[go: up one dir, main page]

AU684955B2 - Installation of an oil storage tank - Google Patents

Installation of an oil storage tank Download PDF

Info

Publication number
AU684955B2
AU684955B2 AU24930/95A AU2493095A AU684955B2 AU 684955 B2 AU684955 B2 AU 684955B2 AU 24930/95 A AU24930/95 A AU 24930/95A AU 2493095 A AU2493095 A AU 2493095A AU 684955 B2 AU684955 B2 AU 684955B2
Authority
AU
Australia
Prior art keywords
construction
buoy
pay out
seabed
installation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Ceased
Application number
AU24930/95A
Other versions
AU2493095A (en
Inventor
Morten Diesen
Lars Friisk
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kvaerner AS
Original Assignee
Kvaerner AS
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kvaerner AS filed Critical Kvaerner AS
Publication of AU2493095A publication Critical patent/AU2493095A/en
Application granted granted Critical
Publication of AU684955B2 publication Critical patent/AU684955B2/en
Anticipated expiration legal-status Critical
Ceased legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D23/00Caissons; Construction or placing of caissons
    • E02D23/08Lowering or sinking caissons

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Laying Of Electric Cables Or Lines Outside (AREA)
  • Revetment (AREA)

Description

Our Ref: 558513 P/00/011 Regulation 3:2
AUSTRALIA
Patents Act 1990
ORIGINAL
COMPLETE SPECIFICATION STANDARD PATENT ro s r sc o r orr a o s Applicant(s): Address for Service: Invention Title: Kvaerner a.s.
P O Box 100 Skoyen N-0212 OSLO
NORWAY
DAVIES COLLISON CAVE Patent Trade Mark Attorneys Level 10, 10 Barrack Street SYDNEY NSW 2000 Installation of an oil storage tank The following statement is a full description of this invention, including the best method of performing it known to me:- 5020 Installation of an oil storage tank The invention concerns a method for installation of a subsea construction with ballast tanks, typically a storage tank for oil, on the seabed, wherein the construction is ballasted until it floats at a suitable depth in the water, and is towed to the field by means of tugs.
It is a known procedure to instal constructions on the seabed by towing the construction to the position in which is has to be installed by means of one or more tugs, ballasting the construction and lowering it by means of crane ships and/or winches. The drawback with this method, however, is that it requires relatively large crane and/or winch capacity, which entails major expenses.
Moreover, substantial dynamic forces can be transferred both to the construition, the wires, the crane ship and/or the tugs, especially in bad weather conditions, thus increasing the capacity demands on these.
i: US patent specification No. 4 909 671 describes an installation of a construc- S: 15 tion on the seabed in which the construction is connected to a buoy, typically with wires, of a predetermined length. The construction is ballasted so that it .is given a desired vertical sinking velocity, whereupon it will sink to a predetermined depth at a suitable height above the seabed, determined by the length of the wires and the buoyancy of the buoy. The final lowering is performed by ballasting the buoy, the subsea construction, or both.
**US patent specification No. 5 215 410 describes an installation of a construction on the seabed in which weights are attached to the construction, these weights being suspended below the construction, preferably in the form of belts with weights. If the construction itself does not have built-in 25 buoyancy tanks/ballast tanks, it is positioned below a buoyant member with such tanks. The construction is lowered by ballasting the buoyancy tanks, either in the actual construction or in the buoyant member. When the weights reach the bottom the forces from the weights on the construction will be reduced, thus stopping the lowering process and the construction is stabilized at a specific distance from the seabed. The final part of the submersion 4 performed by further ballasting, thus ensuring a steady and controlled lowering of the construction.
During the submersion of bodies in the water, the increase in the static pressure will cause the construction to be compressed, thus reducing the volume of the construction. According to Archimedes' law, which states that a body submerged in a fluid acquires a buoyancy which is equal to the weight of the volume of fluid it displaces, the buoyancy will consequently also be reduced. In most cases this can be disregarded, but during the installation of large constructions at great depths it is extremely pronounced, and can mean that the buoyancy of the construction is reduced by several hundreds of tons as it is lowered to the bottom.
This means that installations based on the two above-mentioned U.S. patents will encounter problems in the installation of large constructions at great depths, since in both cases the construction's lowering rate will increase as the construction moves downwards. This can be counteracted by a continuous or gradual deballasting of the construction, which, however, is difficult to achieve in practice. A continuous deballasting of this kind will require .constant connection of an umbilical, which will constitute a risk, and will probably make further measures necessary in order to maintain the safety of the operation.
.i With a submersion operation according to the prior art, represented by the patents mentioned in the introduction, the construction's lowering rate is exclusively a consequence of the balance between buoyancy and ballasting, which means that the movement can only be stopped by deballasting. Due to the inertia of the construction this will take a very long time or require a considerable amount of over-deballasting. If the deballasting continues right S 25 up until the construction stops, the construction will turn and move upwards.
The construction will therefore be very difficult to stop, as countercorrections will have to be carried out over and over again. Thus an active S" ballasting system is necessary, and an advanced control system which observes when the acceleration is turning, thus enabling the deballasting to be stopped in time.
Weather conditions will always be critical for offshore operations, including for the installation of subsea constructions according to known methods, where the entire operation is dependent on the fact that wave height and wind speed do not exceed stated maximum values.
I':\WP'DOCSflYSSPI3CIE\493O. 3t/S/9 -3- An object of the present invention is to provide an improved method of installing subsea construction which alleviates one or more of the foregoing problems.
According to the present invention there is provided a method for the installation of a subsea construction, the construction including one or more ballast tanks having valves for controlling the ingress or egress of ballast therefrom, the method being for use with sea vessels having pay out lines which can be paid out therefrom and a buoy, said pay out lines being operatively connected to the buoy, the method including the steps of: 10 a) ope:atively connecting the construction to the pay out lines between the sea vessel and the buoy so that it can be carried thereby so that there can be relative movement between the construction and the pay out line along the pay out line;
S
b) supplying ballast to the construction until it is a selected weight and sinks from a position in which it is at or generally adjacent the water level to a selected depth below the water level where it is supported by the pay out lines; S c) lowering the construction by means of the pay out lines until it is a selected lhight above the seabed; and d) supplying further ballast so that the construction is caused to sink to the seabed whereafter the pay out lines are removed.
In one preferred form of the invention at least one of the pay out lines extends between one of the sea vessels and a fixed installation. The constuction and the buoy are operatively connected to the pay out line so that there is relative movement between the construction and, the pay out line and the buoy and the pay out line along the pay out line.
Preferably, the buoy is generally oblong in shape and when in use, disposed with its longitudinal axis generally upright, thereby providing spring-like characteristics during the lowering of the construction.
I:AWIDOCSDY-SOPlCImM3'95 -161 -3a- In one preferred form there is provided an additional step prior to the final ballasting step and after the initial lowering step using the pay lines wherein the construction is deballasted so as to provide a general state of equilibrium.
In one preferred form the final phase of the lowering down to the seabed is performed by ballasting the construction. In another preferred form the final phase of the lowering down to the seabed is performed by ballasting the buoy.
Preferably, the pay out lines are operatively connected to the constrztion by pulleys 10 and one embodiment the pay out line is operatively connected to the buoy by pulleys.
0 Advantages of the invention in its various preferred forms are set out below.
o By using a buoy, and with the wires running from the buoy to the tugs via pulleys on the construction, the buoy which is positioned above the construction will be able to absorb vertical forces as great as those absorbed by the tugs, thereby relieving them of some of the 0 strain. This means that the buoy reduces the tugboat capacity required with regard to vertical forces.
0 o 'The buoy causes the forces to be centred at a point which lies vertically directly above the construction, thus achieving a simpler positioning than if only tugs had been used.
The buoy will act as a spring element, absorbing most of the tugs' heaving movement, thus preventing these movements from being transferred to the construction. In designing the buoy, account must be taken of rigidity and mass, in such a manner that the interplay of buoy/boat results in as small dynamic loads in the wires as possible. In ballasting the buoy it will also be possible to optimize the dynamic properties with regard to the installation concerned. This means easier vertical manoeuvring and reduced dynamic stresses on the construction, wires and tugboats in comparison with a lowering process where crane ships or winches alone are employed.
The buoy will naturally be hollow inside, which means that it can easily be equipped with ballast tanks. The ballast tanks can be used for fine adjustment of vertical position during the final phase of the lowering of the construction, where the construction is placed on the bottom.
The buoy is reasonable to produce compared to the costs involved in extra tugboat capacity, and if the conditions are favourable the buoy can be employed in other similar marine operations, since it can be calibrated for the individual installation by means of pre-ballasting.
By means of a lowering process according to the present invention the construction will be ballasted before submersion by admitting water until it has reached a predetermined weight of, 25-50 tons. This starting weight is dependent on the extent to which the construction is compressed due to S 15 the pressure increase during lowering, as well as the density profile for sea water at the installation site.
oo .I :If the ballasting of the construction is controlled by means of an umbilical, this will be disconnected and remain disconnected right up until the lowering is stopped at a suitable height above the seabed. Critical balance in the 20 ballasting is avoided during installation, since the increased tension in the wires, due to reduced buoyancy as a result of compression of the construction, is absorbed by the buoy/tug.
If the weight of the construction after ballasting is, 25 tons and the capacity of the winch is 100 tons, an effective braking power of 75 tons is S 25 obtained. The result of this is that the velocity of the construction can be braked at any time causing it to stop, which means that it is completely under control during the entire lowering process. Compared with the known methods, represented by the patents mentioned in the introduction, in which an active ballasting system with an advanced control system is required, a completely different degree of controllability is thus obtained during the lowering process.
It should also be mentioned that a method for installation of a subsea construction according to the invention will be less dependent on the weather conditions than known methods, the construction being capable of lying in a completely submerged state awaiting acceptable weather before lowering starts.
The above-mentioned factors indicate a substantial saving in costs compared with known methods, in which a buoy is not employed.
I n o ric0, e 2 a The invention will now be described in more detail by means of the drawing which illustrates the method according to the invention used during installation of a storage tank for oil on the seabed, and in which: fig. 1 is a plan view of the tank and three tugs, and fig. 2 is a side view of the tank with three tugs and the buoy, where the tank is located immediately below the surface, and fig. 3 is a side view of the tank with two tugs and the buoy, where the tank is 15 installed on the seabed.
A typical area of application for the present invention will be a storage tank for oil which is installed on the seabed. Figure 1 illustrates such a storage tank 1 with six cells 2. The three cells in the middle have compressive strength and are used for ballasting, while the three external cells lack S 20 compressive strength, and are open to the water, thereby always having the same pressure as the water. In this context compressive strength )r lack of compressive strength refer to whether the cells are designed to withstand the oeooo pressure difference which arises between the cells and the environment during the lowering of the tank due to the increase in the hydrostatic pressure.
Figure 1 shows two tugboats 3 which keep the storage tank 1 in place in the surface position by means of the wires 4. The buoy 5 is not connected here.
The wires pass directly from the tugs to the tank's wire fastenings, and will normally be the same wires which are used during the towing. A third tugboat 6 is in the process of ballasting the tank by means of an umbilical 7.
Figure 2 shows the storage tank 1 15-20 metres below the surface, where it is suspended from the wires 8 which run from the tugboats 3 to pulleys on the tank 1, and on to the buoy 5. Here the tank has been ballasted to a weight of approximately 50 tons. The umbilical 7 is disconnected and will remain disconnected during the lowering process.
The actual lowering is performed by the tugs paying out wires, thus causing the tank to be lowered.
Figure 3 shows the storage tank in the process of being placed on the seabed.
As will be evident from the patent claims, this final part of the operation can be performed in several ways. If the wave motion is moderate, and the requirements with regard to positioning and lowering rate permit it, the final part of the lowering can also be performed by means of the wires. In the event of high waves, and if greater accuracy is required during the final phase of the installation, the final part of the lowering can be performed by 15 deballasting the tank until the tension in the wires is reduced, thus stabilizing the construction by means of the balance between its specific weight, buoyancy and the forces from the buoy and the tugs. One is then faced by two possibilities: either to ballast the tank or to ballast the buoy, thus enabling the tank to sink slowly and in a controlled manner to the bottom.
20 Once it is installed on the bottom the ballasting valves are opened, resulting in an increase in the weight of the tank and causing it to sink into the seabed.
The wires are than removed.
e It will be seen that many modifications are possible within the scope of the invention. For example the number of tugs can vary, the number and size of 25 the tugs naturally being selected from what is the most favourable option ooaeo S"economically for the installation concerned. If the buoy is also equipped with pulleys, it will be possible to replace one of the tugs with a fixed installation.
The wires will then be attached in the fixed installation, pass via a pulley on the subsea construction to the buoy, from there via a pulley down again to the subsea construction, and via a pulley to the tugboat's winch. This method could be feasible for an installation in the vicinity of an oil platform, where the use of a tugboat close to the platform can be undesirable for safety reasons.
The greatest possibility of variation will probably be associated with the buoy. The shape, size and possibility of ballasting of the buoy can be varied in a number of different ways. The most obvious shape for the buoy is a vertical cylindrical shape, where the spring constant will be linear, and dependent of the slenderness, i.e. the ratio between length ap diameter. A conical form can also be envisaged, which will give a spring constant which increases progressively with the buoy's draught.
These examples of modifications will all lie within the scope of the invention, since, as mentioned above, the essential feature of the invention is the use of the buoy, in that it is connected to the subsea construction by means of wires, which via pulleys on the subsea construction pass on to the tugs.
o o

Claims (9)

1. A method for the installation of a subsea construction, the construction including one or more ballast tanks having valves for controlling the ingress or egress of ballast therefrom, the method being for use with sea vessels having pay out lines which can be paid out therefrom and a buoy, said pay out lines being operatively connected to the buoy, the method including the steps of: a) operatively connecting the construction to the pay out lines between the sea vessel and 10 the buoy so that it can be carried thereby so that there can be relative movement between the construction and the pay out line along the pay out line; b) supplying ballast to the construction until it is a selected weight and sinks from a position in which it is at or generally adjacent the water level to a selected depth below the water level where it is supported by the pay out lines; c) lowering the construction by means of the pay out lines until it is a selected height above the seabed; and d) supplying further ballast so that the construction is caused to sink to the seabed whereafter the pay out lines are removed.
2. A method according to claim 1 wherein at least one of the pay out lines extends between one of the sea vessels and a fixed installation, said construction and said buoy being operatively connected to the pay out line so that there is relative movement between the construction and the pay out line and the buoy and the pay out line along the pay out line.
3. A method for installation of a subsea construction on the seabed according to claim 1, or claim 2 wherein said buoy is generally oblong in shape and when in use, disposed with its longitudinal axis generally upright, said buoy providing spring-like characteristics during qa I Ij_ I I':\WI'IIO(:~7DY:i~S1'IY, llFa4130,P~ JI~N4 -9- the lowering of the construction.
4. A method for installation of a subsea construction on the seabed according to any preceding claim wherein prior to the final ballasting step and after the initial lowering step using the pay lines, the construction is deballasted so as to provide a general state of equilibrium.
A method for installation of a subsea construction on the seabed according to any preceding claim wherein the final phase of the lowsring down to the seabed is performed by 10 ballasting the construction.
6. A method for installation of a subsea construction of the seabed according to any one of claims 1 to 4 wherein the final phase of the icwering down to the seabed is performed by Sballasting the buoy.
7. A method according to any preceding claim wherein the pay out lines are operatively connected to tte construction by pulleys.
8. A method according to claim 2, wherein the pay out line is operatively connected to the buoy by pulleys.
9. A method of installing a subsea construction substantially as hereinbefore described with reference to the drawings. DATED this 31st day of May, 1996. KVAERNER A.S. By Its Patent Attorneys DAVIES COLLISON CAVE r ~g -L SUMMARY A subsea construction with ballast tanks, typically a storage tank for oil, is installed on the seabed by connecting the construction to a buoy and two or more tugboats by means of wires which are attached to the buoy and run from there to pulleys on the construction and on to the tugs. The construction is ballasted until it has a suitable weight, typically 50 tons, and is lowered to a depth at a suitable height above the seabed by paying out wires from winches on the tugs. The construction is lowered the final distance to the seabed by ballasting the construction. Fig. 3 e o0 0 0 o* -r I-'1 C~C
AU24930/95A 1994-07-13 1995-07-11 Installation of an oil storage tank Ceased AU684955B2 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
NO942635 1994-07-13
NO942635A NO305608B1 (en) 1994-07-13 1994-07-13 Procedure for the installation of an underwater structure

Publications (2)

Publication Number Publication Date
AU2493095A AU2493095A (en) 1996-04-04
AU684955B2 true AU684955B2 (en) 1998-01-08

Family

ID=19897261

Family Applications (1)

Application Number Title Priority Date Filing Date
AU24930/95A Ceased AU684955B2 (en) 1994-07-13 1995-07-11 Installation of an oil storage tank

Country Status (3)

Country Link
AU (1) AU684955B2 (en)
GB (1) GB2291090A (en)
NO (1) NO305608B1 (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB2464714B (en) 2008-10-24 2010-09-08 Subsea Deployment Systems Ltd Method and apparatus for subsea installations
FR3093316B1 (en) * 2019-03-01 2021-03-12 Naval Energies Method of operating a submerged technical center structure, in particular a data center
CN112487529B (en) * 2020-11-26 2024-01-02 广州打捞局 Pipe joint bottom setting and depositing method

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB2206628A (en) * 1987-06-05 1989-01-11 Conoco Inc Method of installing a template on the seafloor
US4909671A (en) * 1987-05-14 1990-03-20 Norwegian Contractors A/S Method for installation of a buoyant body on a sea bottom
US5215410A (en) * 1990-08-14 1993-06-01 Norwegian Contractors Method and means for controlled submersion and positioning of large, heavy gravity elements on the sea bottom

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
NO169530C (en) * 1988-07-01 1992-07-08 Norwegian Contractors DEVICE FOR SINGLE-SHIPPING AND INSTALLATION OF SEALS

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4909671A (en) * 1987-05-14 1990-03-20 Norwegian Contractors A/S Method for installation of a buoyant body on a sea bottom
GB2206628A (en) * 1987-06-05 1989-01-11 Conoco Inc Method of installing a template on the seafloor
US5215410A (en) * 1990-08-14 1993-06-01 Norwegian Contractors Method and means for controlled submersion and positioning of large, heavy gravity elements on the sea bottom

Also Published As

Publication number Publication date
GB9513759D0 (en) 1995-09-06
GB2291090A (en) 1996-01-17
NO305608B1 (en) 1999-06-28
AU2493095A (en) 1996-04-04
NO942635L (en) 1996-01-15
NO942635D0 (en) 1994-07-13

Similar Documents

Publication Publication Date Title
US5609442A (en) Offshore apparatus and method for oil operations
US6206614B1 (en) Floating offshore drilling/producing structure
US4995762A (en) Semisubmersible vessel with captured constant tension buoy
US6652192B1 (en) Heave suppressed offshore drilling and production platform and method of installation
US4784529A (en) Mooring apparatus and method of installation for deep water tension leg platform
US4966495A (en) Semisubmersible vessel with captured constant tension buoy
JP5264593B2 (en) Fixing bottom member, tension mooring float system and installation method thereof
US5054415A (en) Mooring/support system for marine structures
RU2141427C1 (en) Low-draft floating drilling and oil production off-shore platform (versions)
EA020375B1 (en) Method for lowering a load to the bed of a body of water and apparatus therefor
US20030031517A1 (en) Floating, modular deepwater platform and method of deployment
CA1307171C (en) Mooring apparatus and method of installation for deep water tension leg platform
US20040182297A1 (en) Riser pipe support system and method
JP2025508101A (en) Marine structure and method
US8813670B2 (en) Floating structure
USRE32119E (en) Mooring and supporting apparatus and methods for a guyed marine structure
EP0311398A1 (en) Mooring apparatus for deep water tension leg platform
AU684955B2 (en) Installation of an oil storage tank
GB2344574A (en) Floating heavy lift vessel with stabilizing suction anchors
US4834014A (en) Floating platform structure
EP1725447B1 (en) Floating structure
KR20010108376A (en) System with a guide frame for petroleum production risers; a guide frame for risers; riser buoyancy elements and a semi-submersible production platform
CN100384691C (en) mooring system
US7422394B2 (en) Tendon for tension leg platform
JPH06219372A (en) Mooring method for floatable and sinkable floating body

Legal Events

Date Code Title Description
MK14 Patent ceased section 143(a) (annual fees not paid) or expired