[go: up one dir, main page]

AT411473B - FINISHED CONCRETE WALL SHUTTER ELEMENT SYSTEM WITH ONLY ONE SIDE SIDE - Google Patents

FINISHED CONCRETE WALL SHUTTER ELEMENT SYSTEM WITH ONLY ONE SIDE SIDE Download PDF

Info

Publication number
AT411473B
AT411473B AT5972000A AT5972000A AT411473B AT 411473 B AT411473 B AT 411473B AT 5972000 A AT5972000 A AT 5972000A AT 5972000 A AT5972000 A AT 5972000A AT 411473 B AT411473 B AT 411473B
Authority
AT
Austria
Prior art keywords
formwork element
concrete
spacers
wall formwork
prefabricated wall
Prior art date
Application number
AT5972000A
Other languages
German (de)
Other versions
ATA5972000A (en
Inventor
Otto Ritzinger
Original Assignee
Otto Ritzinger
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Otto Ritzinger filed Critical Otto Ritzinger
Priority to AT5972000A priority Critical patent/AT411473B/en
Publication of ATA5972000A publication Critical patent/ATA5972000A/en
Application granted granted Critical
Publication of AT411473B publication Critical patent/AT411473B/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls
    • E02D29/0258Retaining or protecting walls characterised by constructional features
    • E02D29/0275Retaining or protecting walls characterised by constructional features cast in situ

Landscapes

  • Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Description

       

   <Desc/Clms Page number 1> 
 



   Das Betonfertigwandschalsystem mit nur einer Sichtseite ist im Prinzip gleich aufgebaut wie jenes mit zwei Sichtseiten (Doppelwand siehe AT   408 004   B). Der Vorteil liegt darin, dass bei Bauten (Wänden), bei denen es geologisch bedingt nur eine Sichtseite gibt, auch nur eine gemacht werden muss. Die   zweite "Schalseite" ist - wie erwähnt - durch   eine steinige, felsige bzw. mit Spritzbeton   versteifte "Rohwand" vorgegeben.   



   Der Unterschied des Betonfertigwandschalsystems mit nur einer Sichtseite liegt gegenüber der Doppelwand darin, dass anstelle eines erstaufgestellten Schalelementes an hang-, brust- bzw. ulmseitig ausgerichteten und befestigten Trägern, Stehern und dgl. eine Baustahlgittermatte derart befestigt ist (senkrecht oder schräg geneigt und fluchtend), dass Distanzhalter in ihren entsprechenden Positionen   (It.   Plan) eingesteckt sind, und das Betonfertigwandschalelement mit der fabrikmässig gefertigten Sichtseite auf die aus dem Fundament bzw. der Sohle herausragenden Aufnahmebolzen aufgefädelt und mit den eingesteckten Distanzhaltern der-bauseits aufgestellten - Baustahlgittermatte mit von oben durchgefädelten Verbindungsbolzen verbunden und gesichert sind, sodass ein Hinterfüllen (wie bei Doppelwänden) bei Beachtung der Betoniergeschwindigkeit möglich ist.

   Massgeblich dafür sind Dimension und Qualität der Bauteile selbst, sowie der Abstand (horizontal und vertikal) der Distanzhalter zueinander. 



   Notwendige Vorarbeiten auf der Baustelle sind : Das Setzen von Höhenausgleichsunterlagen (bei unebenem Untergrund) und das Setzen der Aufnahmebolzen für das Auffädeln der untersten Distanzhalter des Betonfertigwandschalelementes. Ausserdem ist bzw. sind die Baustahlgittermatte (n) an der Rohwand mittels ausgerichteter Steher oder dergleichen auszurichten und zu fixieren und die Distanzhalter - It. Plan - einzustecken. 



   Ausserdem kann dieses Schalungssystem auch im Tunnel- und Stollen bau eingesetzt werden und zwar als Firstverbau bzw. Firstverkleidung. Hiebei wird die Firste (das Hangende) mit entsprechenden Ankern gesichert. Die unten vorstehenden Enden der Anker (bzw. Zwischenstücke) sind so ausgebildet, dass damit die Bewehrungsgittermatte   - mit   den eingesteckten Distanzhaltern fixiert und höhenmässig einjustiert werden kann bzw. können. Dann wird   das "Betonfertigdecken-   element" mit entsprechenden Hebezeugen angehoben, positioniert, und mit den Verbindungsbolzen, welche durch alle horizontal auf einer Linie liegenden Distanzhalter (der Gittermatte und des Deckenschalelementes) durchgefädelt und (durch Verdrehen) gesichert sind, verbunden. Beim Ausbetonieren muss das Schalelement jedoch unterstützt sein.

   Die bei Betonfertigwandschalelementen (für die Positionierung) notwendigen Aufnahmebolzen sind beim Firstverbau nicht notwendig. Die Gewichtskräfte der   Deckenverkleidung - inklusive Versatzbeton - werden   von den Firstankern aufgenommen. Bei Firstverbauten nach Fig. 5 ist für Installationsleitungen   (z. B.   Löschwasser) genügend Platz vorhanden. Durch   die "Betonummantelung" sind   die Installationsleitungen auch brandgeschützt. 



   FIG. 1 zeigt einen Vertikalschnitt mit felsiger bzw. befestigter roher Wand 26, ausgerichteten und an der Wand 26 befestigten Stehern bzw. Trägern 24, einer an den Stehern 24 befestigte Baustahlgittermatte 12, darin eingehängten Distanzhaltern 13 und die bauseits eingebohrten-in bezug auf die Steher 24 ausgerichteten - Aufnahmebolzen 17. Ein Betonfertigwandschalelement 11 mit den untersten Distanzhaltern 13 auf die Aufnahmebolzen 17 aufgefädelt und weiters auf Verbindungsbolzen 18 - durch die senkrecht auf einer Achse liegenden Distanzhalter 13 der Bau- 
 EMI1.1 
 zen 18 verdreht und dadurch gesichert. Der Verbindungsbolzen 18 ist nicht bis zur Sohle gezeichnet, bis zu welcher er eigentlich reicht. 



   FIG. 2 zeigt einen Vertikalschnitt wie Fig. 1, jedoch mit nach oben hin kleiner werdendem Abstand des Betonfertigwandschalelementes 11 in bezug auf die senkrecht ausgerichtete Baustahlgittermatte 12. Erreicht wird dies, durch Distanzhalter 13 mit untereinander verschiedenen Bezugsmassen (= Mitte Baustahlgittermatte im Schalelement 11 bis Mitte der beiden Distanzhalter Längsdrähte 15) in Bezug auf eine Horizontalebene und gleichen Abständen in bezug auf die Höhe. 



   FIG. 3 zeigt einen Vertikalschnitt wie Fig. 1 bzw. Fig. 2. Hier ist der Träger, die Stütze bzw. der Steher 24 schräg zum Berg hin geneigt und entsprechend an diesem abgestützt. Das Betonfertigwandschalelement 11 ist parallel zum Steher 24 und somit auch parallel zur Baustahlgittermatte 12. Äusserlich unterscheiden sich Fig. 2 und Fig. 3 nicht. Die Aufnahmebolzen 17 sind jedoch in der Schräge der Mittelachse zwischen 11 und 12 einzubohren. 

 <Desc/Clms Page number 2> 

 



   FIG. 4 zeigt einen Vertikalschnitt der Verbundbauweise (Stossfugen der einzelnen Schalelemente auf gegenüberliegenden Seiten gegeneinander der Höhe nach versetzt). Diese ist für hohe bzw. sehr hohe Wände geeignet. Die Betonfertigwandschalelemente 11 sind perspektivisch darge-   stellt - mit Höhenausgleichselementen   28 zur geraden und ebenen Unterkante des Schalelementes 11. Die Verbundbauweise (Verbundsystem) ist auch für geneigte Wände (Fig. 2 u. Fig. 3) einsetzbar. 



   FIG. 5 zeigt einen Vertikalschnitt der oberen Profilhälfte 36 eines Tunnels mit Firstankern 31 und der daran befestigten und horizontal ausgerichteten Baustahlgittermatte 12. Dargestellt sind ferner das positionierte Deckenschalelement 11. 1 und die durchgesteckten Verbindungsbolzen 18 durch die Distanzhalter 13, die aus der Gittermatte 12 und aus dem Deckenschalelement 11. 1 herausragen und einander zugewandt sind, und seitliche Abdichtungen 33 (zum Verfülen des Raums oberhalb des   Schalelements   11. 1 mit Beton). 



   PATENTANSPRÜCHE : 
1. Betonfertigwandschalelement - System mit nur einseitiger Sichtbetonseite, dadurch ge- kennzeichnet. dass es aus einer mittels eines Stehers (24), entsprechend positionierten, ausgerichteten und befestigten Baustahlgittermatte (12), mit darin eingesteckten Distanz- haltern (13) einerseits, und einem Betonfertigwandschalelement (11) - mit in diesem mit- eingegossener Bewehrungsgittermatte (nicht dargestellt) und ebenfalls darin eingesteckten
Distanzhaltern (13)-andererseits besteht, wobei mindestens zwei (vorzüglich mehrere) der untersten Distanzhalter (13) des Betonfertigwandschalelementes (11) auf untereinan- der entsprechend positionierte Aufnahmebolzen (17) aufgefädelt sind, und die einander zugewandten Teile der Distanzhalter (13) (Bügel (14) und daran angeschweisste Längs- drähte (15)) des Betonfertigwandschalelementes (11)

   und der bergseits aufgestellten - positionierten, ausgerichteten und   befestigten - Baustahigittermatte   (12) über den gesam- ten Höhenbereich von mindestens zwei lotrechten Verbindungsbolzen (18) gleichermassen aufgefädelt und nach dem Verdrehen der Verbindungsbolzen (18) gesichert und dadurch miteinander verbunden sind   (Fig. 1).  



   <Desc / Clms Page number 1>
 



   The precast concrete wall formwork system with only one visible side is basically the same as that with two visible sides (double wall see AT 408 004 B). The advantage is that in buildings (walls) where there is only one visible side due to geology, only one must be made. The second "formwork side" is - as mentioned - given by a stony, rocky or "reinforced wall" stiffened with shotcrete.



   The difference of the prefabricated concrete wall formwork system with only one visible side compared to the double wall lies in the fact that instead of a first erected formwork element on beams, uprights and the like on the slope, chest or elm side and fastened, a structural steel mesh mat is attached in this way (vertically or obliquely inclined and aligned) that the spacers are inserted in their corresponding positions (according to the plan), and the prefabricated concrete formwork element with the factory-made visible side is threaded onto the locating bolts protruding from the foundation or the sole and with the inserted spacers on-site installed - structural steel mesh mat with thread through from above Connecting bolts are connected and secured so that backfilling (as with double walls) is possible if the concreting speed is observed.

   Decisive for this are the dimension and quality of the components themselves, as well as the distance (horizontal and vertical) between the spacers.



   The necessary preparatory work on the construction site is: the setting of leveling pads (for uneven ground) and the setting bolts for threading the lowest spacers of the prefabricated concrete formwork element. In addition, the structural steel mesh mat (s) must be aligned and fixed on the bare wall using aligned supports or the like, and the spacers - according to the plan - must be inserted.



   In addition, this formwork system can also be used in tunnel and gallery construction as a ridge shoring or ridge cladding. The ridge (the hanging end) is secured with appropriate anchors. The ends of the anchors (or intermediate pieces) projecting below are designed in such a way that the reinforcing mesh mat can be fixed with the inserted spacers and adjusted in height. Then the "precast concrete slab element" is lifted, positioned, and connected to the connecting bolts, which are threaded through all spacers lying horizontally on a line (the mesh mat and the ceiling formwork element) and secured (by twisting). However, the formwork element must be supported when concreting.

   The mounting bolts required for precast concrete formwork elements (for positioning) are not necessary for ridge shoring. The weight of the ceiling cladding - including offset concrete - is absorbed by the ridge anchors. 5 there is enough space for installation lines (e.g. fire water). The installation lines are also fire-protected due to the "concrete coating".



   FIG. 1 shows a vertical section with rocky or fastened raw wall 26, aligned and fastened supports or supports 24 fastened to the wall 26, a structural steel mesh mat 12 fastened to the upright 24, spacers 13 suspended therein and the drilled-in on-site with respect to the upright 24 aligned - locating bolts 17. A prefabricated concrete wall formwork element 11 with the lowest spacers 13 is threaded onto the locating bolts 17 and furthermore onto connecting bolts 18 - through the spacers 13 of the construction which are perpendicular to an axis.
 EMI1.1
 zen 18 twisted and thereby secured. The connecting bolt 18 is not drawn to the sole to which it actually reaches.



   FIG. 2 shows a vertical section as in FIG. 1, but with an increasing distance between the prefabricated concrete wall formwork element 11 and the vertically oriented structural steel mesh mat 12. This is achieved by spacers 13 with different reference masses (= middle structural steel mesh mat in the formwork element 11 to the middle of the two spacers longitudinal wires 15) with respect to a horizontal plane and equal distances in terms of height.



   FIG. 3 shows a vertical section like FIG. 1 or FIG. 2. Here the support, the support or the upright 24 is inclined obliquely towards the mountain and is supported accordingly on the latter. The precast concrete wall formwork element 11 is parallel to the upright 24 and thus also parallel to the steel mesh mat 12. Externally, FIGS. 2 and 3 do not differ. However, the locating bolts 17 are to be drilled in between 11 and 12 in the slope of the central axis.

 <Desc / Clms Page number 2>

 



   FIG. 4 shows a vertical section of the composite construction (butt joints of the individual formwork elements offset on the other side in terms of height). This is suitable for high or very high walls. The prefabricated concrete wall formwork elements 11 are shown in perspective - with height compensation elements 28 for the straight and flat lower edge of the formwork element 11. The composite construction (composite system) can also be used for inclined walls (FIGS. 2 and 3).



   FIG. 5 shows a vertical section of the upper profile half 36 of a tunnel with ridge anchors 31 and the horizontally oriented structural steel mesh mat 12 fastened thereon. Also shown are the positioned ceiling formwork element 11.1 and the plug-in connecting bolts 18 through the spacers 13, which come from the mesh mat 12 and from Project ceiling formwork element 11.1 and face each other, and side seals 33 (to fill the space above the formwork element 11.1 with concrete).



   PATENT CLAIMS:
1. Concrete prefabricated wall formwork element - system with only one-sided exposed concrete side, marked. that it consists, on the one hand, of a structural steel mesh mat (12), appropriately positioned, aligned and fastened by means of a post (24), with spacers (13) inserted therein, and a prefabricated concrete wall formwork element (11) - with a reinforcing mesh mat (also not shown) cast therein ) and also inserted in it
There are spacers (13) on the other hand, at least two (preferably several) of the lowest spacers (13) of the prefabricated concrete wall formwork element (11) being threaded onto correspondingly positioned locating bolts (17), and the mutually facing parts of the spacers (13) ( Bracket (14) and longitudinal wires (15) welded to it of the prefabricated concrete formwork element (11)

   and the structural steel mesh mat (12) set up, positioned, aligned and fastened on the mountain face are equally threaded over the entire height range by at least two vertical connecting bolts (18) and secured after the connecting bolts (18) have been rotated and are thereby connected to one another (FIG. 1 ).


    

Claims (1)

2. Betonfertigwandschalelement-System nach Anspruch 1, dadurch gekennzeichnet, dass durch die aus dem Schalelement (11) bzw. der bergseits aufgestellten Baustahigittermatte (12) im aufgestellten Zustand im Wandinneren befindlichen horizontalen liegenden Längs- drähte (15) der Distanzhalter (13), jeweils mit einem Verbindungsbolzen (18) durch Einfä- deln der Längsdrähte (15) verbunden und durch Verdrehen der Verbindungsbolzen (18) gesichert sind, sodass das Betonfertigwandschalelement (11) mit der eingerichteten und befestigten Baustahlgittermatte (12) schon im noch nicht vergossenen Zustand fest mitein- ander verbunden ist, das heisst praktisch eine Einheit bildet (Fig. 1).  2. Concrete prefabricated wall formwork element system according to claim 1, characterized in that the horizontal spacer wires (15) of the spacers (13) from the formwork element (11) or the construction steel grid mat (12) set up on the mountain side in the set up state inside the wall. are each connected to a connecting bolt (18) by threading the longitudinal wires (15) and secured by turning the connecting bolts (18) so that the prefabricated wall formwork element (11) with the installed and fastened structural steel mesh mat (12) is already firm in the not yet poured state is connected to one another, that is to say practically forms a unit (FIG. 1). 3. Betonfertigwandschalelement - System nach einem der vorgenannten Ansprüche, dadurch gekennzeichnet, dass mit diesem System nicht nur lotrechte Sichtbetonflächen möglich sind, sondern auch schräg zur Rohwand geneigte Sichtbetonwände geschalt werden kön- nen, wobei sowohl eine lotrechte Stellung des Baustahlgitters (12) mit Distanzhaltern ver- schiedener Bezugsmasse (14. 1, 14. 2...) entweder im Baustahlgitter (12), oder im dazu schräggestellten Betonfertigwandschalelement (11) (Fig. 2) dies bewirken, oder auch ein zur rohen Wand geneigtes befestigtes und ausgerichtetes Baustahlgitter (12) mit parallel dazu verbundenen Betonfertigwandschalelementen (11) (Fig. 3) möglich sind.  3. Concrete prefabricated wall formwork system according to one of the preceding claims, characterized in that not only vertical exposed concrete surfaces are possible with this system, but also exposed concrete walls inclined at an angle to the raw wall can be formed, both a vertical position of the structural steel grid (12) with spacers Different reference dimensions (14. 1, 14. 2 ...) either in the structural steel grid (12) or in the inclined concrete prefabricated wall formwork element (11) (Fig. 2) do this, or a fixed and aligned structural steel grid inclined to the raw wall (12) with parallel connected prefabricated wall formwork elements (11) (Fig. 3) are possible. 4. Betonfertigwandschalelement - System nach einem der vorgenannten Ansprüche, dadurch gekennzeichnet, dass mit diesem Wandschalungssystem auch hohe Wände hergestellt werden können, wobei die Stossfugen der einzelnen Schalelemente gegeneinander-der Höhe nach versetzt- (nach dem Ausgiessen des jeweils unteren Schalelementes) ange- ordnet werden, und entsprechende Verbindungsbolzen (18. 1) Verwendung finden (Fig. 4).  4. Concrete prefabricated wall formwork element - System according to one of the preceding claims, characterized in that high walls can also be produced with this wall formwork system, the butt joints of the individual formwork elements against one another Height offset (after pouring out the lower formwork element), and appropriate connecting bolts (18.1) are used (Fig. 4). 5. Betonfertigwandschalelement - System mit nur einer Sichtbetonseite, dadurch gekenn- zeichnet, dass es als Firstverbau bzw. Firstverkleidung bei Tunneln und dgl. eingesetzt wer- den kann, wobei auf aus der Firste vorstehende Firstanker (31) ein Baustahlgitter (12) mit eingesteckten Distanzhaltern (13) höhenmässig und eben justiert sowie ausgerichtet und <Desc/Clms Page number 3> befestigt ist (Befestigung und Höhenjustierungsteile (32)) und ein Betonfertigwandschalelement (11) - nun Betonfertigdeckenschalelement (11. 1) - (mit entsprechendem Hebezeug positioniert) mit dem Baustahlgitter (12) mittels Verbindungsbolzen (18) verbunden ist (Fig. 5).  5. Concrete prefabricated wall formwork element - system with only one exposed concrete side, characterized in that it can be used as a ridge lining or ridge cladding in tunnels and the like, a steel mesh (12) with inserted on the ridge anchor (31) protruding from the roof Spacers (13) in height and level adjusted and aligned and  <Desc / Clms Page number 3>  is fastened (fastening and height adjustment parts (32)) and a prefabricated concrete formwork element (11) - now prefabricated concrete formwork element (11.1) - (positioned with the appropriate lifting gear) is connected to the steel grid (12) by means of connecting bolts (18) (Fig. 5).
AT5972000A 2000-04-10 2000-04-10 FINISHED CONCRETE WALL SHUTTER ELEMENT SYSTEM WITH ONLY ONE SIDE SIDE AT411473B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
AT5972000A AT411473B (en) 2000-04-10 2000-04-10 FINISHED CONCRETE WALL SHUTTER ELEMENT SYSTEM WITH ONLY ONE SIDE SIDE

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
AT5972000A AT411473B (en) 2000-04-10 2000-04-10 FINISHED CONCRETE WALL SHUTTER ELEMENT SYSTEM WITH ONLY ONE SIDE SIDE

Publications (2)

Publication Number Publication Date
ATA5972000A ATA5972000A (en) 2003-06-15
AT411473B true AT411473B (en) 2004-01-26

Family

ID=3677243

Family Applications (1)

Application Number Title Priority Date Filing Date
AT5972000A AT411473B (en) 2000-04-10 2000-04-10 FINISHED CONCRETE WALL SHUTTER ELEMENT SYSTEM WITH ONLY ONE SIDE SIDE

Country Status (1)

Country Link
AT (1) AT411473B (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CH461751A (en) * 1967-06-29 1968-08-31 Paul Sauter Bauunternehmung Board-shaped, lost formwork element with internal reinforcement
DE2242202A1 (en) * 1972-08-28 1974-03-07 Willi Wessel DEVICE FOR MANUFACTURING REINFORCED CONCRETE WALLS IN THE IN-SITE CONCRETE PROCESS
GB1400277A (en) * 1971-06-07 1975-07-16 Rousset M C F Process for the erection of concrete constructions
EP0061100B1 (en) * 1981-03-18 1986-11-26 SISMO INTERNATIONAL personenvennootschap met beperkte aansprakelijkheid Prefabricated structures, method for their manufacture and their use in the building industry

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CH461751A (en) * 1967-06-29 1968-08-31 Paul Sauter Bauunternehmung Board-shaped, lost formwork element with internal reinforcement
GB1400277A (en) * 1971-06-07 1975-07-16 Rousset M C F Process for the erection of concrete constructions
DE2242202A1 (en) * 1972-08-28 1974-03-07 Willi Wessel DEVICE FOR MANUFACTURING REINFORCED CONCRETE WALLS IN THE IN-SITE CONCRETE PROCESS
EP0061100B1 (en) * 1981-03-18 1986-11-26 SISMO INTERNATIONAL personenvennootschap met beperkte aansprakelijkheid Prefabricated structures, method for their manufacture and their use in the building industry

Also Published As

Publication number Publication date
ATA5972000A (en) 2003-06-15

Similar Documents

Publication Publication Date Title
DE212018000245U1 (en) Connection structure of prestressing concrete frame nodes
DE2727159A1 (en) Flat reinforced concrete ceiling column area reinforcement - using flat bars plugged into concrete and welded below vertical tapering bars
DE69108246T2 (en) METHOD FOR ESTABLISHING A FOUNDATION STRUCTURE FOR A BUILDING SUB-CONSTRUCTION.
CH610966A5 (en) Rock or slope revetment and method of constructing it
AT411473B (en) FINISHED CONCRETE WALL SHUTTER ELEMENT SYSTEM WITH ONLY ONE SIDE SIDE
CH707356A2 (en) Precast concrete to create a protective wall.
DE1784137A1 (en) Production of walls made of concrete or reinforced concrete underground
AT372734B (en) CONSTRUCTION
AT523783B1 (en) Cladding for a wall shell and method for manufacturing
DE3704900A1 (en) Cellar vault
DE3925591A1 (en) Building set for balcony - consists of prefab. consists slab with shackles for anchoring into brickwork and two supporting columns
DE2803860A1 (en) Horizontally loaded support or free standing wall - has vertical support joined to foot piece protruding beyond outline
DE2649132A1 (en) Noise screening wall slab - has reinforced concrete perforated panel inset in load bearing rear frame with edge ribs
DE341982C (en) Concrete support
DE856215C (en) Process for the production of structures from prefabricated parts and prefabricated parts for the implementation of the process
DE3026732A1 (en) Masonry ring anchor component - has stiffeners, reinforcing loops and bars on slab with concrete filled channel
AT212541B (en) Prestressed concrete suspended roof
DE2614539C3 (en) Method and kit for manufacturing slurry tanks
DE7913787U1 (en)
DE2651590A1 (en) Steel pile system for retaining wall - uses U-section vertical piles to support horizontal planks
DE2516723A1 (en) Tunnel rock consolidation system - support mats with flanges bolted to rock round excavation and concreted in
DE2553732C2 (en) Prefabricated anchoring element, especially for prefabricated house construction
AT412485B (en) NOISE PROTECTION WALL CONCRETE FABRICATION ELEMENTS
AT165399B (en)
AT371520B (en) FORMWORK FOR THE CONSTRUCTION OF WALLS OR WALLS IN CONCRETE CONSTRUCTION

Legal Events

Date Code Title Description
ELJ Ceased due to non-payment of the annual fee