NL9201967A - Method and device for removing objects from the ground - Google Patents

Method and device for removing objects from the ground Download PDF

Info

Publication number
NL9201967A
NL9201967A NL9201967A NL9201967A NL9201967A NL 9201967 A NL9201967 A NL 9201967A NL 9201967 A NL9201967 A NL 9201967A NL 9201967 A NL9201967 A NL 9201967A NL 9201967 A NL9201967 A NL 9201967A
Authority
NL
Netherlands
Prior art keywords
pipe
ground
soil
vertical drainage
drainage pipes
Prior art date
Application number
NL9201967A
Other languages
Dutch (nl)
Other versions
NL193728B (en
NL193728C (en
Original Assignee
Martens En Van Oord B V
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Martens En Van Oord B V filed Critical Martens En Van Oord B V
Priority to NL9201967A priority Critical patent/NL193728C/en
Publication of NL9201967A publication Critical patent/NL9201967A/en
Publication of NL193728B publication Critical patent/NL193728B/en
Application granted granted Critical
Publication of NL193728C publication Critical patent/NL193728C/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D9/00Removing sheet piles bulkheads, piles, mould-pipes or other moulds or parts thereof
    • E02D9/02Removing sheet piles bulkheads, piles, mould-pipes or other moulds or parts thereof by withdrawing

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)
  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Abstract

The invention relates to a method for removing from the ground objects which extend substantially vertically into the ground, comprising the following steps: from ground level, driving a pipe which surrounds the object to be removed into the ground; and pulling the pipe upwards together with the enclosed ground and the object which is to be removed. The invention also relates to a device for removing from the ground objects which extend substantially vertically into the ground comprising: a pipe, a device for driving the pipe into the ground and pulling the pipe out of the ground. Using the abovementioned method and device, only a minimal quantity of ground has to be removed together with the object which is to be removed, so that the amount of energy consumed is minimal. It should be noted that the method can be carried out in a single operation, so that the number of machine hours and the amount of human labour are also low.

Description

WERKWIJZE EN INRICHTING VOOR HET VERWIJDEREN VAN LICHAMEN UIT DE GRONDMETHOD AND APPARATUS FOR REMOVING BODIES FROM THE GROUND

De uitvinding heeft betrekking op een werkwijze voor het uit de grond verwijderen van zich hoofdzakelijk vertikaal in de grond uitstrekkende lichamen.The invention relates to a method for removing from the ground mainly bodies extending vertically in the ground.

De uitvinding heeft eveneens betrekking op een inrichting voor het uit de grond verwijderen van zich hoofdzakelijk vertikaal in de grond uitstrekkende lichamen.The invention also relates to a device for removing from the ground substantially bodies extending vertically in the ground.

Der gelijke werkwijzen zijn algemeen bekend in de vorm van het bijvoorbeeld met een graafmachine graven van een gat en het tegelijkertijd met het graven van het gat verwijderen van de daarin aanwezige voorwerpen.Such methods are generally known in the form of, for example, digging a hole with an excavator and removing the objects present therein at the same time as digging the hole.

Het zal duidelijk zijn dat in het bijzonder bij langgerekte, zich hoofdzakelijk vertikaal in de grond uitstrekkende voorwerpen dit een omstandig karwei is. Om met een graafmachine een gat te kunnen graven moet het desbetreffende gat een minimale oppervlakte hebben die vele malen groter is dan die van het te verwijderen lichaam. Aldus wordt een grote hoeveelheid grond verplaatst, voordat het eigenlijke doel wordt bereikt. Het zal duidelijk zijn dat dit veel arbeid en veel machine-uren vergt en een groot energiegebruik met zich meebrengt. In het bijzonder moet bedacht worden dat, na het verwijderen van het lichaam, de uitgegraven grond weer naar zijn oorspronkelijke plaats moet worden teruggebracht.It will be clear that this is an elaborate task, in particular with elongated objects extending mainly vertically in the ground. In order to be able to dig a hole with an excavator, the hole in question must have a minimum surface area that is many times larger than that of the body to be removed. A large amount of soil is thus moved before the actual goal is reached. It will be clear that this takes a lot of labor and a lot of machine hours and involves a large energy consumption. In particular, it should be remembered that, after removing the body, the excavated soil must be returned to its original location.

Het doel van de onderhavige uitvinding is het verschaffen van een werkwijze en inrichting, waarbij bovengenoemde nadelen worden vermeden.The object of the present invention is to provide a method and device, wherein the above drawbacks are avoided.

Dit doel wordt bereikt door een werkwijze, omvattende de volgende stappen: het van het maaiveld af tot in de grond doen dringen van een het te verwijderen lichaam omringende pijp? en het tezamen met de omvatte grond en het te verwijderen lichaam omhoog trekken van de pijp.This object is achieved by a method comprising the following steps: penetrating a pipe surrounding the body to be removed from ground level? and pulling up the pipe together with the contained soil and the body to be removed.

Het doel wordt eveneens bereikt door een inrich- ting, omvattende: een pijp, een inrichting voor het tot in de grond doen dringen van de pijp en het uit de grond trekken van de pijp.The object is also achieved by a device comprising: a pipe, a device for pushing the pipe into the ground and pulling the pipe out of the ground.

Met behulp van bovengenoemde werkwijze en inrichting behoeft tezamen met het te verwijderen voorwerp slechts een minimale hoeveelheid grond te worden verwijderd, zodat de hoeveelheid gebruikte energie minimaal is. Hierbij zij opgemerkt dat de werkwijze in één enkele handeling kan plaatsvinden, zodat het aantal machine-uren en de hoeveelheid menselijke arbeid eveneens gering is.With the aid of the above-mentioned method and device, only a minimal amount of soil needs to be removed together with the object to be removed, so that the amount of energy used is minimal. It should be noted here that the method can take place in a single operation, so that the number of machine hours and the amount of human labor is also small.

Vervolgens zal de uitvinding worden toegelicht aan de hand van bijgaande tekeningen, waarin voorstellen: fig. 1: een doorsnede-aanzicht van een stuk grond, waarin vertikale drainagepijpen zijn aangebracht; fig. 2: een gedeeltelijk als doorsnede-aanzicht uitgevoerd schematisch perspectivisch aanzicht van een inrichting volgens de uitvinding; fig. 3: een gedeeltelijk als doorsnede-aanzicht uitgevoerd perspectivisch detailaanzicht van de in fig. 2 afgebeelde inrichting tijdens het in de grond dringen van de pijp; en fig. 4: een met fig. 3 overeenkomend aanzicht tijdens het uit de grond trekken van de pijp.The invention will be elucidated hereinbelow with reference to the annexed drawings, in which: fig. 1 shows a sectional view of a piece of ground in which vertical drainage pipes are arranged; fig. 2 is a schematic perspective view partly in cross-sectional view of a device according to the invention; fig. 3 is a partly detailed sectional perspective view of the device shown in fig. 2 during the penetration of the pipe; and fig. 4: a view corresponding with fig. 3 during the pulling of the pipe out of the ground.

De onderhavige uitvinding is onder meer van toepassing op situaties, waarin vertikale drainage wordt toegepast. Een dergelijke situatie is in fig. 1 afgebeeld. In fig. 1 is een stuk grond 1 afgebeeld, waarin vertikale drainagepijpen 2 zijn aangebracht.The present invention applies, inter alia, to situations where vertical drainage is used. Such a situation is shown in Fig. 1. Fig. 1 shows a piece of ground 1 in which vertical drainage pipes 2 are arranged.

Vertikale drainage vindt onder meer toepassing bij het verdichten van grond. Wanneer bijvoorbeeld bij het aanleggen van wegen of het plaatsen van gebouwen op een stuk grond een zware belasting komt te rusten, is het, afhankelijk van de omstandigheden zoals hoogte van het omringende land en vochtigheidsgraad van de grond, in sommige situaties aantrekkelijk de grond vooraf te verdichten door een grote hoeveelheid zand op het stuk grond te laten rusten gedurende enige tijd. Tijdens het verdich- tingsproces zal, afhankelijk van de vochtigheidsgraad en de grondsoort, in veel gevallen water vrijkomen, dat zonder verdere maatregelen op het grensvlak tussen grond en belasting vrijkomt, en daar de belasting kan doen schuiven, omdat de grond in een min of meer vloeibare toestand terechtkomt. Om dergelijke en eventuele andere problemen te voorkomen wordt veelal zogenaamde vertikale drainage toegepast. Zoals in fig. 1 is weergegeven, is in de grond, bijvoorbeeld door middel van grondboren een aantal vertikale drainagepijpen aangebracht, welke aan hun bovenste vrije einde met een horizontale afvoerpijp 3 zijn verbonden. In afhankelijkheid van de situatie kan een pomp 4 worden toegepast, in het bijzonder wanneer het vrijkomende drainagewater naar een grotere hoogte moet worden opgevoerd.Vertical drainage is used, among other things, for compacting soil. When, for example, the construction of roads or the construction of buildings on a piece of land puts a heavy load on it, it is attractive in some situations, depending on the circumstances such as the height of the surrounding land and the degree of moisture of the soil, to pre-soil the soil. compaction by resting a large amount of sand on the plot for some time. During the compaction process, depending on the degree of moisture and the soil type, water will in many cases be released, which will be released without further measures at the interface between soil and load, and can cause the load to slide there, because the soil in a more or less liquid state. So-called vertical drainage is often used to prevent such and any other problems. As shown in Fig. 1, a number of vertical drainage pipes, which are connected at their upper free end to a horizontal discharge pipe 3, are arranged in the ground, for example by means of earth drilling. Depending on the situation, a pump 4 can be used, in particular when the drainage water released has to be raised to a greater height.

Vervolgens wordt op het te verdichten stuk grond zand 5 aangebracht, waarna het verdichtingsproces kan aanvangen, hetgeen een tijdsduur in beslag neemt van enkele weken tot enkele maanden.Sand 5 is then applied to the piece of soil to be compacted, after which the compaction process can commence, which takes a period of time from a few weeks to a few months.

Daarna wordt het zand 5 weggeruimd, evenals de horizontale afvoerpijp 3. Vervolgens moeten de vertikale drainagepijpen 2 worden verwijderd.Then the sand 5 is removed as well as the horizontal discharge pipe 3. Then the vertical drainage pipes 2 must be removed.

Het is in principe wel mogelijk deze te laten zitten, doch wanneer het stuk grond 2 vervolgens belast wordt, blijft het gevaar van verdichting bestaan, zodat aan de bovenzijde van de vertikale drainagepijpen 2 water vrijkomt, zodat aldaar de aanwezige grond zal vervloeien en de op de verdichte grond aanwezige last zal gaan verschuiven.In principle it is possible to leave it, but when the piece of soil 2 is subsequently loaded, the danger of compaction remains, so that water is released at the top of the vertical drainage pipes 2, so that the soil present will flow there and the soil the compacted soil present will shift.

Om deze nadelen te vermijden moeten de vertikale drainagepijpen worden verwijderd. Hiertoe wordt gebruik gemaakt van een in fig. 2 afgebeelde inrichting. De inrichting omvat een graafmachine 6 die voorzien is van een draaibare, daaraan bevestigde giek 7, waarover een kabel 8 is aangebracht, waaraan een trilinrichting 9 is bevestigd. Aan de trilinrichting is een pijp 10 bevestigd die tot in de grond kan worden bewogen.The vertical drainage pipes must be removed to avoid these disadvantages. For this purpose use is made of a device shown in fig. 2. The device comprises an excavator 6 which is provided with a rotatable, attached boom 7, over which a cable 8 is mounted, to which a vibrating device 9 is attached. A pipe 10 is attached to the vibrating device and can be moved into the ground.

Een verdere verbinding tussen de pijp 10 en de trilinrichting 9 wordt gevormd door twee kettingen 11 die gebruikt worden bij het naar boven trekken van de pijp 10. In de pijp 10 is, in de nabijheid van het boveneinde daarvan, een aantal gaten 12 aangebracht.A further connection between the pipe 10 and the vibrating device 9 is formed by two chains 11 which are used in pulling the pipe 10 upwards. A number of holes 12 are arranged in the pipe 10, in the vicinity of the top end thereof.

Verder is een luchttoevoerinrichting aangebracht die gevormd wordt door een op de graafmachine bevestigde compressor 13 en een daarop aangesloten luchtleiding 14 die via de binnenzijde van de pijp 10 gevoerd is, en aan de onderzijde van de pijp 10 uitmondt.Furthermore, an air supply device is provided, which is formed by a compressor 13 mounted on the excavator and an air pipe 14 connected thereto, which is fed via the inside of the pipe 10 and opens at the bottom of the pipe 10.

Zoals in de tekening is weergegeven, wordt de pijp 10 boven de te verwijderen vertikale drainpijp 2 aangebracht. Hiervoor wordt veelal gebruik gemaakt van een helper die het ondereinde van de pijp precies boven de te verwijderen drain aanbrengt.As shown in the drawing, the pipe 10 is placed above the vertical drain pipe 2 to be removed. For this, use is often made of a helper that places the bottom end of the pipe exactly above the drain to be removed.

Vervolgens wordt de trilinrichting 9 ingeschakeld, en dringt de pijp 10 zich als gevolg van de door de tril-inrichting 10 opgewekte trillingen naar beneden rondom de vertikale drainpijp 2. Dit proces, waarvan de benodigde tijdsduur, afhankelijk van de lengte van de pijp, in de grootteorde van een minuut ligt, en hetgeen in fig. 3 is afgebeeld, wordt voortgezet tot de pijp de vereiste diepte heeft bereikt. Een dergelijke situatie is in fig. 4 weergegeven .Subsequently, the vibrating device 9 is switched on, and the pipe 10 is forced downwards around the vertical drain pipe 2 as a result of the vibrations generated by the vibrating device 10. This process, of which the required time depends on the length of the pipe. the order of magnitude is one minute, and what is shown in Figure 3 continues until the pipe has reached the required depth. Such a situation is shown in Fig. 4.

Dan wordt de compressor 13 ingeschakeld, en wordt via de leiding 14 onder de pijp lucht geblazen, waarna de pijp 10 met behulp van de kabel 8 en de kettingen 11 naar boven wordt bewogen. Hierbij zal de in de pijp aanwezige grond mee worden genomen, evenals de in de grond aanwezige vertikale drainpijp 2. Wanneer de drainpijp, zoals in fig. 4 getekend is, zich tot een grotere diepte uitstrekt dan de pijp, zal de drainpijp afbreken. Vervolgens wordt de hele pijp naar boven bewogen. Aldus is de vertikale drainpijp, ten minste het bovenste deel ervan, verwijderd.Then the compressor 13 is switched on and air is blown under the pipe 14 via the pipe 14, after which the pipe 10 is moved upwards with the aid of the cable 8 and the chains 11. The soil present in the pipe will be taken along, as will the vertical drain pipe 2 present in the ground. When the drain pipe, as shown in Fig. 4, extends to a greater depth than the pipe, the drain pipe will break off. Then the whole pipe is moved upwards. Thus, the vertical drain pipe, at least its upper part, has been removed.

Vervolgens kan een volgende drainpijp worden verwijderd, waarbij dezelfde procedure wordt toegevoerd.A subsequent drain pipe can then be removed, the same procedure being applied.

De dan reeds in de pijp aanwezige grond wordt bij het naar beneden dringen van de pijp door de gaten 10 heen afgevoerd.The soil already present in the pipe is drained through the holes 10 when the pipe is pressed downwards.

Aldus bestaat de mogelijkheid tot het verzamelen van de drainageslangen, zodat bewezen kan worden dat de desbetreffende aantal drainageslangen is verwijderd.Thus it is possible to collect the drainage hoses, so that it can be proved that the relevant number of drainage hoses has been removed.

Alhoewel bovenstaand uitvoeringsvoorbeeld betrekking heeft op het verwijderen van drainageslangen, is de uitvinding eveneens van toepassing op het verwijderen van andere, langgerekte, zich hoofdzakelijk vertikaal uitstrekkende lichamen.Although the above exemplary embodiment relates to the removal of drainage hoses, the invention also applies to the removal of other, elongated, mainly vertically extending bodies.

Claims (9)

1. Werkwijze voor het uit de grond verwijderen van zich hoofdzakelijk vertikaal in de grond uitstrekkende lichamen, gekenmerkt door de volgende stappen: - het van het maaiveld af tot in de grond doen dringen van een het te verwijderen lichaam omringende pijp? en - het tezamen met de omvatte grond en het te verwijderen lichaam omhoog trekken van de pijp.Method for removing from the ground mainly bodies extending vertically in the ground, characterized by the following steps: - penetrating a pipe surrounding the body to be removed from ground level? and - pulling up the pipe together with the contained soil and the body to be removed. 2. Werkwijze volgens conclusie 1, met het kenmerk, dat de pijp tijdens het naar beneden dringen aan een trilling wordt onderworpen.Method according to claim 1, characterized in that the pipe is subjected to vibration during the downward movement. 3. Werkwijze volgens conclusie 1 of 2, met het kenmerk, dat, voordat de pijp omhoog wordt getrokken, onder de pijp perslucht wordt toegevoerd.Method according to claim 1 or 2, characterized in that before the pipe is pulled up, compressed air is supplied under the pipe. 4. Werkwijze volgens conclusie 3, met het kenmerk, dat bij het verwijderen van een volgende pijp de tijdens een eerste verwijdering in de pijp aangebrachte grond via in het bovenbste deel van de pijp aangebrachte openingen wordt verwijderd.Method according to claim 3, characterized in that when a subsequent pipe is removed, the soil placed in the pipe during a first removal is removed via openings provided in the upper part of the pipe. 5. Werkwijze volgens een van de voorafgaande conclusies, met het kenmerk, dat de te verwijderen lichamen door vertikale drainagepijpen worden gevormd.Method according to one of the preceding claims, characterized in that the bodies to be removed are formed by vertical drainage pipes. 6. Werkwijze volgens conclusie 5, met het kenmerk, dat de vertikale drainagepijpen uit de van de pijp afkomstige grond wordt verwijderd en dat de vertikale drainagepijpen worden verzameld.A method according to claim 5, characterized in that the vertical drainage pipes are removed from the soil coming from the pipe and the vertical drainage pipes are collected. 7. Werkwijze volgens conclusie 5 of 6, met het kenmerk, dat de vertikale drainagepijpen zich uitstrekken tot een grotere diepte dan de lengte van de pijp, en dat bij het naar boven bewegen van de pijp de drainageslang afbreekt.Method according to claim 5 or 6, characterized in that the vertical drainage pipes extend to a greater depth than the length of the pipe, and that the drainage hose breaks off when the pipe is moved upwards. 8. Inrichting voor het uit de grond verwijderen van zich hoofdzakelijk vertikaal in de grond uitstrekkende lichamen, gekenmerkt door: een pijp, een inrichting voor het tot in de grond doen dringen van de pijp en het uit de grond trekken van de pijp.8. Device for removing bodies substantially vertically extending into the ground from the ground, characterized by: a pipe, a device for pushing the pipe into the ground and pulling the pipe out of the ground. 9. Inrichting volgens conclusie 8, gekenmerkt door een van een giek voorziene graafmachine, waarbij aan de punt van de giek de pijp via een trilorgaan bevestigd is.Device according to claim 8, characterized by a boomed excavator, wherein the pipe is attached to the tip of the boom via a vibrating member.
NL9201967A 1992-11-10 1992-11-10 Device for removing bodies from the ground. NL193728C (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
NL9201967A NL193728C (en) 1992-11-10 1992-11-10 Device for removing bodies from the ground.

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
NL9201967A NL193728C (en) 1992-11-10 1992-11-10 Device for removing bodies from the ground.
NL9201967 1992-11-10

Publications (3)

Publication Number Publication Date
NL9201967A true NL9201967A (en) 1994-06-01
NL193728B NL193728B (en) 2000-04-03
NL193728C NL193728C (en) 2000-08-04

Family

ID=19861506

Family Applications (1)

Application Number Title Priority Date Filing Date
NL9201967A NL193728C (en) 1992-11-10 1992-11-10 Device for removing bodies from the ground.

Country Status (1)

Country Link
NL (1) NL193728C (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
NL7117628A (en) * 1971-12-22 1973-06-26
JPS60138116A (en) * 1983-12-26 1985-07-22 Teruo Koi Remover for driven pile
JPS615121A (en) * 1984-06-19 1986-01-10 Kajima Corp Drawing work of existing pile
JPS6192214A (en) * 1984-10-09 1986-05-10 Sanwa Kizai Co Ltd Method of pulling out pile
NL9000262A (en) * 1990-02-02 1991-09-02 Instituut Voor Funderingscontr Method of inserting component in ground - generates simultaneous vibration in anti-phase in component and ground

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
NL7117628A (en) * 1971-12-22 1973-06-26
JPS60138116A (en) * 1983-12-26 1985-07-22 Teruo Koi Remover for driven pile
JPS615121A (en) * 1984-06-19 1986-01-10 Kajima Corp Drawing work of existing pile
JPS6192214A (en) * 1984-10-09 1986-05-10 Sanwa Kizai Co Ltd Method of pulling out pile
NL9000262A (en) * 1990-02-02 1991-09-02 Instituut Voor Funderingscontr Method of inserting component in ground - generates simultaneous vibration in anti-phase in component and ground

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
PATENT ABSTRACTS OF JAPAN vol. 10, no. 151 (M-483)(2208) 31 Mei 1986 & JP,A,61 005 121 ( KAJIMA KENSETSU K.K. ) 10 Januari 1986 *
PATENT ABSTRACTS OF JAPAN vol. 10, no. 267 (M-516)(2323) 11 September 1986 & JP,A,61 92 214 ( SANWA KIZAI CO. LTD. ) 10 Mei 1986 *
PATENT ABSTRACTS OF JAPAN vol. 9, no. 300 (M-433)(2023) 27 November 1985 & JP,A,60 138 116 ( TERU KOI ) 22 Juli 1985 *

Also Published As

Publication number Publication date
NL193728B (en) 2000-04-03
NL193728C (en) 2000-08-04

Similar Documents

Publication Publication Date Title
US3859809A (en) Pipe burying ripper and method
JPS62502128A (en) Pile construction method and equipment for implementing this method
US3969904A (en) Method of laying a pipeline in a trench
NL9201967A (en) Method and device for removing objects from the ground
US2777294A (en) Method of laying pipe
US3986280A (en) Apparatus for forming a concrete wall
US5473793A (en) Method and apparatus for rejuvenating a drainfield or dry well
US5256005A (en) Method and apparatus for placing cementitious materials in earth excavations
CN108560551A (en) A kind of pile pulling sleeve and its application method
EP0921234A1 (en) Method and device for arranging a pile in a ground
NL8303613A (en) METHOD AND APPARATUS FOR THE ON-SITE MANUFACTURE OF ENLARGED CONCRETE POSTS
CN218479240U (en) Excavation construction device for reservoir box culvert foundation
JP2886373B2 (en) The management method in the vibration compaction method of the saturated sand ground
JPH08284158A (en) Application method of pile with water hole
US6238140B1 (en) Method for laying tile or pipe underground
JPH0472928B2 (en)
NL1009671C2 (en) Tank-installation method in ground
BE1011096A3 (en) METHOD AND DEVICE FOR ALMOST HORIZONTAL IN THE SOIL PLACING AN drain.
US6009958A (en) Soil sampling apparatus and a geological observation method using the same
JPS592189Y2 (en) Continuous concrete wall construction equipment
NL1013079C2 (en) Bicycle parking stand has at least one support on which at least one input slope and at least one accommodation component for the bicycle bar or similar are incorproated
SU1437483A1 (en) Method and apparatus for pressing-down holes in soil
JPS5922851B2 (en) Pile driving method
NL8900733A (en) Contaminated ground-removal method - pumps out mixture of drilling liquid and disturbed earth while boring holes
NL7903255A (en) Construction and placing of caisson - involves mixing injected water with soil under base, withdrawal of mixture by suction, filling of space with support mass

Legal Events

Date Code Title Description
A1B A search report has been drawn up
BC A request for examination has been filed
V1 Lapsed because of non-payment of the annual fee

Effective date: 20090601