NO20101647A1 - Device for a well for well operations and use of the same - Google Patents
Device for a well for well operations and use of the same Download PDFInfo
- Publication number
- NO20101647A1 NO20101647A1 NO20101647A NO20101647A NO20101647A1 NO 20101647 A1 NO20101647 A1 NO 20101647A1 NO 20101647 A NO20101647 A NO 20101647A NO 20101647 A NO20101647 A NO 20101647A NO 20101647 A1 NO20101647 A1 NO 20101647A1
- Authority
- NO
- Norway
- Prior art keywords
- tower
- equipment
- platform
- lock
- well
- Prior art date
Links
- 239000000725 suspension Substances 0.000 claims description 25
- 230000007246 mechanism Effects 0.000 claims description 19
- 238000000034 method Methods 0.000 claims description 11
- 210000000078 claw Anatomy 0.000 claims description 3
- 241000191291 Abies alba Species 0.000 description 13
- 238000005553 drilling Methods 0.000 description 10
- 244000261422 Lysimachia clethroides Species 0.000 description 8
- 230000008878 coupling Effects 0.000 description 5
- 238000010168 coupling process Methods 0.000 description 5
- 238000005859 coupling reaction Methods 0.000 description 5
- 238000007667 floating Methods 0.000 description 4
- 238000012423 maintenance Methods 0.000 description 4
- 238000005516 engineering process Methods 0.000 description 3
- 239000007789 gas Substances 0.000 description 3
- 238000004519 manufacturing process Methods 0.000 description 3
- 239000011435 rock Substances 0.000 description 3
- 229930195733 hydrocarbon Natural products 0.000 description 2
- 150000002430 hydrocarbons Chemical class 0.000 description 2
- 238000002347 injection Methods 0.000 description 2
- 239000007924 injection Substances 0.000 description 2
- 238000003780 insertion Methods 0.000 description 2
- 230000037431 insertion Effects 0.000 description 2
- 238000007789 sealing Methods 0.000 description 2
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 2
- 241000251468 Actinopterygii Species 0.000 description 1
- PEDCQBHIVMGVHV-UHFFFAOYSA-N Glycerine Chemical compound OCC(O)CO PEDCQBHIVMGVHV-UHFFFAOYSA-N 0.000 description 1
- 101100293261 Mus musculus Naa15 gene Proteins 0.000 description 1
- 230000015572 biosynthetic process Effects 0.000 description 1
- 239000003795 chemical substances by application Substances 0.000 description 1
- 238000010276 construction Methods 0.000 description 1
- 239000004744 fabric Substances 0.000 description 1
- 239000012530 fluid Substances 0.000 description 1
- 238000005755 formation reaction Methods 0.000 description 1
- 239000005431 greenhouse gas Substances 0.000 description 1
- 239000007788 liquid Substances 0.000 description 1
- 239000002184 metal Substances 0.000 description 1
- 239000003208 petroleum Substances 0.000 description 1
- 239000004576 sand Substances 0.000 description 1
Landscapes
- Input Circuits Of Receivers And Coupling Of Receivers And Audio Equipment (AREA)
Description
ANORDNING VED ET TÅRN FOR BRØNNOPERASJONER OG BRUK AV SAMME DEVICE AT A TOWER FOR WELL OPERATIONS AND USE THEREOF
Oppfinnelsen angår et tårn forsynt med vertikalt bevegelige plattformer der plattfor-mene er uavhengig bevegelige. Mer spesielt angår oppfinnelsen et tårn til bruk ved brønnoperasjoner der tårnet i bruksstilling på sin utside er forsynt med en nedre, vertikalt bevegelig arbeidsplattform og en øvre, vertikalt bevegelig utstyrsplattform. The invention relates to a tower provided with vertically movable platforms where the platforms are independently movable. More particularly, the invention relates to a tower for use in well operations, where the tower in use position is provided on its outside with a lower, vertically movable work platform and an upper, vertically movable equipment platform.
Fra petroleumsindustrien er det kjent å bore hull ned gjennom jordskorpen for å få adkomst til de såkalte reservoarbergarter som inneholder hydrokarboner i form av olje og gass. Slike hull er kjent som brønner. Det er også kjent å bore såkalte injeksjons-brønner hvor væske eller gass pumpes ned for å opprettholde trykket i reservoar berg-artene etter hvert som hydrokarbonene utvinnes. Det er også kjent å pumpe C02-gass ned i egnede bergarter gjennom injeksjonsbrønner for å deponere denne klimagassen. Det er videre kjent å anvende for så vidt samme teknologi til å utvinne vann fra vann-deponi som befinner seg i geologiske formasjoner. Boring av slike brønner utføres med for så vidt kjent brønnboringsutstyr. Videre er det kjent å anvende slikt brønnbo-ringsutstyr til å komplettere brønnene med nødvendige fåringsrør, produksjonsrør og stigerør. From the petroleum industry, it is known to drill holes down through the earth's crust to gain access to the so-called reservoir rocks that contain hydrocarbons in the form of oil and gas. Such holes are known as wells. It is also known to drill so-called injection wells where liquid or gas is pumped down to maintain the pressure in the reservoir rocks as the hydrocarbons are extracted. It is also known to pump C02 gas into suitable rocks through injection wells to deposit this greenhouse gas. It is also known to use much the same technology to extract water from water landfills located in geological formations. Drilling of such wells is carried out with well-drilling equipment known to the extent known. Furthermore, it is known to use such well drilling equipment to complete the wells with necessary casing pipes, production pipes and risers.
I senere faser av en brønns levetid er det behov for å gjøre vedlikeholdsarbeid. Vedli-keholdsarbeidet kan blant annet omfatte plugging, perforering av brønnforingen, innsetting av sandfilter og innsetting av ventiler. Til slikt vedlikeholdsarbeid kan det være ønskelig å bruke lettere utstyr enn det tunge opprinnelige boreutstyret, for eksempel kabel (såkalt wire eller slick line), såkalt nedihullstraktor og kveilerør. Det lette utstyret er raskere å operere og det kan anvendes mindre fartøy hvis vedlikeholdet skal gjøres på en sjøbunnsbrønn. In later phases of a well's lifetime, there is a need to carry out maintenance work. The maintenance work may include plugging, perforation of the well casing, insertion of sand filters and insertion of valves. For such maintenance work, it may be desirable to use lighter equipment than the heavy original drilling equipment, for example cable (so-called wire or slick line), so-called downhole tractor and coiled pipe. The light equipment is faster to operate and smaller vessels can be used if the maintenance is to be done on a seabed well.
Til utføring av de ønskede arbeidsoperasjoner monteres det såkalte nedihullsverktøy på den enden av kabelen, nedihullstraktoren eller kveilerøret som først senkes ned i brønnen. Til slike verktøy hører også verktøy for å fiske opp annet verktøy eller gjen-stander som enten har falt ned i brønnen ved et uhell eller som har satt seg fast under en arbeidsoperasjon. To carry out the desired work operations, the so-called downhole tool is mounted on the end of the cable, downhole tractor or coiled pipe which is first lowered into the well. Such tools also include tools for fishing out other tools or objects that have either fallen into the well by accident or that have become stuck during a work operation.
Ved arbeid på trykksatte brønner er det viktig å forhindre såkalte utblåsninger. Til dette anvendes det utblåsningsventiler. Disse er innen faget kjent som blowout preventer og vil i det følgende omtales som BOP-ventiler. When working on pressurized wells, it is important to prevent so-called blowouts. Exhaust valves are used for this. These are known in the field as blowout preventers and will be referred to below as BOP valves.
Det er vanlig å plassere en BOP-ventil ved brønnhodet, for eksempel på sjøbunnen når det er en utaskjærs brønn. I tilknytning til en bunnfast, marin produksjonsinnretning løper det et stigerør fra brønnhodet og til kjellerdekket. På stigerøret i kjellerdekket er det anordnet enda ett sett med ventiler, det såkalte juletre. Juletreet er anordnet slik at kabel, nedihullstraktor eller kveilerør kan føres inn i stigerøret. Dette krever at det over juletreet befinner seg en sluse, innen faget omtalt som en riser, som verktøyet først plasseres i. Når verktøyet er plassert inne i slusen, stenges slusen først i sin øvre ende og deretter åpnes den i sin nedre ende mot juletreet og trykket i slusen stiger til samme trykk som i stigerøret. Deretter kan verktøyet senkes nedover i stigerøret og deretter i selve brønnen. Slusen tildannes ved et eget sett med stigerør, innen faget kjent som riser joint, som kobles sammen til ønsket lengde. For ekstra sikkerhet er det på slusens øvre ende montert en egen BOP-ventil som kabelen eller kveilerøret løper gjennom. Det er anordnet egnede tetningsmidler omkring kabelen eller kveile-røret i form av en justerbar tetning, innen faget kjent som såkalt pack box eller stripper, for å kunne opprettholde trykket i slusen under operasjonen. Slike midler er kjent innen faget og omtales ikke nærmere her. It is common to place a BOP valve at the wellhead, for example on the seabed when it is an offshore well. In connection with a fixed marine production facility, a riser runs from the wellhead to the basement deck. Another set of valves, the so-called Christmas tree, is arranged on the riser in the basement deck. The Christmas tree is arranged so that cable, downhole tractor or coiled pipe can be fed into the riser. This requires that there is a sluice above the Christmas tree, referred to in the trade as a riser, in which the tool is first placed. When the tool is placed inside the sluice, the sluice is first closed at its upper end and then it is opened at its lower end towards the Christmas tree and the pressure in the lock rises to the same pressure as in the riser. The tool can then be lowered down into the riser and then into the well itself. The lock is formed by a separate set of risers, known in the field as a riser joint, which are connected to the desired length. For extra safety, a separate BOP valve is mounted on the upper end of the lock, through which the cable or coil pipe runs. Suitable sealing means are arranged around the cable or the coil pipe in the form of an adjustable seal, known in the art as a so-called pack box or stripper, in order to be able to maintain the pressure in the lock during the operation. Such agents are known in the art and are not described in more detail here.
Verktøyet som senkes ned i brønnen for å utføre ønskede operasjoner kan typisk være 15 meter lange. En perforeringskanon kan være 25 til 30 meter lang. Anvendelse av slikt verktøy krever da at slusen er minst tilsvarende lang. Slusen vil derfor rage opp fra juletreet gjennom et eventuelt lukedekk og videre gjennom et såkalt riggflyttingsdekk. På dette dekket befinner det seg en skliramme som boretårnet kan forskyves horisontalt langs. På riggflyttingsdekket kan det bygges et eget tårn omkring slusen for å operere nedihullsverktøyet. Dette tårnet må bygges så høyt at det rager over slusens øvre endeparti med sin BOP og så høyt at det fastholder det utstyret som er nødvendig for drive kabel eller kveilerør ned i eller ut av brønnen. Slikt utstyr kan for en kveilerørsoperasjon omfatte en injektor og øverst en såkalt svanehals. The tool that is lowered into the well to perform the desired operations can typically be 15 meters long. A perforating gun can be 25 to 30 meters long. Use of such a tool then requires that the lock be at least correspondingly long. The lock will therefore protrude from the Christmas tree through a possible hatch deck and further through a so-called rig moving deck. On this deck is a skid frame along which the derrick can be moved horizontally. On the rig moving deck, a separate tower can be built around the lock to operate the downhole tool. This tower must be built so high that it projects over the upper end of the lock with its BOP and so high that it holds the equipment necessary to drive cable or coiled tubing down into or out of the well. For a coiled pipe operation, such equipment can comprise an injector and at the top a so-called gooseneck.
Tårnet som bygges for å kunne utføre lette brønnoperasjoner, kan ikke stå perma-nent. Som nevnt rager slusen opp gjennom riggflyttingsdekket og dette forhindrer at boreriggen kan flyttes langs hele sklirammen. Tårnet bygges derfor opp av tårnmoduler til nødvendig høyde og demonteres igjen etter bruk. Bygging og demontering av tårnet tar tid, og i denne tiden kan ikke andre operasjoner utføres på brønnen. The tower, which is built to be able to carry out light well operations, cannot stand permanently. As mentioned, the lock protrudes through the rig moving deck and this prevents the drilling rig from being moved along the entire skid frame. The tower is therefore built up of tower modules to the required height and dismantled again after use. Building and dismantling the tower takes time, and during this time no other operations can be carried out on the well.
Det er en risiko for at hele eller deler av nedihullsverktøyet ved et uhell mistes eller blir sittende fast. Verktøyet må da fiskes opp igjen for at brønnen igjen skal kunne There is a risk of all or part of the downhole tool being accidentally lost or stuck. The tool must then be fished up again for the well to work again
produsere. Til dette formål finnes det egne fiskeverktøy. Disse kan være 10 til 15 meter lange. Ved anvendelse av et fiskeverktøy må slusen være så lang at den kan rom-me både fiskeverktøyet og det oppfiskede verktøy. Det er derfor vanlig å bygge slusen så lang fra starten av at den er forberedt for denne type uhell, selv om den da blir betydelig lengre enn det som er nødvendig for den planlagte brønnoperasjon. Dersom slusen ikke bygges lang nok, vil det ved et uhell nede i brønnen være nødvendig å bygge tårnet høyere. Dette vil kreve flere tårnmoduler. Hvis flere tårnmoduler ikke er tilgjengelig må disse bringes tilveie, med et ytterligere tidstap til følge. produce. There are special fishing tools for this purpose. These can be 10 to 15 meters long. When using a fishing tool, the lock must be so long that it can accommodate both the fishing tool and the fished tool. It is therefore common to build the lock so long from the start that it is prepared for this type of accident, even if it then becomes significantly longer than what is necessary for the planned well operation. If the lock is not built long enough, it will be necessary to build the tower higher by accident down in the well. This will require several tower modules. If several tower modules are not available, these must be provided, resulting in a further loss of time.
Det er således flere ulemper ved bruk av lettere utstyr for å utføre brønnoperasjoner. Det tar tid å bygge det nødvendige tårnet på riggflyttingsdekket og å demontere dette. Tårnet er sammensatt av mange moduler som må heises på plass. Krankapasitet er en knapp ressurs på en produksjonsplattform og løfteoperasjoner er en av de far-ligste operasjonene som utføres med hensyn til personellets liv og helse. Tårnet er modulært og er ikke forsynt med en heis, men med innvendige trapper. Disse trappe-ne må gjøres så brede at skadet personell kan bringes ned på båre. Dette gjør at tårnets fotavtrykk blir relativt stort. Slusen befinner seg i senter av tårnet. Nedihullsverk-tøyet må derfor først heises opp over tårnet og deretter senkes ned gjennom tårnets øverste del inntil det kan tres inn i slusens øvre ende. Arbeidsoperasjoner som omfatter sammenkobling av nedihullsverktøy og sammenkobling av det komplette nedi-hullsverktøy med kabelen eller kveilerøret, samt føring av kabel eller kveilerør gjennom slusens BOP, gjøres alt ved slusens øvre ende. Dette er tungvint da personellet må klatre en betydelig høyde i tårnets trapp for å komme til arbeidsstedet fra riggflyttingsdekket. There are thus several disadvantages when using lighter equipment to carry out well operations. It takes time to build the necessary tower on the rig moving deck and to dismantle it. The tower is composed of many modules that must be lifted into place. Crane capacity is a scarce resource on a production platform and lifting operations are one of the most dangerous operations carried out with regard to the life and health of personnel. The tower is modular and is not provided with an elevator, but with internal stairs. These stairs must be made wide enough that injured personnel can be brought down on stretchers. This means that the tower's footprint will be relatively large. The lock is located in the center of the tower. The downhole tool must therefore first be hoisted up over the tower and then lowered down through the upper part of the tower until it can be threaded into the upper end of the lock. Work operations that include connecting the downhole tool and connecting the complete downhole tool with the cable or coiled pipe, as well as routing the cable or coiled pipe through the lock's BOP, are all done at the lock's upper end. This is cumbersome as the personnel have to climb a considerable height in the tower's stairs to get to the work site from the rig moving deck.
Patentskrift WO 2009/001088 beskriver et tårn om bord i et fartøy innrettet for boring av havbunnsbrønner og operasjoner i slike brønner. For å kunne gjøre kveilerørsope-rasjoner er tårnet forsynt med en ramme hvor det inne i rammen er integrert en førs-te fast, øvre plattform som holder en injektor, en justerbar tetning og en svanehals, og en andre fast, nedre plattform som holder en BOP-ventil. Når kveilerørsutstyret ikke er i bruk, eller når det klargjøres, er rammen parkert på utsiden av tårnet. Før operasjon flyttes rammen sidelengs inn i tårnet ved hjelp av føringsarmer og eventuelt en kran, slik at rammen henger i tårnets toppblokk over fartøyets senterbrønn, den såkalte moon pool. Løfting av verktøy for sammenstilling utføres av skipets kraner. Patent document WO 2009/001088 describes a tower on board a vessel designed for drilling seabed wells and operations in such wells. In order to be able to perform coiled pipe operations, the tower is provided with a frame where inside the frame is integrated a first fixed, upper platform that holds an injector, an adjustable seal and a gooseneck, and a second fixed, lower platform that holds a BOP valve. When the coiled tubing equipment is not in use, or when it is being prepared, the frame is parked on the outside of the tower. Before operation, the frame is moved sideways into the tower using guide arms and possibly a crane, so that the frame hangs in the tower's top block above the vessel's center well, the so-called moon pool. Lifting of tools for assembly is carried out by the ship's cranes.
Patentskrift GB 2399838 beskriver et sammenfold bart tårn for bruk ved kveilerørsope-rasjoner spesielt om bord i et fartøy, en flytende boreplattform eller en strekkforank- ret plattform. Tårnet består i bruksstilling av en ramme med to eller flere vertikale rammeelementer eller bein. Hensikten med rammen er å overføre vekten av en nedre BOP-ventil og et øvre kveilerørsutstyr fra brønnhodet og til fartøyet eller til boreplatt-formen. Mellom rammens bein er det plassert en nedre plattform for BOP-ventilen. Denne plattformen kan bevege seg vertikalt i forhold til rammen. Videre er det mellom rammens bein plassert en øvre plattform for det øvre kveilerørsutstyr som omfatter blant annet en injektor og en svanehals. Denne plattformen kan bevege seg vertikalt uavhengig av BOP plattformen. Injektoren kan forskyves horisontalt bort fra slusens lengdeakse eller inn mot denne. Slusen befinner seg mellom rammens bein og er således inne i rammen. Rammen er ytterligere forsynt med midler for hiv-kompensering. Nedihullsutstyr som skal plasseres i slusen heises inn med en ekstern kran. Rammens øvre tverrelement gir en høydebegrensing for lengden på nedihullsutstyr som kan heises inn i rammen. Patent document GB 2399838 describes a collapsible bare tower for use in coiled pipe operations, especially on board a vessel, a floating drilling platform or a tension-anchored platform. In use, the tower consists of a frame with two or more vertical frame elements or legs. The purpose of the frame is to transfer the weight of a lower BOP valve and upper coiled tubing equipment from the wellhead and to the vessel or to the rig form. A lower platform for the BOP valve is placed between the legs of the frame. This platform can move vertically relative to the frame. Furthermore, an upper platform is placed between the legs of the frame for the upper coil pipe equipment, which includes, among other things, an injector and a gooseneck. This platform can move vertically independently of the BOP platform. The injector can be moved horizontally away from the longitudinal axis of the lock or towards it. The lock is located between the legs of the frame and is thus inside the frame. The framework is further provided with funds for HIV compensation. Downhole equipment to be placed in the lock is hoisted in with an external crane. The frame's upper cross member provides a height limitation for the length of downhole equipment that can be hoisted into the frame.
Patentskrift US 2004/0206551 viser en borerigg i form av en mast montert på en tilhenger. En plattform for en kveilerørsinjektor er fast montert på mastens ene side og kveilerørsinjektoren hviler på plattformen. Masten reises ved et dreiearrangement i mastens nedre ende og dreiearrangementet er fastgjort til riggens faste rotasjons-bord. En BOP-ventil henger under det faste rotasjonsbordet. Patent document US 2004/0206551 shows a drilling rig in the form of a mast mounted on a trailer. A platform for a coiled pipe injector is fixedly mounted on one side of the mast and the coiled pipe injector rests on the platform. The mast is raised by a turning arrangement at the lower end of the mast and the turning arrangement is attached to the rig's fixed rotation table. A BOP valve hangs below the fixed rotary table.
Patentskrift US 6,032,744 viser en borerigg der en injektor for blant annet kveilerørs-operasjoner er montert hengende under en arbeidsplattform og hvor det er en fast avstand mellom en BOP-ventil som befinner seg under injektoren, og injektoren. En svanehals for å lede kveilerøret ned i injektoren befinner seg over arbeidsplattformen. Injektoren og svanehalsen er derfor adskilte komponenter. Svanehalsen kan i én ut-førelse beveges vertikalt langs en mast mens injektoren er i ro. I en alternativ utførel-se er en spole for kveilerøret montert for vertikal bevegelse i nevnte mast. Patent document US 6,032,744 shows a drilling rig where an injector for, among other things, coiled pipe operations is mounted hanging below a work platform and where there is a fixed distance between a BOP valve located below the injector and the injector. A gooseneck to guide the coil tube down into the injector is located above the work platform. The injector and the gooseneck are therefore separate components. In one embodiment, the gooseneck can be moved vertically along a mast while the injector is at rest. In an alternative embodiment, a coil for the coil pipe is mounted for vertical movement in said mast.
Patentskrift US 6,431,286 viser en borerigg forsynt med et boretårn i form av en to-delt mast montert på en tilhenger. En vugge, som er innrettet til å kunne fastholde en kveilerørsinjektor på sin underside, er bevegelig langs mastenes mot hverandre vendende sider og slik at kveilerørsinjektoren beveges langs mastenes yttersider. Boretårnet er innrettet til å kunne holde en BOP-ventil. Patent document US 6,431,286 shows a drilling rig provided with a derrick in the form of a two-part mast mounted on a trailer. A cradle, which is designed to hold a coiled pipe injector on its underside, is movable along the opposite sides of the masts and so that the coiled pipe injector is moved along the outer sides of the masts. The derrick is designed to be able to hold a BOP valve.
I tillegg til de nevnte metoder for brønnoperasjoner, brukes også en metode som innen faget er kjent som snubbing. Snubbing vil si at en rørstreng som består av gjengede rørseksjoner, føres inn i en trykksatt brønn gjennom en BOP-ventil. Det brukes en jekk for å presse røret ned i brønnen for å overkomme brønntrykket. In addition to the aforementioned methods for well operations, a method known in the field as snubbing is also used. Snubbing means that a pipe string consisting of threaded pipe sections is fed into a pressurized well through a BOP valve. A jack is used to push the pipe down into the well to overcome the well pressure.
Med nedihullsutstyr menes her utstyr som plasseres i en brønn og etterlates der. Med nedihullsverktøy menes her verktøy som etter å ha utført sin oppgave, føres ut igjen av brønnen. Downhole equipment here means equipment that is placed in a well and left there. Downhole tools here mean tools which, after having performed their task, are taken back out of the well.
Oppfinnelsen har til formål å avhjelpe eller å redusere i det minste én av ulempene ved kjent teknikk, eller i det minste å skaffe tilveie et nyttig alternativ til kjent teknikk. The purpose of the invention is to remedy or to reduce at least one of the disadvantages of known technology, or at least to provide a useful alternative to known technology.
Formålet oppnås ved trekk som er angitt i nedenstående beskrivelse og i etterfølgende patentkrav. The purpose is achieved by features that are stated in the description below and in subsequent patent claims.
I et første aspekt vedrører oppfinnelsen en anordning for brønnoperasjoner omfattende et tårn med en utside og en innside, hvor tårnet på sin utside er forsynt med en i bruksstilling vertikalt bevegelig arbeidsplattform og en vertikalt bevegelig utstyrsplattform som er uavhengig bevegbar i forhold til arbeidsplattformen, og hvor arbeidsplattformen er forsynt med en avhengingsanordning. Dette har den fordel at det er fri til-gang til brønnens senter for heising av nedihullsutstyr og nedihullsverktøy inn i brønnen, og at heisløftet ikke behøver være høyere enn at det fritt kan passere utstyrsplattformen når denne befinner seg i en lav posisjon. Det har videre den fordel at sammenkobling av nedihullsutstyr, nedihullsverktøy og for eksempel kveilerør, kabel eller en snubbingrørstreng kan gjøres fra arbeidsplattformen. Derved unngås arbeid høyt oppe i tårnet og personell slipper å gå opp og ned store høyder i en trapp, noe som effektiviserer operasjonen. At arbeidsplattformen er forsynt med en avhengingsanordning har den fordel at arbeidsplattformen temporært holder vekten av slusen mens denne settes sammen eller demonteres, og mens utstyr eller verktøy plasseres i slusen. Det har videre den fordel at arbeidsplattformen kan brukes til å heve eller senke slusen i forhold til juletreet. Avhengingsanordningen kan omfatte et såkalt false rotary og kilebelter. Kilebelter kalles også for slips. Avhengingsanordningen kan i en alternativ utførelsesform omfatte en gripeklo av for så vidt kjent type. In a first aspect, the invention relates to a device for well operations comprising a tower with an outside and an inside, where the tower is provided on its outside with a vertically movable working platform in use position and a vertically movable equipment platform which is independently movable in relation to the working platform, and where the work platform is equipped with a suspension device. This has the advantage that there is free access to the center of the well for hoisting downhole equipment and downhole tools into the well, and that the hoist lift does not need to be higher than it can freely pass the equipment platform when it is in a low position. It also has the advantage that connecting downhole equipment, downhole tools and, for example, coiled tubing, cable or a snubbing pipe string can be done from the work platform. This avoids working high up in the tower and personnel do not have to go up and down great heights on a staircase, which makes the operation more efficient. The fact that the work platform is provided with a suspension device has the advantage that the work platform temporarily holds the weight of the lock while it is assembled or dismantled, and while equipment or tools are placed in the lock. It also has the advantage that the work platform can be used to raise or lower the lock in relation to the Christmas tree. The suspension device can comprise a so-called false rotary and wedge belts. V-belts are also called ties. In an alternative embodiment, the suspension device can comprise a gripping claw of a known type.
Minst én av arbeidsplattformen og utstyrsplattformen kan være forsynt med festemidler for bevegelig innfesting i tårnets utside. Slike festemidler er velkjente innen faget og kan omfatte en styrevogn, såkalt dolly, og tilhørende styrevognsføring i form av en skinne. Arbeidsplattformen og utstyrsplattformen kan heves og senkes på for så vidt kjent måte ved bruk av for eksempel tannstang, hydrauliske stempler, vinsj eller ski-vehjul. Nødvendige motorer kan være elektrisk drevne eller hydraulisk drevne. At least one of the work platform and the equipment platform can be provided with fasteners for movable attachment to the outside of the tower. Such fasteners are well-known in the field and can include a steering carriage, so-called dolly, and associated steering carriage guidance in the form of a rail. The work platform and the equipment platform can be raised and lowered in a known manner by using, for example, a rack, hydraulic pistons, a winch or a pulley wheel. Necessary motors can be electrically driven or hydraulically driven.
Arbeidsplattformen kan være forsynt med en BOP-ventil. Utstyrsplattformen kan være forsynt med minst ett brønnoperasjonsutstyr valgt fra gruppen bestående av en injek tor, kabeloperasjonsutstyr og snubbingutstyr. Dette har den fordel at anordningen kan brukes til flere typer brønnoperasjoner. The work platform can be equipped with a BOP valve. The equipment platform can be provided with at least one well operation equipment selected from the group consisting of an injector, cable operation equipment and snubbing equipment. This has the advantage that the device can be used for several types of well operations.
Injektoren kan i bruksstilling være forsynt med midler for horisontal og vertikal bevegelse i forhold til utstyrsplattformen. The injector can be provided with means for horizontal and vertical movement in relation to the equipment platform in the position of use.
Tårnet kan være innrettet til å motta et magasin for brønnutstyr slik som for eksempel sluseseksjoner. Magasinet kan være forsynt med en åpning vendende mot arbeidsplattformen og utstyrsplattformen. Utstyrsplattformen kan i én utførelsesform være The tower can be arranged to receive a magazine for well equipment such as, for example, sluice sections. The magazine can be provided with an opening facing the work platform and the equipment platform. In one embodiment, the equipment platform can be
forsynt med en hentemekanisme for betjening av brønnutstyr. Dette har den fordel at magasinet inneholder de nødvendige komponenter og seksjoner for bygging av slusen og disse vil befinne seg i en vertikal posisjon. Samvirket med magasinet, den vertikalt bevegelige utstyrsplattform og utstyrsplattformens hentemekanisme, reduserer antall nødvendige kranløft og sammenstillingen går raskere siden slusens komponenter og seksjoner kan beveges en kort, horisontal avstand. Dette har ytterligere den fordel at en ekstra sluseseksjon ligger klar i magasinet i tilfelle det er behov for å forlenge slusen ved et uhell, for eksempel at det er nødvendig å fiske opp ødelagt utstyr eller ødelagt verktøy fra brønnen. Siden utstyrsplattformen kan beveges høyere opp i tårnet, er det plass til den ekstra sluseseksjonen mellom BOP-ventilen og utstyrsplattformen uten at tårnet må forlenges. En slik forlenging av slusen kan gjøres raskt, samtidig som det er spart tid ved ikke å montere denne siste sluseseksjonen ved den ordinære sammenstilling av slusen, da det bare unntaksvis er behov for en så lang sluse. provided with a retrieval mechanism for operating well equipment. This has the advantage that the magazine contains the necessary components and sections for building the lock and these will be in a vertical position. In cooperation with the magazine, the vertically movable equipment platform and the equipment platform retrieval mechanism, the number of required crane lifts is reduced and the assembly is faster since the lock's components and sections can be moved a short, horizontal distance. This has the further advantage that an extra sluice section is ready in the magazine in case there is a need to extend the sluice by accident, for example if it is necessary to fish out broken equipment or broken tools from the well. Since the equipment platform can be moved higher up the tower, there is room for the additional sluice section between the BOP valve and the equipment platform without the tower having to be extended. Such an extension of the lock can be done quickly, while saving time by not fitting this last lock section during the ordinary assembly of the lock, as there is only exceptionally a need for such a long lock.
Tårnet kan i én utførelsesform være forsynt med en utvendig, vertikal posisjonerbar manipulatorarm. Grunnet den utvendige plassering av arbeidsplattform og utstyrsplattform, og at disse er vertikalt bevegelige, kan en utvendig manipulatorarm komme høyt nok opp til å svinge nedihullsutstyr og nedihullsverktøy inn over BOP-ventilen. Dette har den fordel at antall løft med ekstern kran reduseres. In one embodiment, the tower can be provided with an external, vertically positionable manipulator arm. Due to the external location of the work platform and equipment platform, and that these are vertically movable, an external manipulator arm can reach high enough to swing downhole equipment and downhole tools in over the BOP valve. This has the advantage that the number of lifts with an external crane is reduced.
Tårnet kan i en ytterligere utførelsesform være forsynt med en vertikal posisjonerbar heis. I enda en ytterligere utførelsesform kan tårnet være innrettet for å transporteres horisontalt og forsynt med midler i form av for eksempel en tapp for vertikal posisjonering på et brukssted. Dette har den fordel at tårnet kan transporteres som én enhet og dermed unngås arbeid og tid til å bygge et modulært tårn. In a further embodiment, the tower can be provided with a vertically positionable lift. In yet another embodiment, the tower can be arranged to be transported horizontally and provided with means in the form of, for example, a pin for vertical positioning at a point of use. This has the advantage that the tower can be transported as one unit, thus avoiding the work and time required to build a modular tower.
I et andre aspekt vedrører oppfinnelsen en framgangsmåte ved brønnoperasjoner omfattende bruk av et tårn med en utside og en innside, hvor tårnet på sin utside forsynes med en i bruksstilling vertikalt bevegelig arbeidsplattform og en vertikalt bevegelig utstyrsplattform som er uavhengig bevegelig i forhold til arbeidsplattformen, og hvor arbeidsplattformen forsynes med en avhengingsanordning og avhengingsanordningen temporært bringes til å fastholde en sluse eller en sluseseksjon. In a second aspect, the invention relates to a procedure for well operations involving the use of a tower with an outside and an inside, where the tower is provided on its outside with a vertically movable working platform in use position and a vertically movable equipment platform which is independently movable in relation to the working platform, and where the working platform is provided with a suspension device and the suspension device is temporarily brought to hold a lock or a lock section.
Framgangsmåten kan videre omfatte trinnene: The procedure can further include the steps:
- å hente en sluseseksjon fra tårnets magasin ved hjelp av en hentemekanisme som utstyrsplattformen er forsynt med; - ved hjelp av utstyrsplattformens hentemekanisme å bevege en første sluseseksjon til over senter av en avhengingsanordning som arbeidsplattformen er forsynt med; - utstyrsplattformen senkes til avhengingsanordningen kan bringes i inngrep med og bringes til å fastholde sluseseksjonen i dens øvre endeparti; - hentemekanismen bringes til å løsne fra sluseseksjonen og utstyrsplattformen heves for å hente en andre sluseseksjon fra magasinet; - den andre sluseseksjonen bringes over og i forlengelse av den første sluseseksjonen, deretter senkes utstyrsplattformen til den andre sluseseksjonen møter den første sluseseksjonen og de to sluseseksjonene kobles sammen; - avhengingsanordningen bringes til å løsne taket i den første sluseseksjonen; - utstyrsplattformen senkes sammen med slusen til avhengingsanordningen kan gripe tak i den andre sluseseksjonens øvre endeparti; - operasjonen gjentas til slusen er ferdigstilt; - utstyrsplattformen bringes til å løfte en BOP-ventil til toppen av slusen for fastgjøring av BOP-ventilen til slusen; og - utstyrsplattformens utstyr valgt fra gruppen bestående av injektor, kabeloperasjonsutstyr og snubbingutstyr bringes til å slutte tettende mot BOP-ventilen. - retrieving a lock section from the tower's magazine by means of a retrieving mechanism with which the equipment platform is provided; - using the equipment platform's retrieval mechanism to move a first lock section to the center of a suspension device with which the work platform is provided; - the equipment platform is lowered until the suspension device can be brought into engagement with and brought to retain the lock section in its upper end portion; - the retrieval mechanism is caused to disengage from the sluice section and the equipment platform is raised to retrieve a second sluice section from the magazine; - the second lock section is brought over and in extension of the first lock section, then the equipment platform is lowered until the second lock section meets the first lock section and the two lock sections are connected; - the suspension device is brought to release the roof in the first lock section; - the equipment platform is lowered together with the lock until the suspension device can take hold of the second lock section's upper end part; - the operation is repeated until the lock is completed; - the equipment platform is brought to lift a BOP valve to the top of the lock for securing the BOP valve to the lock; and - the equipment platform equipment selected from the group consisting of injector, cable operation equipment and snubbing equipment is brought to close sealing against the BOP valve.
Framgangsmåten kan videre omfatte trinnene: The procedure can further include the steps:
- å parkere injektoren på utstyrsplattformen til sides for BOP-ventilens senter; og - to park the injector on the equipment platform to the side of the BOP valve center; and
- å klargjøre injektoren ved å tre et kveilerør gjennom injektoren. - to prepare the injector by threading a coiled tube through the injector.
Framgangsmåten kan videre omfatte trinnene: The procedure can further include the steps:
- å bringe en vertikalt bevegelig manipulatorarm på tårnets utside til å hente og pluk-ke opp et nedihullsutstyr eller et nedihullsverktøy som befinner seg på et dekk som tårnet står på; - å bringe manipulatorarmen så høyt opp langs en av tårnets styreskinner at nedihullsutstyret eller nedihullsverktøyet kan svinges inn over BOP-ens senter og deretter senkes ned i slusen; - å henge av nedihullsutstyret eller nedihullsverktøyet på en C-plate; - å frigjøre manipulatorarmen fra nedihullsutstyret eller nedihullsverktøyet; - å gjenta framgangsmåten og å skjøte sammen nedihullsutstyret eller nedihullsverk- - bringing a vertically movable manipulator arm on the outside of the tower to retrieve and pick up a downhole equipment or a downhole tool located on a deck on which the tower stands; - bringing the manipulator arm so high up along one of the tower's guide rails that the downhole equipment or downhole tool can be swung in over the center of the BOP and then lowered into the lock; - suspending the downhole equipment or the downhole tool on a C plate; - to release the manipulator arm from the downhole equipment or the downhole tool; - to repeat the procedure and to join the downhole equipment or downhole work-
tøyet til en nedihullssammenstilling; - å bringe nedihullssammenstillingen fast til et kveilerør eller en kabel. the cloth for a downhole assembly; - to secure the downhole assembly to a coiled pipe or cable.
Framgangsmåten kan videre omfatte trinnet: The method may further include the step:
- å bringe injektoren eller kabeloperasjonsutstyret over BOP-ventilens senter og koble injektoren eller kabeloperasjonsutstyret tettende til BOP-ventilen. - bringing the injector or cable operating equipment over the center of the BOP valve and tightly connecting the injector or cable operating equipment to the BOP valve.
Framgangsmåten kan videre omfatte trinnet: The method may further include the step:
- å bringe slusen inneholdende nedihullssammenstillingen tettende til et juletre. - to bring the lock containing the downhole assembly tightly to a Christmas tree.
Framgangsmåten som beskrevet ovenfor kan gjøres i motsatt rekkefølge. The procedure as described above can be done in reverse order.
I det etterfølgende beskrives et eksempel på en foretrukket utførelsesform som er anskueliggjort på medfølgende tegninger, hvor: Fig. 1 viser et sideriss av et tårn med en i bruksstilling nedre, vertikalt bevegelig arbeidsplattform og en øvre, vertikalt bevegelig utstyrsplattform, der arbeidsplattformen befinner seg i sin nedre posisjon; og In the following, an example of a preferred embodiment is described which is visualized in the accompanying drawings, where: Fig. 1 shows a side view of a tower with a lower, vertically movable work platform in use position and an upper, vertically movable equipment platform, where the work platform is located in its lower position; and
Fig. 2 viser et riss av tårnet og plattformer som vist i figur 1, sett ovenfra. Fig. 2 shows a view of the tower and platforms as shown in Fig. 1, seen from above.
I figurene viser henvisningstallet 1 til en anordning i henhold til oppfinnelsen. I figur 1 er et tårn 2 på sin utside 22 forsynt med en i bruksstilling nedre, vertikalt bevegelig arbeidsplattform 3 og en øvre, vertikalt bevegelig utstyrsplattform 4. Tårnet 2 er på sin ene utside 22 forsynt med to vertikale styreskinner 24. Arbeidsplattformen 3 er på en side som vender mot tårnet 2, forsynt med minst én styrevogn 32 av for så vidt kjent type og vil ikke omtales videre i detalj. I figurene er det vist to styrevogner 32 som beveger seg langs hver sin vertikale styreskinne 24. Utstyrsplattformen 4 er på en side som vender mot tårnet 2, forsynt med minst én styrevogn 42 av for så vidt kjent type. I figurene er det vist to styrevogner 42 som beveger seg langs hver sin vertikale styreskinne 24. In the figures, reference number 1 shows a device according to the invention. In Figure 1, a tower 2 is provided on its outside 22 with a lower, vertically movable work platform 3 in use position and an upper, vertically movable equipment platform 4. The tower 2 is provided on one outside 22 with two vertical guide rails 24. The work platform 3 is on a side facing the tower 2, provided with at least one steering carriage 32 of a known type and will not be discussed further in detail. In the figures, two guide carriages 32 are shown which each move along a vertical guide rail 24. The equipment platform 4 is on a side facing the tower 2, provided with at least one guide carriage 42 of a known type. In the figures, two guide carriages 42 are shown which each move along their own vertical guide rail 24.
Tårnet 2 er på sin innside 25 forsynt med faste tårndekk 26 og stiger 28 for innvendig adkomst til tårnets 2 forskjellige høydenivåer og for evakuering fra tårnet. The tower 2 is provided on its inside 25 with fixed tower decks 26 and ladders 28 for internal access to the tower's 2 different height levels and for evacuation from the tower.
I eksemplet er utstyrsplattformen 4 forsynt med en injektor 5 av for så vidt kjent type innrettet til å føre et kveilerør (ikke vist) inn i og ut av en brønn (ikke vist). Injektoren 5 er forsynt med en fast svanehals 52 av for så vidt kjent type. Injektor 5 og svanehals 52 vil ikke bli beskrevet i detalj. Injektoren 5 står via fire høydejusteringsmeka-nismer 54 på et injektorfundament 56 som er bevegelig fastgjort til utstyrsplattformen 4. Injektorfundamentet 56 er horisontalt bevegelig i en retning markert med en pil på tegningene og horisontalt bevegelig i en retning perpendikulært på den markerte retning. Under injektoren 5 er injektoren 5 forsynt med en justerbar tetning 58 som kan være en såkalt stripper eller en pack box, og en hydraulisk hurtigkobling 59 for fast-gjøring til en sluseseksjon eller en BOP-ventil 34. In the example, the equipment platform 4 is provided with an injector 5 of a known type designed to lead a coiled pipe (not shown) into and out of a well (not shown). The injector 5 is provided with a fixed gooseneck 52 of a known type. Injector 5 and gooseneck 52 will not be described in detail. The injector 5 stands via four height adjustment mechanisms 54 on an injector foundation 56 which is movably attached to the equipment platform 4. The injector foundation 56 is horizontally movable in a direction marked with an arrow in the drawings and horizontally movable in a direction perpendicular to the marked direction. Below the injector 5, the injector 5 is provided with an adjustable seal 58 which can be a so-called stripper or a pack box, and a hydraulic quick coupling 59 for attachment to a lock section or a BOP valve 34.
I eksemplet er arbeidsplattformen 3 forsynt med en BOP-ventil 34 av for så vidt kjent type og denne omtales ikke nærmere. Arbeidsplattformen 3 er videre forsynt med en åpning (ikke vist) for vertikal gjennomføring av en sluse, og arbeidsplattformen er ytterligere forsynt med en avhengingsanordning 36 som kan være et såkalt false rotary med kilebelter innen faget omtalt som slips. In the example, the work platform 3 is provided with a BOP valve 34 of a known type and this is not described in more detail. The work platform 3 is further provided with an opening (not shown) for the vertical passage of a lock, and the work platform is further provided with a suspension device 36 which can be a so-called false rotary with V-belts referred to in the art as ties.
Figur 2 viser tårnet 2 sett ovenfra med utstyrsplattformen 4 der det meste av arbeidsplattformen 3 er skjult. Figuren 2 er forenklet og noen detaljer er utelatt. Mellom styreskinnene 24 er tårnet 4 innrettet til å motta et magasin (ikke vist) for brønnutstyr slik som komponenter for å bygge en sluse (ikke vist). Magasinet plasseres i det åpne rommet 27 mellom styreskinnene 24. Magasinet kan være et fingerbord eller anordnet til å være roterbart. En hentemekanisme 7 av for så vidt kjent type er innrettet til å hente brønnutstyr fra magasinet. Hentemekanismen 7 er i dette eksemplet bevegelig fastgjort til injektorfundamentet 56. Hentemekanismen 7 kan i bruksstilling bevege seg horisontalt i samme retning som injektorfundamentet 56, vist med pil, og horisontalt i en retning perpendikulært på injektorfundamentets 56 bevegelsesretning. Figure 2 shows the tower 2 seen from above with the equipment platform 4 where most of the work platform 3 is hidden. Figure 2 is simplified and some details are omitted. Between the guide rails 24, the tower 4 is adapted to receive a magazine (not shown) for well equipment such as components for building a lock (not shown). The magazine is placed in the open space 27 between the guide rails 24. The magazine can be a finger board or arranged to be rotatable. A retrieval mechanism 7 of a known type is designed to retrieve well equipment from the magazine. In this example, the retrieval mechanism 7 is movably attached to the injector foundation 56. In use, the retrieval mechanism 7 can move horizontally in the same direction as the injector foundation 56, shown with an arrow, and horizontally in a direction perpendicular to the direction of movement of the injector foundation 56.
Tårnet 2 er på sin utside 22 forsynt med en vertikal bevegelig manipulatorarm av for så vidt kjent type (ikke vist). Manipulatorarmen er innfestet i én av tårnets styreskinner 24 og er innrettet til på for så vidt kjent måte å bevege seg vertikalt langs sty-reskinnen 24. Manipulatorarmen er innrettet til med en gripeanordning av for så vidt kjent type, å kunne hente nedihullsverktøy eller nedihullsutstyr fra dekket (ikke vist) som tårnet 2 står på, heise dette opp og bringe det inn over senter av slusen og BOP-ventilen 34, for deretter å senke verktøyet ned gjennom BOP-ventilen 34 og inn i slusen. Tilsvarende kan manipulatorarmen i motsatt rekkefølge bringe nedihullsverktøy ut av slusen og plassere dette på dekket som tårnet 2 står på. Tårnet 2 er videre på sin utside 22 forsynt med en vertikalt bevegelig heis av for så vidt kjent type (ikke vist). Heisen er innfestet i én av tårnets styreskinner 24 og beveger seg vertikalt langs denne. Manipulatorarm og heis er innfestet i hver sin styreskinne 24. Heisen er innrettet til å kunne stoppe ved tårnets 2 innvendige plattformer 26, ved arbeidsplattformen 3, uansett hvilket høydenivå arbeidsplattformen 3 befinner seg på, og ved The tower 2 is provided on its outside 22 with a vertical movable manipulator arm of a known type (not shown). The manipulator arm is attached to one of the tower's guide rails 24 and is arranged to move vertically along the guide rail 24 in a generally known manner. The manipulator arm is arranged to be able to retrieve downhole tools or downhole equipment from the deck (not shown) on which the tower 2 stands, hoist this up and bring it in over the center of the lock and BOP valve 34, then lower the tool down through the BOP valve 34 and into the lock. Correspondingly, in the opposite order, the manipulator arm can bring downhole tools out of the lock and place this on the deck on which the tower 2 stands. The tower 2 is further provided on its outside 22 with a vertically movable lift of a known type (not shown). The lift is attached to one of the tower's guide rails 24 and moves vertically along this. The manipulator arm and elevator are each attached to a guide rail 24. The elevator is designed to be able to stop at the tower's 2 internal platforms 26, at the work platform 3, regardless of the height level the work platform 3 is at, and at
utstyrsplattformen 4, uansett hvilket høydenivå utstyrsplattformen 4 befinner seg på. the equipment platform 4, regardless of the height level at which the equipment platform 4 is located.
Tårnet 2 er på utsiden 22 i sitt ene endeparti 29 forsynt med en tapp 8 på to av tår nets 2 utsider 22. Tårnet 2 kan transporteres i en horisontal posisjon ombord i for eksempel et forsyningsskip og heises i horisontal posisjon over til sitt brukssted. På tårnets 2 brukssted er det anordnet en hevemekanisme (ikke vist) som griper om tappe-ne 8 og reiser tårnet 2 opp i en vertikal bruksposisjon. Magasinet med brønnutstyr kan plasseres mellom tårnets 2 styreskinner 24 før tårnet 2 reises. Etter at tårnet 2 er reist, heises arbeidsplattformen 3 og utstyrsplattformen 4 på plass, og disse fastgjøres via sine styrevogner 32, 42 til styreskinnene 24. Manipulatorarmen og heisen heises også på plass og festes til sine respektive styreskinner 24. 1 det etterfølgende forklares hvordan oppfinnelsen anvendes ved en kveilerørsope-rasjon. Fagpersonen vil vite hvordan tilsvarende operasjon kan utføres ved bruk av kabel, wirelinetraktor og snubbing, samt hvilket utstyr som må plasseres på arbeidsplattformen og utstyrsplattformen for slike operasjoner. The tower 2 is provided on the outside 22 in its one end part 29 with a pin 8 on two of the outsides 22 of the tower net 2. The tower 2 can be transported in a horizontal position on board, for example, a supply ship and hoisted in a horizontal position over to its place of use. At the place of use of the tower 2, a lifting mechanism (not shown) is arranged which grips the pins 8 and raises the tower 2 into a vertical position of use. The magazine with well equipment can be placed between the tower's 2 guide rails 24 before the tower 2 is erected. After the tower 2 has been erected, the work platform 3 and the equipment platform 4 are lifted into place, and these are fixed via their guide carriages 32, 42 to the guide rails 24. The manipulator arm and the elevator are also lifted into place and attached to their respective guide rails 24. 1 the following explains how the invention used in a coiled pipe operation. The specialist will know how a similar operation can be carried out using cable, wireline tractor and snubbing, as well as which equipment must be placed on the work platform and the equipment platform for such operations.
Arbeidsplattformen 3 stilles i ønsket nivå. Utstyrsplattformen er forsynt med injektoren 5 og hentemekanismen 7. Utstyrsplattformen 3 heves til riktig høyde for ved hjelp av hentemekanismen 7 å hente den første sluseseksjonen i magasinet mellom tårnets 2 styreskinner 24. Arbeidsplattformen 3 er forsynt med en avhengingsmekanisme 36 i form av en såkalt false rotary og et kilebelte. Injektorfundamentet 56 og hentemekanismen 7 flytter sluseseksjonen til senter av avhengingsanordningen 36. Utstyrsplattformen 4 senkes til ønsket nivå. Avhengingsanordningen 36 bringes i inngrep med sluseseksjonen i dens øvre endeparti og holder sluseseksjonen fast. Hentemekanismen 7 løsnes fra sluseseksjonen og utstyrsplattformen 4 heves til riktig høyde for ved hjelp av hentemekanismen 7 å hente den andre sluseseksjonen fra magasinet. Den andre sluseseksjonen bringes over og i forlengelse av den første sluseseksjonen. Deretter senkes utstyrsplattformen 4 til den andre sluseseksjonen møter den første sluseseksjonen og de to sluseseksjonene kobles sammen. Deretter løsnes avhengingsan-ordningens 36 tak i den første sluseseksjonen og utstyrsplattformen 4 senkes sammen med slusen til avhengingsanordningen 36 kan gripe tak i den andre sluseseksjonens øvre endeparti. På toppen av den andre sluseseksjonens øvre endeparti plasseres et greinrør av for så vidt kjent type ved hjelp av manipulatorarmen eller ved å heve og senke utstyrsplattformen 4. Greinrøret tjener som en sirkulasjonsport for returvæske-strøm fra brønnen. Deretter plasseres en tredje sluseseksjon på toppen av greinrøret på samme måte som beskrevet for den første og andre sluseseksjon. Til slutt løfter utstyrsplattformen 4 ved hjelp av injektorens 5 hydrauliske hurtigkobling 59, BOP-ventilen 34, som har stått parkert på arbeidsplattformen 3, på plass over den sist monterte sluseseksjonen. Work platform 3 is set at the desired level. The equipment platform is provided with the injector 5 and the retrieval mechanism 7. The equipment platform 3 is raised to the correct height in order to retrieve the first lock section in the magazine between the tower's 2 guide rails 24 using the retrieval mechanism 7. The work platform 3 is provided with a suspension mechanism 36 in the form of a so-called false rotary and a wedge belt. The injector foundation 56 and the retrieval mechanism 7 move the lock section to the center of the suspension device 36. The equipment platform 4 is lowered to the desired level. The suspension device 36 is brought into engagement with the lock section in its upper end portion and holds the lock section firmly. The retrieval mechanism 7 is detached from the sluice section and the equipment platform 4 is raised to the correct height to use the retrieval mechanism 7 to retrieve the second sluice section from the magazine. The second lock section is brought over and in extension of the first lock section. The equipment platform 4 is then lowered until the second lock section meets the first lock section and the two lock sections are connected. The suspension device 36 is then loosened in the first lock section and the equipment platform 4 is lowered together with the lock until the suspension device 36 can grip the second lock section's upper end part. On top of the second sluice section's upper end part, a branch pipe of a known type is placed using the manipulator arm or by raising and lowering the equipment platform 4. The branch pipe serves as a circulation port for return fluid flow from the well. A third sluice section is then placed on top of the branch pipe in the same way as described for the first and second sluice section. Finally, with the aid of the injector 5's hydraulic quick coupling 59, the equipment platform 4 lifts the BOP valve 34, which has been parked on the work platform 3, into place above the most recently installed lock section.
Injektoren 5 skyves til side og parkeres slik at den ikke er i veien for nedihullsutstyr eller nedihullsverktøy som skal senkes ned i slusen. Kveilerøret (ikke vist) tres gjennom injektoren 5 på for så vidt kjent måte og dette omtales ikke videre her. The injector 5 is pushed aside and parked so that it is not in the way of downhole equipment or downhole tools to be lowered into the lock. The coil pipe (not shown) is threaded through the injector 5 in a manner known to the extent known and this is not discussed further here.
Manipulatorarmen kjøres deretter ned til dekket og plukker opp ønsket nedihullsutstyr eller nedihullsverktøy. Deretter kjøres manipulatorarmen så høyt opp at nedihullsutstyret eller nedihullsverktøyet kan fritt dreies inn over BOP-ventilens 34 senter og deretter senkes ned i slusen. Nedihullsutstyret eller nedihullsverktøyet henges av på en såkalt C-plate. Manipulatorarmen frigjøres deretter fra nedihullsutstyret eller nedi-hullsverktøyet og returnerer for å hente neste nedihullsutstyr eller nedihullsverktøy. Nedihullsutstyret eller nedihullsverktøyet skjøtes sammen av personell som befinner seg ved BOP-ventilen 34. Når nedihullsutstyret og/eller nedihullsverktøyet er sam-menstilt til en såkalt nedihullssammenstilling, innen faget kjent som bottom hole as-sembly, kobles nedihullssammenstillingen til kveilerøret. Injektoren 5 skyves over BOP-ventilen 34 og kobles til BOP-ventilen med den hydrauliske hurtigkoblingen 59. Kveilerørsarrangementet er nå klart til bruk. Tilkobling og frakobling av slusens nedre parti til juletreet gjøres på kjent måte og omtales ikke her. The manipulator arm is then driven down to the deck and picks up the desired downhole equipment or downhole tool. The manipulator arm is then driven up so high that the downhole equipment or the downhole tool can be freely turned in over the center of the BOP valve 34 and then lowered into the lock. The downhole equipment or downhole tool is hung from a so-called C-plate. The manipulator arm is then released from the downhole equipment or downhole tool and returns to retrieve the next downhole equipment or downhole tool. The downhole equipment or the downhole tool is spliced together by personnel located at the BOP valve 34. When the downhole equipment and/or the downhole tool is assembled into a so-called bottomhole assembly, known in the art as a bottomhole assembly, the downhole assembly is connected to the coil pipe. The injector 5 is pushed over the BOP valve 34 and connected to the BOP valve with the hydraulic quick coupling 59. The coil pipe arrangement is now ready for use. Connecting and disconnecting the lower part of the lock to the Christmas tree is done in a known way and is not discussed here.
I en alternativ utførelsesform er arbeidsplattformen 3 forsynt med en avhengingsmekanisme 36 i form av en gripeklo av for så vidt kjent type (ikke vist). In an alternative embodiment, the work platform 3 is provided with a suspension mechanism 36 in the form of a gripping claw of a known type (not shown).
I en alternativ utførelsesform utgjøres anordningens 1 brukssted av en ikke vist for-skyvbar bro forsynt med et brodekk. Broa er videre på sin underside forsynt med to nedragende bropilarer. De nedragende bropilarer kan utgjøres av en metallkonstruk-sjon. Bropilarene er i sine nedre ender forsynt med midler innrettet til å kunne skli på en første skliramme på et riggflyttingsdekk. I en foretrukket utførelsesform er broas lengderetning perpendikulær på riggflyttingsdekkets skliramme. Brodekket er forsynt med en andre skliramme som strekker seg i broas lengderetning. Anordningen 1 er forsynt med midler (ikke vist) innrettet til å kunne skli på den andre skliramme. Ved å forskyve anordningen 1 langs broas andre skliramme og ved å skli broa langs riggflytningsdekkets første skliramme, kan anordningen 1 bringes til en valgt posisjon på riggflytningsdekket. Brodekket er mellom den andre skliramme forsynt med luker hvor slusen kan føres fra anordningen 1 ned til og gjennom lukeåpninger i riggflytningsdekket og ned til juletreet på kjellerdekket. In an alternative embodiment, the place of use of the device 1 is constituted by a not shown movable bridge provided with a bridge deck. The bridge is also provided on its underside with two lowering bridge pillars. The lowering bridge pillars can be made of a metal construction. The bridge piers are provided at their lower ends with means designed to be able to slide on a first sliding frame on a rig moving deck. In a preferred embodiment, the longitudinal direction of the bridge is perpendicular to the skid frame of the rig moving deck. The bridge deck is provided with a second sliding frame that extends in the bridge's longitudinal direction. The device 1 is provided with means (not shown) designed to be able to slide on the second sliding frame. By displacing the device 1 along the bridge's second sliding frame and by sliding the bridge along the rig moving deck's first sliding frame, the device 1 can be brought to a selected position on the rig moving deck. The bridge deck is between the second sliding frame provided with hatches where the lock can be led from device 1 down to and through hatch openings in the rig floating deck and down to the Christmas tree on the basement deck.
Anordningen 1 anvendes til å sammenstille en sluse som før beskrevet over et første juletre på kjellerdekket. Etter at arbeidet er utført i den første brønnen, tas, om nød-vendig, nedihullssammenstillingen ut av slusen. Slusens nedre ende frigjøres fra juletreet. Arbeidsplattformens 3 avhengingsanordning 36 fastholder slusen. Ved å heve arbeidsplattformen 3 heises slusens nedre ende opp fra kjellerdekket og slik at slusens nedre ende rager over riggflytningsdekket når arbeidsplattformen 3 er ført oppover til et øvre parti i tårnet 2. Derved oppnås at anordningen 1 kan føres til en posisjon over en annen brønn ved å skli tårnet 2 langs broas skliramme og ved å skli broa langs riggflytningsdekkets skliramme uten at slusen trengs å adskilles. Når anordningen er kommet til ny, ønsket posisjon, senkes slusen ved å senke arbeidsplattformen 3 inntil slusens nedre ende kan kobles til et andre juletre på kjellerdekket. Utstyrsplattformen 4 beveges slik at den ikke kommer i veien for arbeidsplattformen 3.1 denne utførel-sesformen spares det betydelig tid når det skal utføres arbeid i flere brønner. The device 1 is used to assemble a lock as previously described above a first Christmas tree on the basement deck. After the work has been carried out in the first well, if necessary, the downhole assembly is removed from the lock. The lower end of the lock is released from the Christmas tree. The suspension device 36 of the work platform 3 holds the lock. By raising the working platform 3, the lower end of the lock is raised from the basement deck and so that the lower end of the lock protrudes above the rig floating deck when the working platform 3 is brought up to an upper part of the tower 2. This achieves that the device 1 can be moved to a position above another well by to slide tower 2 along the bridge's sliding frame and by sliding the bridge along the rig floating deck's sliding frame without the lock needing to be disassembled. When the device has reached the new, desired position, the lock is lowered by lowering the working platform 3 until the lower end of the lock can be connected to a second Christmas tree on the basement deck. The equipment platform 4 is moved so that it does not get in the way of the work platform 3. In this embodiment, considerable time is saved when work is to be carried out in several wells.
I en alternativ utførelsesform frigjøres ikke slusen fra den hydrauliske hurtigkoblingen 59. Etter at slusens nedre ende er frigjort fra juletreet og slusen eventuelt frigjort fra arbeidsplattformens avhengingsanordning 36, kan slusen heises opp og senkes ned ved hjelp av utstyrsplattformen 4. I denne utførelsesform spares det også betydelig tid når det skal utføres arbeid i flere brønner. In an alternative embodiment, the lock is not released from the hydraulic quick coupling 59. After the lower end of the lock is released from the Christmas tree and the lock is possibly released from the work platform suspension device 36, the lock can be raised and lowered using the equipment platform 4. In this embodiment, it is also saved considerable time when work is to be carried out in several wells.
I en ytterligere alternativ utførelsesform kan heising og senking av slusen utføres ved at slusen samtidig holdes fast av arbeidsplattformens 3 avhengingsanordning 36 og av den hydrauliske hurtigkoblingen 59, og at arbeidsplattformen 3 og utstyrsplattformen 4 samvirker ved å heves eller senkes med samme fart. Dette har den ytterligere fordel at slusen fastholdes av to uavhengige mekanismer, noe som øker sikkerheten i ar-beidsoperasjonen. In a further alternative embodiment, raising and lowering the lock can be carried out by the lock being simultaneously held by the suspension device 36 of the working platform 3 and by the hydraulic quick coupling 59, and that the working platform 3 and the equipment platform 4 cooperate by being raised or lowered at the same speed. This has the further advantage that the lock is maintained by two independent mechanisms, which increases the safety of the work operation.
Claims (13)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| NO20101647A NO20101647A1 (en) | 2010-11-23 | 2010-11-23 | Device for a well for well operations and use of the same |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| NO20101647A NO20101647A1 (en) | 2010-11-23 | 2010-11-23 | Device for a well for well operations and use of the same |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| NO20101647A1 true NO20101647A1 (en) | 2011-05-25 |
Family
ID=45498163
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| NO20101647A NO20101647A1 (en) | 2010-11-23 | 2010-11-23 | Device for a well for well operations and use of the same |
Country Status (1)
| Country | Link |
|---|---|
| NO (1) | NO20101647A1 (en) |
-
2010
- 2010-11-23 NO NO20101647A patent/NO20101647A1/en not_active Application Discontinuation
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| US20120318530A1 (en) | Device for a Tower for Well Operations and Use of Same | |
| US4208158A (en) | Auxiliary offshore rig and methods for using same | |
| DK3114026T3 (en) | Offshore drilling system, vessels and methods | |
| US20060213653A1 (en) | Multi-function well servicing vehicle | |
| NO742065L (en) | ||
| WO2011135541A2 (en) | Modular multi-workstring system for subsea intervention and abandonment operations | |
| NO331541B1 (en) | Kill / leash interconnect device between a riser and a floating drilling vessel | |
| NO20120189A1 (en) | Offshore Drilling System | |
| MX2007004709A (en) | Pivoting pipe handler for off-line make up of drill pipe joints. | |
| NO314771B1 (en) | Drilling frame for an underwater wellhead assembly | |
| US7527100B2 (en) | Method and apparatus for cutting and removal of pipe from wells | |
| US9217297B2 (en) | Method and support apparatus for supporting down hole rotary tools | |
| CN110753780A (en) | Riser inline pipe jacking column assembly on floating ship for processing, testing and storing | |
| US20170211340A1 (en) | Telescoping Snubbing Unit Frame | |
| AU2015349120B2 (en) | A mobile offshore drilling unit, a method of using such a unit and a system comprising such a unit | |
| NO325441B1 (en) | Mobile equipment for riserless drilling, well intervention, subsea construction from a vessel | |
| US11560683B2 (en) | Offshore drilling unit | |
| NO117070B (en) | ||
| KR20120031405A (en) | Drill ship with auxiliary structure | |
| US10086917B2 (en) | Drilling vessel and method for operating a drilling vessel adapted to run large diameter casing strings | |
| US11499379B2 (en) | System and method for subsea well operation | |
| RU2472901C1 (en) | Water-intake tubular well and device for its erection | |
| NO20101647A1 (en) | Device for a well for well operations and use of the same | |
| KR20130138503A (en) | Fixing apparatus for elevating tubular | |
| NO333539B1 (en) | System and method for switching between ordinary drilling and high pressure operations |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| CREP | Change of representative |
Representative=s name: HAMSOE PATENTBYRA ANS, POSTBOKS 171, 4302 SANDNES |
|
| FC2A | Withdrawal, rejection or dismissal of laid open patent application |