which is simple and easy to adjust.

调整好主船体11浮态后再重复步骤S21至S23即可完成下一段桩腿分段122的合拢,如此重复多次直至完成所有桩腿分段122的安装。After adjusting the floating state of the main hull 11, repeat steps S21 to S23 to complete the closing of the next leg segment 122, and repeat this many times until the installation of all leg segments 122 is completed.

对于上述的步骤S21,较优地,通过使主船体11在干船坞3内转动而调节待安装桩腿分段处与海吊2之间的距离和角度,由于主船体11漂浮于水面上,可以轻松地调节主船体11的位置,且在干船坞3内也便于主船体11的系泊定位。主船体11与海吊2之间的相对位置最好使海吊2与待安装桩腿分段处的距离尽可能小,海吊2吊杆仰角尽可能大,达到降低海吊2租赁费用、使海吊2吊杆22长度尽可能短的目的。For the above step S21, preferably, by rotating the main hull 11 in the dry dock 3 to adjust the distance and angle between the section of the legs to be installed and the sea crane 2, since the main hull 11 floats on the water surface, The position of the main hull 11 can be easily adjusted, and the mooring positioning of the main hull 11 is also facilitated in the dry dock 3 . The relative position between the main hull 11 and the sea crane 2 is preferably such that the distance between the sea crane 2 and the section of the pile legs to be installed is as small as possible, and the elevation angle of the sea crane 2 boom is as large as possible, so as to reduce the sea crane 2 rental fee, The purpose of making the length of the sea crane 2 boom 22 as short as possible.

参阅图4,桩腿分段122的截面呈等边三角形,较优地,在步骤S22中,海吊2从等边三角形的顶点A至重心G方向的延长线一侧对桩腿分段122吊装。对比参阅图5和图6,图5和图6中海吊的吊高相同,吊杆22的长度和仰角均相同,吊杆22顶部均大致位于桩腿分段122等边三角形重心G的正上方,图5是海吊2从等边三角形的重心G至顶点A方向的延长线一侧进行吊装的示意图,图6则是海吊2从等边三角形的顶点A至重心G方向的延长线一侧进行吊装的示意图。明显,两种吊装方式相比,桩腿分段122与海吊2吊杆22之间的水平距离L0的差值即为重心G距顶点A距离L2与重心G距边长距离L1的差值。以常见的桩腿分段结构尺寸为例,等边三角形的边长为13米,三角形的高约为11米,则重心G距边长的距离L1约为3.75米,重心G距顶点A的距离L2约为7.5米,按图6所示方式对桩腿分段122进行吊装时,桩腿分段122与吊杆22之间的水平距离L0比图5的方式要增加约3.75米(即L2-L1),有效降低了桩腿分段122在高空中摇摆时存在的与海吊2结构碰撞的风险。为保证海吊2大约保持在顶点A至重心G方向的延长线一侧,在步骤S21中转动主船体11时应考虑主船体11与海吊2的摆放角度,以使吊装的桩腿分段122与主船体11上的基层桩腿段121对应。在某些实施例中,如果海吊2能力足够,海吊2吊装桩腿分段122的方式可以不受图6所示方式的限制。Referring to Fig. 4, the cross section of the leg segment 122 is an equilateral triangle. Preferably, in step S22, the sea crane 2 aligns the leg segment 122 from the side of the extension line from the apex A of the equilateral triangle to the center of gravity G direction. Hoisting. Refer to Fig. 5 and Fig. 6 for comparison. In Fig. 5 and Fig. 6, the hoisting height of the sea crane is the same, the length and elevation angle of the boom 22 are the same, and the top of the boom 22 is roughly located directly above the center of gravity G of the equilateral triangle 122 of the leg segment. , Fig. 5 is a schematic diagram of sea crane 2 hoisting on one side of the extension line from the center of gravity G of the equilateral triangle to the vertex A, and Fig. 6 is an extension line of the sea crane 2 from the vertex A of the equilateral triangle to the center of gravity G. Schematic diagram of side lifting. Obviously, comparing the two hoisting methods, the difference in the horizontal distance L0 between the leg segment 122 and the boom 22 of the sea crane 2 is the difference in the distance L2 between the center of gravity G and the apex A and the long distance L1 between the center of gravity G and the side . Taking the common segmental structure size of pile legs as an example, the side length of an equilateral triangle is 13 meters, and the height of the triangle is about 11 meters. The distance L2 is about 7.5 meters. When the leg segment 122 is hoisted in the manner shown in FIG. L2-L1), which effectively reduces the risk of collision with the structure of the sea crane 2 when the leg segment 122 is swinging in the sky. In order to ensure that the sea crane 2 remains approximately on the side of the extension line from the apex A to the center of gravity G, when rotating the main hull 11 in step S21, the placement angle between the main hull 11 and the sea crane 2 should be considered, so that the hoisted legs are separated. The section 122 corresponds to the base leg section 121 on the main hull 11 . In some embodiments, if the capacity of the sea crane 2 is sufficient, the way the sea crane 2 lifts the leg segment 122 may not be limited to the way shown in FIG. 6 .

本发明的方法在实施前可事先做好如下准备步骤:Before the method of the present invention is implemented, the following preparatory steps can be done in advance:

1、选择合适的干船坞,确定主船体在干船坞内摆放的初始位置和角度;1. Select a suitable dry dock and determine the initial position and angle of the main hull in the dry dock;

2、确定桩靴最低点与干船坞底部的最小安全距离;2. Determine the minimum safe distance between the lowest point of the spud can and the bottom of the dry dock;

3、确定干船坞坞门与海吊的最小安全距离;3. Determine the minimum safe distance between the dry dock door and the sea crane;

4、确定海吊作业时的位置及带缆(即系泊定位)方式;4. Determine the position and cable (that is, mooring positioning) method during sea crane operation;

5、确定桩腿分段安装顺序及主船体转动顺序;5. Determine the segmental installation sequence of pile legs and the rotation sequence of the main hull;

6、确定干船坞内外水面差,主船体吃水深度以及最高一节桩腿分段上吊耳的位置;6. Determine the water surface difference inside and outside the dry dock, the draft of the main hull and the position of the lifting lug on the highest section of the pile leg;

7、确定主船体压载水调节方案;7. Determine the main hull ballast water regulation scheme;

8、选择合理高度的海吊。8. Choose a sea crane with a reasonable height.

上述准备步骤在事先完成后,在实施本发明的发明时即可快速根据预定方案完成桩腿的安装。After the above-mentioned preparatory steps are completed in advance, the installation of the pile legs can be quickly completed according to the predetermined scheme when implementing the invention of the present invention.

虽然已参照几个典型实施方式描述了本发明,但应当理解,所用的术语是说明和示例性、而非限制性的术语。由于本发明能够以多种形式具体实施而不脱离发明的精神或实质,所以应当理解,上述实施方式不限于任何前述的细节,而应在随附权利要求所限定的精神和范围内广泛地解释,因此落入权利要求或其等效范围内的全部变化和改型都应为随附权利要求所涵盖。While this invention has been described with reference to several exemplary embodiments, it is understood that the terms which have been used are words of description and illustration, rather than of limitation. Since the present invention can be embodied in many forms without departing from the spirit or essence of the invention, it should be understood that the above-described embodiments are not limited to any of the foregoing details, but should be construed broadly within the spirit and scope of the appended claims. , all changes and modifications falling within the scope of the claims or their equivalents shall be covered by the appended claims.

Claims (11)

1. a mounting method for jack-up unit spud leg, is characterized in that, comprises step:
The main hull location setting up basic unit's spud leg section is made to float in dry dock;
Keep basic unit spud leg section relative to the inactive state of main hull in the vertical direction, utilize sea hang successively by spud leg segmental hoisting to be installed to closing up Kou Chu, welding is positioned to spud leg segmentation, until the spud leg section on main hull reaches predetermined height; Wherein, the assigned address being positioned the outer marine site of dry dock is hung in sea.
2. the mounting method of jack-up unit spud leg according to claim 1, is characterized in that, described in make to set up basic unit's spud leg section the main hull location step floated in dry dock be specially:
Make to set up water under the main hull of basic unit's spud leg section;
Main hull is moved to the precalculated position in dry dock, close the dock gate of dry dock, regulate water level in dry dock to specified altitude assignment, to locate main hull mooring.
3. the mounting method of jack-up unit spud leg according to claim 2, is characterized in that, described specified altitude assignment is lower than the sea level altitude in the outer marine site of described dry dock.
4. the mounting method of jack-up unit spud leg according to claim 2, is characterized in that, the draft of described main hull in described dry dock is a setting value.
5. the mounting method of jack-up unit spud leg according to claim 1, is characterized in that, described utilization sea is hung and spud leg segmental hoisting is also comprised step before closing up mouth place: regulate sea to hang the relative position with spud leg to be installed segmentation place on main hull.
6. the mounting method of jack-up unit spud leg according to claim 5, it is characterized in that, the described sea that regulates is hung and on main hull, the step of the relative position of spud leg to be installed segmentation place is specially: main hull is rotated in dry dock and regulate spud leg to be installed segmentation place and sea hang between Distance geometry angle.
7. the mounting method of jack-up unit spud leg according to claim 1, it is characterized in that, after one section of spud leg segment folding to next section of spud leg segment folding, also comprise step: adjustment main hull floading condition makes next section of spud leg segmentation installed position be level.
8. the mounting method of jack-up unit spud leg according to claim 7, is characterized in that, described main hull floading condition adjustment realizes by regulating ballast water in main hull.
9. the mounting method of the jack-up unit spud leg according to any one of claim 1-8, it is characterized in that, described spud leg segmentation cross section is equilateral triangle, and described sea is hung and lifted spud leg segmentation from the extended line side in summit to the center of gravity direction of described equilateral triangle.
10. the mounting method of the jack-up unit spud leg according to any one of claim 1-8, it is characterized in that, described spud leg segmentation to be installed is by closing up in tool locating to basic unit's spud leg section of described main hull and positioning welding and closing up in basic unit's spud leg section.
The mounting method of 11. jack-up unit spud legs according to any one of claim 1-8, it is characterized in that, the described main hull location setting up basic unit's spud leg section that makes floats on before in dry dock, utilizes straddle truck or shore tackle spud leg segmentation to be installed on main hull and forms described basic unit spud leg section.
CN201410201333.0A 2014-05-13 2014-05-13 Self-elevating platform pile leg mounting method Pending CN104805814A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410201333.0A CN104805814A (en) 2014-05-13 2014-05-13 Self-elevating platform pile leg mounting method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410201333.0A CN104805814A (en) 2014-05-13 2014-05-13 Self-elevating platform pile leg mounting method

Publications (1)

Publication Number Publication Date
CN104805814A true CN104805814A (en) 2015-07-29

Family

ID=53690984

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410201333.0A Pending CN104805814A (en) 2014-05-13 2014-05-13 Self-elevating platform pile leg mounting method

Country Status (1)

Country Link
CN (1) CN104805814A (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105586864A (en) * 2015-11-30 2016-05-18 中国国际海运集装箱(集团)股份有限公司 Method for folding self-lifting-type platform truss-type pile legs
CN105887789A (en) * 2016-06-20 2016-08-24 上海振华重工集团(南通)有限公司 Pile leg pile pitching technology of heavy lifting mechanism
CN107399412A (en) * 2016-05-19 2017-11-28 烟台中集来福士海洋工程有限公司 MOPU method of construction
CN111188324A (en) * 2019-12-26 2020-05-22 南通润邦海洋工程装备有限公司 Overwater folding process for offshore wind power installation platform lifting system
CN112504229A (en) * 2020-11-13 2021-03-16 中海油能源发展股份有限公司 System for monitoring state of mobile trial production platform
CN114132830A (en) * 2021-12-13 2022-03-04 上海振华重工启东海洋工程股份有限公司 Pile leg section displacement lifting construction method
CN114182710A (en) * 2021-12-17 2022-03-15 山海关船舶重工有限责任公司 Installation method of pile shoe of wind power installation platform
CN114808897A (en) * 2022-04-08 2022-07-29 山海关船舶重工有限责任公司 Method for installing pile leg of wind power installation platform by using gantry crane bearing crane
CN115450848A (en) * 2022-09-20 2022-12-09 烟台中集来福士海洋工程有限公司 Offshore installation system and offshore installation method of floating type wind turbine

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS584016A (en) * 1981-06-26 1983-01-11 Hitachi Zosen Corp Fabrication of legs for elevating type offshore working platform
JPS5833628A (en) * 1981-08-21 1983-02-26 Mitsui Eng & Shipbuild Co Ltd Supporting of offshore working platform
CN101144269A (en) * 2007-10-18 2008-03-19 大连船舶重工集团有限公司 Large-scale trussed-beam spud leg waterborne transmitting and mounting method
CN101636539A (en) * 2007-03-20 2010-01-27 西门子公司 jack-up platform
CN102168417A (en) * 2010-02-25 2011-08-31 烟台来福士海洋工程有限公司 Truss framed leg folding method of jack-up drilling platform
CN203462453U (en) * 2013-01-27 2014-03-05 江齐锋 Single rack spud leg complete cross section shutting tool

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS584016A (en) * 1981-06-26 1983-01-11 Hitachi Zosen Corp Fabrication of legs for elevating type offshore working platform
JPS5833628A (en) * 1981-08-21 1983-02-26 Mitsui Eng & Shipbuild Co Ltd Supporting of offshore working platform
CN101636539A (en) * 2007-03-20 2010-01-27 西门子公司 jack-up platform
CN101144269A (en) * 2007-10-18 2008-03-19 大连船舶重工集团有限公司 Large-scale trussed-beam spud leg waterborne transmitting and mounting method
CN102168417A (en) * 2010-02-25 2011-08-31 烟台来福士海洋工程有限公司 Truss framed leg folding method of jack-up drilling platform
CN203462453U (en) * 2013-01-27 2014-03-05 江齐锋 Single rack spud leg complete cross section shutting tool

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
黄曙光等: "陆地水平滑道建造自升式钻井平台滑移装船技术研究及应用", 《中国海上油气》 *

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105586864A (en) * 2015-11-30 2016-05-18 中国国际海运集装箱(集团)股份有限公司 Method for folding self-lifting-type platform truss-type pile legs
CN107399412A (en) * 2016-05-19 2017-11-28 烟台中集来福士海洋工程有限公司 MOPU method of construction
CN107399412B (en) * 2016-05-19 2019-11-01 烟台中集来福士海洋工程有限公司 The method of construction of MOPU
CN105887789A (en) * 2016-06-20 2016-08-24 上海振华重工集团(南通)有限公司 Pile leg pile pitching technology of heavy lifting mechanism
CN105887789B (en) * 2016-06-20 2018-02-02 南通振华重型装备制造有限公司 A kind of spud leg pitching pile technique of heavy lifting mechanism
CN111188324A (en) * 2019-12-26 2020-05-22 南通润邦海洋工程装备有限公司 Overwater folding process for offshore wind power installation platform lifting system
CN112504229A (en) * 2020-11-13 2021-03-16 中海油能源发展股份有限公司 System for monitoring state of mobile trial production platform
CN114132830A (en) * 2021-12-13 2022-03-04 上海振华重工启东海洋工程股份有限公司 Pile leg section displacement lifting construction method
CN114132830B (en) * 2021-12-13 2023-08-29 上海振华重工启东海洋工程股份有限公司 Pile leg section deflection lifting construction method
CN114182710A (en) * 2021-12-17 2022-03-15 山海关船舶重工有限责任公司 Installation method of pile shoe of wind power installation platform
CN114808897A (en) * 2022-04-08 2022-07-29 山海关船舶重工有限责任公司 Method for installing pile leg of wind power installation platform by using gantry crane bearing crane
CN114808897B (en) * 2022-04-08 2024-05-31 山海关船舶重工有限责任公司 Method for installing pile legs of wind power installation platform by gantry crane bearing crane
CN115450848A (en) * 2022-09-20 2022-12-09 烟台中集来福士海洋工程有限公司 Offshore installation system and offshore installation method of floating type wind turbine

Similar Documents

Publication Publication Date Title
CN104805814A (en) Self-elevating platform pile leg mounting method
CN103332269B (en) Backpack complete offshore wind power machine transport installation ship
CN111661273B (en) Installation and construction method of a deep-sea semi-submersible fan
CN109629568A (en) The process for sinking of the steady stake platform of offshore wind farm jacket foundation steel pipe pile floating
CN111469993A (en) Self-installation floating type fan foundation anchored by bucket foundation and self-installation method
CN202007400U (en) Marine foundation construction platform for jacket construction
CN203393714U (en) Precisely positioned offshore piling guide frame
CN106014874B (en) How to install offshore wind turbines
CN114856919B (en) A method for hoisting a conductor frame using a fully revolving crane vessel
CN104727336A (en) Construction method of large single-pipe pile foundation of shallow-sea wind power plant
CN104229066B (en) A kind of ship mooring localization method
CN104032765A (en) Shallow sea wind power plant rock-socketed monopile foundation construction method
KR20140109248A (en) A vessel and a method for installing or repairing an offshore structure
CN112726622A (en) Method for overturning large-diameter single pile of fixed-boom crane ship
CN101144269A (en) Large-scale trussed-beam spud leg waterborne transmitting and mounting method
CN115584727A (en) Offshore Construction Method of Super Large Single Pile
CN103215956B (en) Multi-pile pile gripper and multi-pile guide pipe frame foundation construction method for shallow wind power farm
CN105523477B (en) A kind of method that spud leg pile extension is carried out using 3000t crane barges
CN206485522U (en) A kind of floating power station piled anchor system
CN102923261A (en) A bottom-mounted offshore wind turbine installation barge
CN112850488A (en) Method for overturning steel pipe pile of fixed-boom crane ship
CN204702437U (en) A kind of build-up type power pontoon combination mast crane device
CN115637724A (en) A low-cost installation method for suction barrel jacket
CN105692449A (en) Method for spud leg lengthening and folding of self-elevating drilling platform
CN105586864A (en) Method for folding self-lifting-type platform truss-type pile legs

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
EXSB Decision made by sipo to initiate substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20150729

WD01 Invention patent application deemed withdrawn after publication