AU2010252013B2 - Offshore structure and mooring arrangement - Google Patents

Offshore structure and mooring arrangement Download PDF

Info

Publication number
AU2010252013B2
AU2010252013B2 AU2010252013A AU2010252013A AU2010252013B2 AU 2010252013 B2 AU2010252013 B2 AU 2010252013B2 AU 2010252013 A AU2010252013 A AU 2010252013A AU 2010252013 A AU2010252013 A AU 2010252013A AU 2010252013 B2 AU2010252013 B2 AU 2010252013B2
Authority
AU
Australia
Prior art keywords
mooring
fairlead
offshore structure
hook
metres
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
AU2010252013A
Other versions
AU2010252013A1 (en
Inventor
Philip Ian Jameson
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shell Internationale Research Maatschappij BV
Original Assignee
SHELL INT RESEARCH
Shell Internationale Research Maatschappij BV
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHELL INT RESEARCH, Shell Internationale Research Maatschappij BV filed Critical SHELL INT RESEARCH
Publication of AU2010252013A1 publication Critical patent/AU2010252013A1/en
Application granted granted Critical
Publication of AU2010252013B2 publication Critical patent/AU2010252013B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B21/00Tying-up; Shifting, towing, or pushing equipment; Anchoring
    • B63B21/50Anchoring arrangements or methods for special vessels, e.g. for floating drilling platforms or dredgers
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B21/00Tying-up; Shifting, towing, or pushing equipment; Anchoring
    • B63B21/50Anchoring arrangements or methods for special vessels, e.g. for floating drilling platforms or dredgers
    • B63B2021/505Methods for installation or mooring of floating offshore platforms on site
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B22/00Buoys
    • B63B22/02Buoys specially adapted for mooring a vessel
    • B63B2022/028Buoys specially adapted for mooring a vessel submerged, e.g. fitting into ship-borne counterpart with or without rotatable turret, or being releasably connected to moored vessel

Landscapes

  • Chemical & Material Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • Combustion & Propulsion (AREA)
  • Mechanical Engineering (AREA)
  • Ocean & Marine Engineering (AREA)
  • Filling Or Discharging Of Gas Storage Vessels (AREA)

Abstract

Offshore structure comprising an outer hull having longitudinal sides and at least one fairlead located adjacent a longitudinal side, and a hook, connected to the structure and located inboard relative to the fairlead and being displaced along the hull longitudinally from the fairlead, such that an angle of displacement between a tangent to the outer hull at the centre of the fairlead and the hook, is less than or equal to 45°.

Description

WO 2010/136444 PCT/EP2010/057142 - 1 OFFSHORE STRUCTURE AND MOORING ARRANGEMENT The present invention relates to an offshore structure and a mooring arrangement. Such an offshore structure may be used to produce hydrocarbon fluids from a subsea or underwater well and 5 to process these fluids into a transportable form. In some cases, e.g. when a pipe line is not technically and/or commercially feasible, the processed hydrocarbon fluids need to be transferred into a tanker ship for transportation away from the offshore structure to a 10 receiving site. In case of natural gas, for instance, the gas may be first liquefied to produce LNG in which form it can be transported by an LNG tanker, generally referred to as an LNG carrier (LNGC). Alternatively, such an offshore structure may be used 15 to receive hydrocarbon fluids that have been transported by a carrier ship from elsewhere, and optionally store and/or process the received hydrocarbon fluids. Liquefied natural gas ("LNG") is produced when natural gas is cooled to a cold, colourless liquid at 20 -1600C (-256 0 F) . Storage of LNG requires much less volume for the same amount of natural gas. A number of storage tanks have been developed to store LNG in cryogenic form. In order to use LNG as a power source, the LNG is converted to its gaseous state using a re-vaporisation 25 process. The re-vapoured LNG can then be distributed through pipelines to various end users. One advantage of LNG is that LNG may be transported by ship to markets further than would be practical with pipelines. The ability of produce LNG offshore and to 30 bring it onto a transport carrier allows for exploitation of gas reservoirs that would otherwise be too far removed WO 2010/136444 PCT/EP2010/057142 -2 from consumers of natural gas. Importing LNG by ships has led to the establishment of LNG storage and re vaporisation facilities at on-shore locations that are close to shipping lanes. There is also a desire in the 5 industry to provide offshore capabilities for receiving LNG and LPG products from a transport carrier. As an example, WO 2006/052896 discloses a floating LNG storage and regasification unit ("FSRU"). Both types of offshore structures described above may 10 advantageously employ a mooring arrangement in order to enable mooring of carrier ships to the offshore structure during loading and/or offloading of the hydrocarbon fluid(s). In W02006/101395 a mooring arrangement is provided on 15 an offshore structure, for mooring a tanker vessel alongside of the offshore structure. The mooring arrangement uses a quick release coupling hook. The mooring lines are rather short because of the small distance of the side-by-side mooring geometry compared to 20 mooring on-shore on a jetty. A relatively short nylon rope can be used in view of an extendable shock absorber that is provided on the hook in the form of a hydraulic cylinder and an extendable arm. The mooring lines may bend around guide means which are located on the deck of 25 the tanker vessel, and opposite ends of the mooring lines are directly attached to the shock absorbers on the offshore structure. US-2008/0295526 discloses a floating LNG terminal comprising a mooring turret, an LNG storage vessel and a 30 regasification vessel. An LNG carrier vessel may be docked adjacent the regasification vessel. A disclosed technique for docking the LNG carrier vessel uses mooring lines to connect the LNG carrier vessel to the 3 regasification vessel. Said mooring lines are located on the carrier vessel, and may bend around guide means which are located on the deck of the carrier vessel. The ends of the mooring lines are directly attached to the regasification vessel. FR-2916732 discloses a floating LNG production vessel and a carrier vessel which is moored adjacent to the LNG production vessel using mooring lines. Said mooring lines are located on the carrier vessel, and the ends of the mooring lines are directly attached to the LNG production vessel. US-2007/0289517 discloses a more elaborate mooring system for mooring a carrier vessel adjacent a floating LNG regasification vessel. The LNG regasification vessel is provided with a plurality of fenders to maintain a predetermined distance between the vessels. The carrier vessel is attached to a mooring arm at the bow of the regasification vessel. A hawser extends from a winch on the carrier vessel, via a sheave on the end of the mooring arm to a winch on the regasification vessel. The winch functions as a force element to maintain a constant tension. The above-described offshore mooring systems all differ substantially with respect to onshore mooring systems, which typically comprise a jetty and a mooring line arrangement. Such jetties are for instance manufactured by Harbour & Marine Engineering Pty Ltd. Besides being equipped to dock at onshore jetties, carriers therefore have to be adapted for each respective offshore mooring system. It is an aim of the present invention to substantially improve upon the prior art mooring systems, at least to an extent. In a first aspect, the present invention provides an offshore structure comprising an outer hull having longitudinal sides and at least one fairlead located adjacent a longitudinal side, and a hook, connected to the structure and located inboard relative to the fairlead and being displaced along the hull longitudinally from the fairlead, such that an angle of displacement (oc) between a tangent to the outer hull at the centre of the fairlead and the hook, is less than or equal to 450. In an embodiment, the offshore structure may comprise a plurality of fairleads and associated hooks, the fairleads being spaced along the outer hull and being configured so as to provide mooring points for a transport carrier, each hook being located inboard relative to the associated 4 fairlead and being displaced along the hull longitudinally from the fairlead. Preferably, the displacement of each hook with respect to the associated fairlead is suitable to accommodate the length of a mooring line of an onshore mooring system. The offshore mooring system of the invention is therefore suitable for mooring typical tanker vessels, thus obviating additional shock absorbing systems or further modification. In a second aspect, the present invention provides a mooring arrangement comprising at least one mooring line having a pennant at an end thereof, and an offshore structure according to the first aspect of the invention, wherein the at least one mooring line is configured to pass inboard of the outer hull through the fairlead and is attachable to the hook such that the angle of displacement of the at least one mooring line between the WO 2010/136444 PCT/EP2010/057142 -5 tangent to the hull at the centre of the fairlead and the hook is less than or equal to 45'. The present invention and its advantages will now be further illustrated by means of examples and with 5 reference to the drawing wherein: Figure 1 shows a schematic plan view of an offshore structure in which the positioning of the fairlead and hook relative to the longitudinal sides of the structure are depicted; 10 Figure 2 shows a schematic plan view of a section of a mooring deck of the offshore structure of Figure 1; Figure 3 shows a cross-sectional representation of an offshore structure according to an embodiment of the invention in which the mooring deck is located within the 15 outer hull and is bounded by the hull; Figure 4 shows a schematic representation of a mooring arrangement according to an embodiment of the invention; Figure 5a shows a schematic representation of a 20 mooring arrangement with mooring points A to P in operation mooring a LNGC; Figure 5b shows a schematic representation of the mooring layout of Figure 5a in operation mooring a further LNGC; 25 Figure 6a shows a schematic representation of the mooring layout of Figure 5a in operation mooring a LPGC; Figure 6b shows a schematic representation of the mooring layout of Figure 5a in operation mooring a further LPGC; and 30 Figure 7 shows a schematic representation of a mooring arrangement of the invention for an LNGC mooring position relative to an offshore structure in the form of an FLNG.
WO 2010/136444 PCT/EP2010/057142 -6 Although the invention will be described in terms of specific embodiments, it will be understood that various elements of the specific embodiments of the invention will be applicable to all embodiments disclosed herein. 5 An improved mooring arrangement for mooring a transport carrier to an offshore structure, which offshore structure is typically deployed in a body of water, is proposed. The mooring arrangement is particularly suitable for application on an offshore 10 liquefied natural gas production unit and/or an offshore liquefied petroleum gas production unit. The offshore structure may be a floating structure, preferably moored in a weathervaning arrangement, which facilitates the mooring procedure of the transport carrier to the 15 offshore structure. Figure 1 depicts an embodiment of an offshore structure incorporating an embodiment of the invention. The offshore structure, in some embodiments, may be a floating liquefied natural gas production unit ("FLNG"). 20 In other embodiments, the offshore structure is a liquefied petroleum gas production unit ("FLPG"). Often, the offshore structure produces both liquefied natural gas (LNG) as well as liquefied petroleum gases (LPG) and/or other condensate(s). For the purpose of this 25 specification, any floating unit producing LNG and/or LPG will be referred to as an FLNG/FLPG structure. The invention may also be incorporated in an offshore structure capable of receiving of, and optionally storing and/or processing of, LNG or LPG or other hydrocarbon 30 fluids from a transport carrier. An example of such a unit for receiving, storing and regasification of LNG is a floating storage regasification unit ("FRSU").
WO 2010/136444 PCT/EP2010/057142 -7 The offshore structure is intended to allow transport carriers, such as for instance LNG and/or LPG carriers (LNGC and/or LPGC), to berth directly alongside the structure and unload and/or load hydrocarbon fluids such 5 as LNG and/or LPG. Such a LNGC or LPGC may be moored alongside the starboard side of the offshore structure, optionally with Yokohama floating fenders protecting each of the (steel) hulls from contact with one another. Mooring of an LNGC or a LPGC with the offshore structure 10 may be accomplished using mooring lines. The mooring lines are deployed from the LNGC/LPGC to the offshore structure, so that the carrier and the offshore structure can be moored alongside one another for transfer of the hydrocarbon fluids. 15 In the present example, the offshore structure 1 will be referred to as FLNG/FLPG structure 1 although the basic principles of the invention are not limited to this type of offshore structure. The FLNG/FLPG structure 1 has an outer hull having two longitudinal sides 2. Bow and 20 stern sections join the longitudinal sides 2 to from the outer perimeter of the outer hull. Although not necessary for the invention, the outer hull, when viewed in cross section from above, is in this particular embodiment a substantially oblong structure, with two parallel 25 longitudinal sides 2, and curved bow 12 and stern 13 sections. In alternative embodiments, the stern and/or bow sections may for instance be a straight hull section between the longitudinal sides of the structure. The FLNG/FLPG structure 1 may be moored at a mooring 30 point, for instance in the form of a turret 17, at the bow 12. Preferably, the FLNG/FLPT structure 1 is capable of weathervaning around the mooring point.
WO 2010/136444 PCT/EP2010/057142 -8 At least one fairlead 3 is positioned adjacent a longitudinal side 2. A hook 4 is connected to the structure 1 and located inboard relative to the fairlead 3 such that the angle of displacement a between a tangent 5 to the outer hull 5 at the centre of the fairlead 3 and the hook 4 is less than or equal to 45'. Selecting the angle of displacement to be less than or equal to 45', allows for using longer mooring lines than is the case in a conventional alongside offshore 10 mooring arrangement, whilst the offshore mooring arrangement consumes considerably less lateral depth between the fairlead and the hook. Herewith it is possible to avoid needing a special hook with shock absorbing properties, or at least to reduce the shock 15 absorbing capacity, because the mooring line can be long enough to absorb shocks in the conventional way. Conventional way herein refers to onshore mooring systems using a jetty, wherein the mooring lines have a predetermined length which is long enough to enable the 20 mooring lines, due to their intrinsic elasticity, to absorb shocks, thus obviating additional shock absorbers. The offshore mooring system of the present invention enables the use of mooring lines which have the same predetermined length as the mooring lines for onshore 25 mooring, as the mooring lines extend past the fairlead or guides onboard the vessel. The hooks are located at a predetermined distance from the guides, so that the total length of the mooring lines is similar to the predetermined length of the mooring lines for the onshore 30 mooring system. The saving in lateral space between the fairlead and the hook may translate in reducing the inboard space required for the mooring deck within the limits of the WO 2010/136444 PCT/EP2010/057142 9 outer hull of the structure, which is particularly welcome for an FLNG/FLPG structure or an FSRU structure since the deck space is needed for top sides hydrocarbon processing equipment. Alternatively, the space saving may 5 be translated in reducing the need for outboard space (i.e. protruding out of the perimeter of the hull), which is considered to enhance the safety during approach operations of a transport carrier to the offshore structure. 10 Further still, by providing for a greater line length inboard of the fairlead over conventional mooring arrangements, the offshore mooring arrangement of the invention emulates the stability of an on-shore mooring arrangement within a more limited special environment. An 15 angle of displacement less than 450 allows for a longer pennant than in prior known offshore mooring systems, thereby allowing the offshore mooring arrangement to more closely resemble an onshore mooring arrangement in which a more secure mooring is provided due to the longer 20 pennant length applicable to the mooring arrangement. When referred to herein, the "pennant" is the tail end of a mooring line or rope. The tail end of the mooring line or rope is the end which is attachable to the hook on the offshore structure or a hook on a 25 liquefied natural gas carrier and/or a liquefied petroleum gas carrier. In a preferred embodiment, the pennant is reinforced over a predetermined length to withstand friction between the pennant and the respective fairlead. The reinforcement of the pennant comprises for 30 instance a protective coating or liner. The predetermined length covered with a protective liner exceeds the length of protective liners applied in onshore mooring systems, WO 2010/136444 PCT/EP2010/057142 - 10 to cover the displacement between the fairleads and the associated hooks of the present invention. Preferably, the distance from the centre of the fairlead to the hook is in the range of from 10 to 22 5 metres. This exceeds the distance of conventional offshore mooring arrangements, which rely on an 11 metre pennant length and therefore typically do not employ hooks in excess of 10 m away from the fairlead. The additional available length in excess of 10 m is 10 advantageous for shock absorbing as in offshore alongside mooring the length that need to be bridged by the mooring lines from the offshore structure to the transport carrier is relatively small. An inboard length of about 15 m is typically recommended, i.e. the distance from the 15 centre of the fairlead to the hook is preferably about 15 m. The angle of displacement a( is preferably less than or equal to 250. Herewith it is possible to maintain approximately 15 m of mooring line length between the 20 fairlead and the hook while consuming less than 7 m of lateral mooring deck depth. This is considered an acceptable lateral space for a mooring deck on an FLSO/FLPG. On the other hand, the angle of displacement a is 25 preferably at least 4'. Maintaining at least 4' ensures that a mooring line, passing through the fairlead to the associated hook approximately 15 m away from the fairlead, is displaced sufficiently inboard of the longitudinal side of the structure to enable safe 30 operation of the hook by an operator who may thus be positioned away from the longitudinal side of the structure during the mooring operation. Moreover, the stress on the mooring line is within operating limits by WO 2010/136444 PCT/EP2010/057142 - 11 way of ensuring that the mooring line passing through the fairlead does not turn sharply towards the longitudinal side as would be the case with an angle of displacement less than 40. 5 The hook and the fairlead as shown in Figure 1 may be provided onto a mooring deck. Figure 2 shows a schematic plan view of an example of such a mooring deck 7 being positioned within the perimeter of the outer hull 2 of the FLNG/FLPG 1. The fairlead 3 is located on the mooring 10 deck at the longitudinal side of the outer hull 2, and the associated hook 4 is located on the mooring deck, inboard of the longitudinal side of the outer hull 2 and offset from the position of the fairlead 3 longitudinally of the hull of the FLNG/FLPG. An operator, heaving a 15 mooring line deployed from a LNGC/LPGC to the FLNG/FLPG onto the mooring deck for attachment to the hook 4, will be positioned away from the longitudinal side of the outer hull 2 and is, therefore, protected from the elements and from falling overboard from the FLNG/FLPG. 20 As generally depicted in Figure 2, the inboard lateral displacement of the hook 4 from its associated fairlead 3 is in the range of 1 to 5 metres to permit safe access to the hook set inboard of the outer hull 2 of the FLNG/FLPG. In a preferred FLNG/FLPG of the 25 invention, the inboard lateral displacement of the hook from its associated fairlead is 3 metres. The lateral width of the mooring deck 7 may be within a range of from 1 to 7, preferably of from 1 to 6 meters. In some embodiments, as generally depicted in Figure 30 3, the mooring deck 7 is bounded by the outer hull 8 on two sides 8a, 8b and is open at the longitudinal side of the outer hull 8c. The outer hull 8c may have a guard means 9, which may be a guard rail, a rope, a steel panel WO 2010/136444 PCT/EP2010/057142 - 12 wall, or combinations thereof, at the open longitudinal side thereof. The operator is, thereby, further protected from both the elements and from the risk of a man overboard scenario. 5 The FNLG/FLPG depicted in Figure 3, further shows the mooring deck 7 with a hook 4 located thereon and a fairlead 3 located at the longitudinal side of the outer hull 8. The mooring deck 7 in this embodiment is contained within the side ballast tanks 10 of the 10 FLNG/FLPG, therefore the cargo carrying capacity of the FLNG/FLPG is not diminished or comprised by the presence of the mooring deck 7 within the bounds of the outer hull 8. Further, the mooring deck being provided in a recess in the outer hull line provides additional safety for an 15 operator heaving a mooring line onto a hook than would be the case with an exposed decking arrangement. By way of providing a mooring deck within the outer hull of the FLNG/FLPG, and integral with the structure, the FLNG/FLPG has a clean hull line and no deck 20 protrusions. Thus, the risk of a protrusion to the outer hull being broken off due to collision with a LNGC/LPGC is reduced or even eliminated. The invention may be implemented on an FLNG/FLPG that is provided with one or more LNG/LPG storage tanks, 25 preferably insulated tanks to hold LNG or LPGs in a cryogenic state. In some embodiments, the offshore structure has a length that is at least equal to a length required to provide sufficient berthing alongside the offshore structure, for a transport carrier, e.g. a 30 tanker, having capacity of greater than about 200,000 cubic metres. Mooring lines may lead from the carrier to fairleads 3 and associated mooring hooks 4 on the FLNG/FLPG as WO 2010/136444 PCT/EP2010/057142 - 13 depicted generally in Figure 2. The hook may be a quick release hook operable to receive the mooring line from the FLNG/FLPG side fairlead. The quick release hook may incorporate a powered capstan to heave a mooring line 5 from an LNGC/LPGC to the FLNG/FLPG structure. In some embodiments, the hook will be a twin set quick release hook with an associated powered capstan set. In embodiments where all of the mooring lines are passed by the LNGC/LPGC to the FLNG/FLPG, the remote 10 operation of the quick release hooks facilitates release of the carrier vessel from the offshore structure in a single operation in the event of an emergency. The hook may comprise a mooring line monitoring load cell. The load cell will be operable to transmit data 15 pertaining to the load applied by the mooring line to the hook to the FLNG/FLPG control room, thereby providing a real time indication and recording of the mooring loads being applied to each and all of the hook sets. Remote release of the mooring hooks may be provided from the 20 control room. Release of the mooring line from the hook under tension may be provided. Mooring line load forces should preferably be kept below about 55% of the Minimum Breaking Load. Increasing mooring line length by leading lines through fairleads 3 25 on the FLNG/FLPG to remote Quick Release Hooks (QRH) may cause chafing. In some embodiments, mooring line flexibility may be in a nylon tail pennant. A mooring line may lead directly from the carrier, through a fairlead 3 to an associated hook 4 as depicted in Figure 30 2. Mooring lines may be designed to comply with OCIMF guidelines. In some embodiments, mooring line flexibility is in the tail pennant. Exemplary materials suitable for use in WO 2010/136444 PCT/EP2010/057142 - 14 a tail pennant are polyamide and PET, for example. It is generally appreciated that longer tail pennant lengths reduce line loading and increase fatigue life. The use of more elastic tail materials may increase the line life of 5 the main mooring line due to decreased line loads. A mooring line length of at least about 15 metres between the fairlead 3 and the QRH may ensure the nylon pennant and joining shackle are clear of the ship's fairlead and not subjected to chafing. In an embodiment, 10 the minimum safe working load of each mooring hook may be more than the minimum-breaking load of the strongest mooring line anticipated. In some embodiments, the operational mooring line may not exceed the greater of 2.5 times the winch brake holding capacity or 2500 KN. 15 The extreme mooring load may not exceed the greater of 2.5 times the minimum breaking load line or 3125 KN. The capstan barrel may be at a suitable height to permit safe handling of messenger lines. The QRH-assembly may be electrically isolated from the platform decks. The 20 insulation may provide an electrical resistance of at least about 1 mega-Ohm. The QRHs may be positioned on the FLNG/FLPG. The mooring lines may lead from the carrier to the fairleads 3 and the QRHs on the FLNG/FLPG. Decks may have rounded 25 edges in front of the mooring hooks to prevent chafing of the mooring lines. In some embodiments the at least one fairlead is connected to the structure. The at least one fairlead may be connected to the structure adjacent a longitudinal side. 30 The fairlead may be an open fairlead having an open top. However, a closed fairlead may be preferred, e.g. of the so-called Panama type, in order to avoid the mooring line to be lifted out of the fairlead. A mooring line may WO 2010/136444 PCT/EP2010/057142 - 15 be passed through the opening in the fairlead. Particularly, a Panama design, closed fairlead may be fitted at the longitudinal side of the FLNG/FLPG to accept the LNGC/LPGC mooring lines and to direct the 5 mooring lines inboard of the longitudinal side to a quick release mooring hook situate on the mooring deck of the FLNG/FLPG. The specification of the fairlead is preferably consistent with the safe working load (SWL) of the quick release hook set. Exemplary SWLs are 125t, SWL, 10 considering the minimum breaking strain (MBL) of the LNGC/LPGC mooring lines. In some embodiments, a single fairlead may exclusively service one single mooring line and hook. Fairleads may be mounted in abutment with, and faired 15 to the FLNG/FLPG longitudinal side. The fairlead will preferably have no protuberances or sharp edges on either the inboard or outboard sides in order to avoid additional wearing on the mooring line as it passes through the fairlead. 20 A Panama design closed fairlead will typically have a base portion attachable to the offshore structure. The fairlead will be in the form of a ring-shape extending upwards from the base portion and having an annular hole in the centre thereof. The annular hole is generally 25 oval. The base portion is typically 1300mm in length and 560mm in width. From the base portion to the centre of the annular hole is typically 505 mm with the fairlead being 930mm in height. The annular hole is typically 450mm in height and 600 mm in length, with a radius of 30 approximately 225 mm. The internal radius of the fairlead will be as large as practicable to reduce stress on the mooring line.
WO 2010/136444 PCT/EP2010/057142 - 16 The fairlead may be lined with a friction reducing agent or material. The friction reducing agent may be a Nylacast TM protective insert for reduction of chafing of a synthetic mooring line pennant. The NylacastT material 5 is a synthetic material incorporating a lubricant that will minimise chafing damage to the LNGC/LPGC mooring pennants in the fairlead. Monitoring systems may be provided on the offshore structure, to detect the carrier speed of approach; 10 mooring line loads through strain gauges on QRHs; and/or pressure monitoring system in air block fenders. Data from the monitoring systems may be centrally collected and displayed in a control room. An embodiment of an FLNG/FLPG incorporating the 15 invention is depicted in Figure 4. The FLNG/FLPG 1 comprises a plurality of fairleads 3 and associated hooks 4. In the depicted embodiment the fairleads 3 are spaced along the outer hull 8 of the FLNG/FLPG and are configured so as to provide mooring points for a 20 liquefied natural gas carrier 11 and/or a liquefied petroleum gas carrier 11. For ease of reference, the fairleads may be numbered from bow to stern using letters from the alphabet, in the present case ranging from A to P. A mooring deck may be defined along the starboard side 25 of the hull (assuming the FLNG/FLPG is moored at its bow) to accommodate side fairleads 3 and mooring hooks 4 generally configured as shown in Figure 4. The mooring arrangement of the FLNG/FLPG may typically comprise mooring lines deployed from the LNGC/LPGC. Typical 30 mooring lines may include headlines, sternlines, breast and spring lines. The FLNG/FLPG may comprise a loading/offloading connection for transferring the hydrocarbon fluid(s). The WO 2010/136444 PCT/EP2010/057142 - 17 connection may comprise a manifold of one or more transfer arms. Such manifolds per se are known, and typically an LNG transfer manifold comprises three arms of which the middle one is a vapour arm. An LPG transfer 5 manifold may also comprise one or more transfer arms. Typically a vapour transfer line is combined on another arm such that no separate vapour arm is provided. The transfer arms may be Chiksan unloading arms available from FMC Energy Systems. Typical LNG/LPG transfer 10 equipment may include power packs, controls, piping and piping manifolds, protection for the piping from mechanical damage, ship/shore access gangway with an operation cubicle, gas detection, fire detection, telecommunications capabilities, space for maintenance, 15 Emergency Release Systems (ERS), Quick Connect / Disconnect Couplers (QCDC), monitoring systems, and/or drainage systems. Assuming mooring on a turret at the bow, the loading/offloading manifold may be suitably located for 20 safety reasons between the mid and aft portion of the offshore structure in order to be removed from as far aft as possible from the process equipment and the turret. Ideally, however, the manifold is also further removed from any crew's quarters on the offshore structure than 25 is the case for a typical transport carrier. For the purpose of illustrating the invention, it is assumed that the transfer manifold comprises both an LNG transfer manifold as well as an LPG manifold. In the examples below, it is assumed that the LNG vapour arm is 30 situated on the FLNG/FLPG at 185 metres from the stern of the structure, with the LPG connection being located some 10 m aft of the LNG vapour arm. Thus, LNGC/LPGC manifold offsets (relative to the middle of the carrier) of up to WO 2010/136444 PCT/EP2010/057142 - 18 25 metres are accommodated. The position of the fairleads 3, referenced to the LNG/LPG vapour arm location, may be configured so as to be capable of receiving mooring lines from an LNGCs ranging from 75,000 cubic metres to 217,000 5 cubic metres capacity, and from LPGCs ranging from 74,000 cubic metres to 84,000 cubic metres capacity. With reference to Figures 5a, 5b, 6a and 6b, in certain embodiments of the invention, the locations (A to P) of the mooring points, represented by fairleads 3, 10 relative to the LNG vapour arm 6 are in accordance with Table 1. Table 1 Lead Distance Number of Direction Distance to LNG leads/hooks of lead to from lead vapour arm hook to hook A 175.0 Double Forward 15m B 155.0 Double Forward 15m C 140.0 Double Forward 15m D 120.0 Double Forward 15m E 100.0 Double Forward 15m F 70.0 Double Towards 15m vapour G 40.0 Double Towards 15m vapour H 20.0 Double Towards 15m vapour I -30.0 Double Towards 15m vapour J -55.0 Double Towards 15m vapour K -80.0 Double Towards 15m vapour WO 2010/136444 PCT/EP2010/057142 - 19 L -110.0 Double Towards 15m vapour M -125.0 Double Towards 15m vapour N -145.0 Double Inboard 15m 0 -155.0 Triple Inboard 15m P -175.0 Triple Inboard 15m A positive value for the distance between the mooring point (A to P) and the LNG vapour manifold in Table 1 indicates a mooring lead location forward of the LNG 5 vapour arm (A to H), and a negative value indicates a mooring lead location aft of the LNG vapour arm (I to P). In the embodiment of Table 1, each lead location accommodates multiple fairleads. Lead locations A to N each accommodate two fairleads and lead locations 0 and P 10 each accommodate three fairleads. The direction of lead to hook is indicated, being the direction the mooring line will be led when passing through the fairlead to the associated hook set. The aft three sets of leads N, 0 and P, situated within the accommodation/service area of the 15 FLNG/FLPG, will be led inboard on the FLNG/FLPG to the associated hook set. In the embodiment described in Table 1, the fairlead to associated hook distance is 15 metres. This distance enables the total LNGC/LPGC mooring line length deployed to be of sufficient length, in 20 combination with the mooring line nylon/polyester pennant, to absorb peak mooring loads in sea states up to 3 m sea height whilst moored. In some embodiments an 11 m tail pennant length will be sufficient. However, in certain embodiments a 22 m 25 tail pennant is preferred.
WO 2010/136444 PCT/EP2010/057142 - 20 In embodiments of the invention wherein the lead to hook distance is 15 metres and the pennant length is 22 metres, the 15 metre lead to hook distance allows the 22 metre mooring pennant to be located in the FLNG/FLPG side 5 lead thereby avoiding conflicting damage of alternate LNGC/LPGC synthetic HMPE and wire mooring lines placed in the same leads. In addition, the 15 metre lead to hook configuration will provide for a greater mooring line length (LNGC/LPGC winch to FLNG/FLPG hook) than would 10 typically be the case. In a conventional shore terminal berth, a mooring line length of 35 to 50 metres is typical, which mooring line length typically is not available in a conventional offshore side-by-side mooring configuration. 15 In order to maximise the length of mooring line inboard of the fairlead, the distance from fairlead to associated hook is preferably as large as possible. As can be seen in Figures 5a, 5b, 6a, 6b, the mooring arrangement allows for alongside berthing of a variety of 20 carrier types and sized while being able to align the carrier's loading/offloading manifold with the corresponding manifold on the FLNG/FLPG structure, even where the carrier's manifold is not located in the centre of the carrier. 25 Figures 5a and b depict an FLNG mooring layouts with mooring points A to P, showing that the FLNG is capable of alongside berthing of 290 metre long LNGCs 11 having their loading/offloading manifolds at different positions relative to the carrier's centre. In Figure 5a the 30 manifold 16 is at the carrier's centre c, but in Figure 5b the manifold 16 is some 15 metres ahead of the carrier's centre c. In both cases, a good alignment WO 2010/136444 PCT/EP2010/057142 - 21 between the carrier's manifold 16 and the target represented by the LNG vapour arm 6 is achievable. Trials using Optimoor analysis tool have shown that even of the LNG manifold on a 290 metre long LNGC is 5 displaced by 24 metre ahead of the carrier's centre line, the carrier can be safely berthed alongside the mooring arrangement. In the latter case, mooring point P is employed. The mooring arrangement is also capable of receiving carriers having their LNG manifold aft of the 10 carrier's centre line, but this situation may be rare in view of the industries desire to remove the manifold as far as possible from the crew's quarters. In the embodiments depicted in Figures 6a and 6b, an offshore structure 1 is shown with a mooring layout 15 having mooring points A to P, capable of alongside mooring of LPGCs having lengths of 203 metres and 214 metres, respectively. The carrier's LPG loading/unloading manifolds 16' are in the shown cases relatively close to the carrier's centre lines c, but the target manifold 6' 20 on the offshore structure 1, being the LPG connection, is some 10 m aft of the LNG vapour arm 6. Again, good alignment is achievable. Thus, an offshore structure 1 accommodating the mooring arrangement as proposed is adapted to accommodate 25 LNGCs and/or LPGCs of widely differing sizes and designs, including manifold offsets. In certain embodiments an FLNG/FLPG accommodating the invention may comprise at least three spring fairlead and associated hook sets. Thus, the mooring layout of the 30 FLNG/FLPG accommodates spring deployment from an LNGC/LPGC. Where weather conditions require, an LNGC/LPGC may deploy two springs from the main deck and one spring from another deck, with a consequential requirement for WO 2010/136444 PCT/EP2010/057142 - 22 the corresponding spring lead and hook sets on the FLNG/FLPG. Figure 7 shows another example of an FLNG/FLPG 1 being anchored to turret 17 at its bow 12. A mooring deck 5 7 is provided on the starboard side of the FLNG/FLPG's outer hull. As is generally depicted in Figure 7, the mooring deck will run from the stern of the FLNG/FLPG 1 forward for approximately 380 metres and at 14.5 metres above the operating waterline. In some embodiments, the 10 FLNG/FLPG 1 may have a mooring deck having a width in the range of 1 to 6 metres to permit safe access between the back of the mooring hook sets and the fore and aft bulkhead, to permit sufficient space to gather the mooring messenger when an operator is heaving mooring 15 lines 20 to the FLNG/FLPG, e.g. with a powered capstan. In an embodiment, the FLNG/FLPG may have a mooring deck with a width of 4 metres. As is further illustrated in Figure 7, a number of fenders 22 are positioned between the FLNG/FLPG and the LNGC/LPGC to prevent damage 20 occurring during the berthing and mooring of the carrier 11 alongside the offshore structure 1. An offshore structure, e.g. in the case of an FLNG/FLPG, may accommodate LNG/LPG storage tanks and allow LNG/LPG vaporization equipment and/or other process 25 equipment and utilities such as liquefaction equipment, gas treating equipment (e.g. acid gas removal equipment, dehydration equipment, mercury removal equipment and the like), gas intake separators and slug catchers, condensate stabilization equipment, etc., to be 30 positioned on an upper surface of the FLNG/FLPG, and safely enable LNGCs/LPGCs to berth directly alongside the FLNG/FLPG. It is also envisaged to provide equipment for carbon (carbon dioxide) capture and sequestration WO 2010/136444 PCT/EP2010/057142 - 23 equipment to handle C02 removed from post combustion flue gases and/or from the hydrocarbon feed. In the case of an FSRU, the offshore structure may accommodate revaporization, heating value control, and 5 metering equipment and other options such as described in for instance WO 2006/052896, the disclosure of which is incorporated herein by reference. An external turret system 17 may be a preferred option for anchoring the offshore structure in a typical 10 water depth of greater than 30 metres. An external turret may be preferable to a Yoke Mooring System but may be dependent on water depth and may require a complete riser design as part of the concept selection. A double hump riser configuration may be a feasible arrangement. 15 A further mooring system of an FLNG/FLPG of the invention may be a weathervaning arrangement to obtain a sufficiently high connecting threshold for the berthing operations of an LNGC/LPGC. A further mooring system and high pressure gas export line may be located at the 20 forward end of an FLNG/FLPG of the invention. After selection of the location of an FLNG/FLPG of the invention, an assessment should be made of the technical feasibility of a further mooring system comprising, for example, an external turret system, an internal turret 25 system, a Yoke Mooring System (YMS), and combinations thereof. An example YMS comprises, for example: a jacket (the jacket may comprise a four legged tubular structure that may be fixed to the seabed via one or more, generally four, piles, driven through the corner 30 tubulars), a mooring head (a mooring head may be located on top of the jacket and may be free to rotate; the mooring head may support the pipe work and equipment, including the swivel stack), a yoke (a yoke may be a WO 2010/136444 PCT/EP2010/057142 - 24 tubular triangular frame that may be connected to the mooring head via a roll and pitch articulation; permanent ballast tanks may be a part of the yoke structure to provide the required pretension in the mooring legs), 5 mooring legs (the mooring legs may comprise tubular steel members connected to the adjacent structure via uni joints; an axial thrust bearing may also be included to provide rotational freedom; the mooring legs with the yoke weight suspended underneath may provide the pendulum 10 mechanism of the mooring system), a mooring structure on the FLNG/FLPG (a mooring structure on the FLNG/FLPG may comprise a tubular frame mounted onto the bow of the FLNG/FLPG; the structure may overhang the bow of the vessel to provide clearance for the yoke; lifting means 15 may be provided for handling of one or more jumper hoses), gas transfer may be performed via one or more, generally two, 16" flexible jumper hoses that may provide a 2x 100% capacity. A further mooring system comprising a YMS may include 20 a gas swivel to transfer send-out gas from the weathervaning FLNG/FLPG to a fixed pipeline riser. An in line swivel may be expected to provide sufficient reliability (typical MTTF of 20 Years) but an 'N+l' arrangement of the fluid transfer system may be obtained 25 through additional toroidal swivel modules. The in-line swivel may be used for operation; the toroidal module may provide the back-up. In case of failure, the in-line may be changed out while the send-out gas may be routed through the toroidal swivel path. 30 In some embodiments, the height of the upper surface, on which mooring equipment, for example, quick-release hooks (QRHs) are disposed, above the surface of the body of water may be such that an angle of mooring lines WO 2010/136444 PCT/EP2010/057142 - 25 extending from the mooring equipment to the liquefied natural gas carrier coupled to the body is less than about 30 degrees. The centerline of the unloading arms may be 5 positioned to create a maximum degree of protection for all types of common LNG/LPGC/LPGCs. Although a three-unloading arm concept as mentioned above may be technically acceptable, a four- unloading arm concept may have more redundancy. Redundancy may 10 increase the integrity and/or reliability level. The spare unloading arm may be used on a day-to-day basis. This may safeguard the proper functioning of the equipment. The installation of one or more spare unloading arms may increase the normal overall LNG/LPG 15 loading capacity. The design of the FLNG/FLPG may account for severe weather conditions. Transfer of LNG/LPG between a LNGC/LPGC and a FLNG/FLPG may be based on traditional hard arms, which are currently used at onshore terminals for ship-shore 20 LNG/LPG transfers. To enable safe and reliable connecting and disconnecting under seaway motions, for floating-to floating transfer, a guide-wire system may be utilized to guide the loading arm to the ship manifold. A suitable overall length of the offshore structure 25 on which the invention is applied may be any length that provides for storing and/or processing of the hydrocarbon fluids such as LNG/LPG as described herein, and is generally at least about 100 metres, specifically at least about 200 metres, more specifically at least about 30 300 metres, and generally no more than about 1000 metres, specifically no more than about 750 metres, and more specifically no more than about 500 metres.
WO 2010/136444 PCT/EP2010/057142 - 26 A suitable breadth of the offshore structure may be any breadth that provides for storing and/or processing of hydrocarbon fluids, such as LNG/LPG as described herein, and is generally at least about 20 metres, 5 specifically at least about 30 metres, more specifically at least about 40 metres, and generally no more than about 300 metres, specifically no more than about 200 metres, and more specifically no more than about 100 metres. 10 A suitable draft of the offshore structure may be any draft that provides for storing and/or processing of hydrocarbon fluids, such as LNG/LPG as described herein, and is generally at least about 5 metres, specifically at least about 7 metres, more specifically at least about 10 15 metres, and generally no more than about 25 metres, preferably no more than about 20 metres. In one embodiment, the draft may be about 17.6 m. A suitable length:depth ratio of the offshore structure may be any length:depth ratio that provides for 20 storing and/or processing of LNG/LPG as described herein and is generally at least about 5, specifically at least about 7, more specifically at least about 10, and generally no more than about 20, specifically no more than about 18, and more specifically no more than about 25 15. An example of a further mooring system of the offshore structure may be a Yoke Mooring System ("YMS"), because the water depth for an inshore location may be in a range of from about 15 metres to about 30 metres and 30 may not allow for the catenary of an external turret system. Maximum sea states should be obtained to ensure that the further mooring system utilized can meet such maximum sea states.
WO 2010/136444 PCT/EP2010/057142 - 27 An example approach procedure of an LNGC/LPGC to an FLNG/FLPG of the invention may include: about 12 hours before the estimated time of arrival ("ETA"), prevailing weather conditions and status of both FLNG/FLPG and 5 LNGC/LPGC are exchanged; preparations are made, for example testing of LNG/LPG arms, mooring equipment, fenders and selecting LNGC/LPGC approach, about 1 hour before ETA, the LNGC/LPGC will arrive at the agreed entry point, at some 2 to 3 nautical miles from the FLNG/FLPG 10 and with a forward speed, typically 4 knots; berthing master will board and tugs are ready to be connected, the LNGC/LPGC will head for a position off the starboard side of the FLNG/FLPG and target to come to complete stop near parallel to the FLNG/FLPG, at approximately 100 m 15 separation, the LNGC/LPGC will move side-ways, whilst monitoring the applied thruster/tug forces, heading relative to the FLNG/FLPG and approach velocity; if control over the LNGC/LPGC position and heading becomes difficult, the approach will have to be aborted, and 20 pneumatic equipment may be used from the FLNG/FLPG to shoot across messenger lines. It may be expected that mooring lines will be passed after touching the fenders. Currently, the significant wave height limit (Hs) for berthing of an LNGC/LPGC alongside an FLNG/FLPG may be 25 considered to be in the range of from about 2.0 to about 2.5 metres, and in the range of from about 2.5 to about 3.0 metres for being moored alongside an FLNG/FLPG of the invention. An example departure manoeuvre looks very much a 30 mirror image of the example approach process. At the start of the actual departure, the ESD link systems is disconnected, with radio links maintaining the integrated systems needed for a safe departure. The LNGC/LPGC WO 2010/136444 PCT/EP2010/057142 - 28 prepares to start the departure manoeuvre. Then the mooring lines are disconnected, which may be implemented one by one, depending on prevailing weather conditions and final operating procedures. 5 An example departure manoeuvre may see the LNGC/LPGC moving the bow clear from the FLNG/FLPG using tugs or carrier bow thruster in combination with wind/wave/current conditions. When the hulls are clear of each other the LNGC/LPGC will use its main propulsion 10 system to move clear and tugs will disconnect. An LNGC/LPGC may be moored in the furthest forward and aft positions. A mooring arrangement of the present invention may be utilised together with breast lines, spring lines. 15 The description above has made apparent that an offshore structure with a mooring arrangement as described, transport carriers of different sizes and designs can be effectively moored in most sea states up to 2.5 or 3.0 m significant wave height. 20 Moreover, the mooring arrangement mimics an on-shore mooring arrangement; that is to say, the moorings deployed from the transport carrier are in a similar plan arrangement to that provided in an on-shore terminal. While the invention is susceptible to various 25 modifications and alternative forms, specific embodiments thereof have been shown by way of example in the drawings and have been described in detail. It should be understood that the drawings and detailed description thereto are not intended to limit the invention to the 30 particular form disclosed, but on the contrary, the intention is to cover all modifications, equivalents and alternatives falling within the spirit and scope of the invention as defined by the appended claims.

Claims (8)

1. An offshore structure comprising an outer hull having longitudinal sides and at least one fairlead located adjacent a longitudinal side, and a hook, connected to the structure and located inboard relative to the fairlead and being displaced along the hull longitudinally from the fairlead, such that an angle of displacement between a tangent to the outer hull at the centre of the fairlead and the hook, is less than or equal to 45*.
2. The offshore structure of claim 1, comprising a plurality of fairleads and associated hooks, the fairleads being spaced along the outer hull and being configured so as to provide mooring points for a transport carrier, each hook being located inboard relative to the associated fairlead and being displaced along the hull longitudinally from the fairlead.
3. The offshore structure of claim 1 or 2, wherein the displacement of each hook with respect to the associated fairlead is suitable to accommodate the length of a mooring line of an onshore mooring system.
4. The offshore structure according to claim 1, wherein the distance from the centre of the fairlead to the hook is in the range from 10 to 22 metres.
5. The offshore structure according to claim 4, wherein the distance from the centre of the fairlead to the hook is about 15 metres.
6. The offshore structure according to claim 1, wherein the angle of displacement is less than or equal to 250.
7. The offshore structure according to claim 1, wherein the angle of displacement is at least
40. 8. The offshore structure according to claim 1, wherein the inboard displacement of the hook from the centre of the fairlead is in the range from 1 to 5 metres. 9. The offshore structure of claim 8, wherein the inboard displacement of the hook from the centre of the fairlead is about 3 metres. 30 10. The offshore structure according to claim 1, wherein the hook and the fairlead are located on a deck, which deck is within the perimeter of the outer hull. 11. The offshore structure according to claim 10, wherein the deck is bounded by the outer hull on two sides and is open at the longitudinal side of the outer hull, and further wherein the outer hull has a guard means at the open longitudinal side. 12. The offshore structure according to claim 10 or claim 11, wherein the deck width is within a range of 1 to 6 metres. 13. The offshore structure according to any one of claims 1 to 12, wherein said structure is a floating liquefied natural gas production unit or a floating liquefied petroleum gas production unit. 14. The offshore structure according to claim 10, wherein the deck is bounded by the outer hull on two sides and is open at the longitudinal side of the outer hull, and further wherein the outer hull has a guard means at the open longitudinal side and the deck width is within a range of 1 to 6 metres and contained within the side ballast tanks of the floating liquefied natural gas production unit or the floating liquefied petroleum gas production unit. 15. The offshore structure according to any one of claims 1 to 14, wherein the fairlead is lined with a friction reducing agent or material. 16. A mooring arrangement comprising at least one mooring line having a pennant at an end thereof, and an offshore structure according to any one of the preceding claims, wherein said at least one mooring line is configured to pass inboard of the outer hull through said fairlead and is attachable to the hook such that the angle of displacement of the at least one mooring line between the tangent to the hull at the centre of the fairlead and the hook is less than or equal to 45 . 17. A mooring arrangement according to claim 16, wherein the pennant is 22 metres in length. 18. An offshore structure, substantially as hereinbefore described with reference to the accompanying drawings. 31 19. A mooring arrangement, substantially as hereinbefore described with reference to the accompanying drawings. Shell Internationale Research Maatschappij B.V. Patent Attorneys for the Applicant/Nominated Person SPRUSON & FERGUSON
AU2010252013A 2009-05-26 2010-05-25 Offshore structure and mooring arrangement Active AU2010252013B2 (en)

Applications Claiming Priority (3)

Application Number Priority Date Filing Date Title
EP09161127.7 2009-05-26
EP09161127A EP2256026A1 (en) 2009-05-26 2009-05-26 Offshore structure and mooring arrangement
PCT/EP2010/057142 WO2010136444A1 (en) 2009-05-26 2010-05-25 Offshore structure and mooring arrangement

Publications (2)

Publication Number Publication Date
AU2010252013A1 AU2010252013A1 (en) 2011-11-24
AU2010252013B2 true AU2010252013B2 (en) 2013-06-06

Family

ID=41152126

Family Applications (1)

Application Number Title Priority Date Filing Date
AU2010252013A Active AU2010252013B2 (en) 2009-05-26 2010-05-25 Offshore structure and mooring arrangement

Country Status (6)

Country Link
EP (1) EP2256026A1 (en)
KR (2) KR20120030059A (en)
CN (1) CN102448810B (en)
AU (1) AU2010252013B2 (en)
BR (1) BRPI1012053B1 (en)
WO (1) WO2010136444A1 (en)

Families Citing this family (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
NO336575B1 (en) * 2012-11-07 2015-09-28 Sevan Marine Asa Device and method for interconnecting a tanker and a floating loading or unloading terminal
KR102087171B1 (en) * 2013-02-19 2020-04-14 대우조선해양 주식회사 System and method for dynamic positioning of floating marine structure
KR101952978B1 (en) 2014-11-12 2019-02-27 현대중공업 주식회사 Floating ocean structure
CN104764428B (en) * 2015-03-31 2017-09-12 舟山实华原油码头有限公司 Ship longitudinal drift detection means
KR20160003728U (en) 2015-04-20 2016-10-28 현대중공업 주식회사 Floating ocean structure
WO2020058342A1 (en) * 2018-09-18 2020-03-26 Single Buoy Moorings Inc. Hydrocarbon production vessel
EP3766773A1 (en) * 2019-07-19 2021-01-20 Ørsted Wind Power A/S Marine transfer apparatus and method of using the same
US11760446B2 (en) 2022-01-07 2023-09-19 New Fortress Energy Offshore LNG processing facility
CN115973354B (en) * 2023-02-10 2025-06-20 中国长江三峡集团有限公司 A floating cleaning boat tying operation system and method
CN116588275A (en) * 2023-06-29 2023-08-15 沪东中华造船(集团)有限公司 A layout method for hanging codes instead of fairleads when a half-ship floats

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN100575184C (en) * 2003-10-03 2009-12-30 海德勒利夫特埃姆克莱德股份有限公司 Fairlead with integrated chain stop
CN1946606B (en) * 2004-04-29 2010-11-10 辛格尔浮筒系船公司 Side-by-side hydrocarbon transfer system
CN101057101A (en) 2004-11-08 2007-10-17 国际壳牌研究有限公司 Liquefied natural gas floating storage regasification unit
EP1705112A1 (en) * 2005-03-22 2006-09-27 Single Buoy Moorings Inc. Enhanced side-by-side mooring construction
US8186170B2 (en) * 2007-05-29 2012-05-29 Sofec, Inc. Floating LNG regasification facility with LNG storage vessel
FR2916732B1 (en) * 2007-06-04 2009-11-13 Doris Engineering FLOATING DOCK MOORING SYSTEM

Also Published As

Publication number Publication date
KR20170084374A (en) 2017-07-19
WO2010136444A1 (en) 2010-12-02
CN102448810A (en) 2012-05-09
BRPI1012053A2 (en) 2016-05-17
EP2256026A1 (en) 2010-12-01
KR102134062B1 (en) 2020-07-15
KR20120030059A (en) 2012-03-27
BRPI1012053B1 (en) 2020-08-25
CN102448810B (en) 2014-07-23
AU2010252013A1 (en) 2011-11-24

Similar Documents

Publication Publication Date Title
AU2010252013B2 (en) Offshore structure and mooring arrangement
EP2356018B1 (en) Floating multi-function unit for the offshore transfer of hydrocarbons
US5944448A (en) Oil field installation with mooring and flowline system
US8286678B2 (en) Process, apparatus and vessel for transferring fluids between two structures
US10549820B2 (en) Method and system for heading control during ship-to-ship transfer of LNG
US20080274655A1 (en) Floating LNG import terminal and method for docking
EP2534040B1 (en) Bow loading station with double deck for cryogenic fluid
AU2008239946B2 (en) System for loading of hydrocarbons from a floating vessel
CA2513180C (en) Ice breaker, method and system for single-support mooring and servicing ships
US8156884B2 (en) Vessel mooring systems and methods
US7117808B2 (en) System for transferring liquid load, mainly oil to a tanker
US20220306244A1 (en) Split mooring system and methods for vessels
KR20170000778U (en) Mooring Device And System For Bunkering Vessel
Hellesmark et al. Development and Qualification of a Tandem FLNG Loading Terminal for Conventional LNG Carriers
Dallas Offshore Loading Systems Shuttle Tanker Installation

Legal Events

Date Code Title Description
FGA Letters patent sealed or granted (standard patent)