US20120312417A1 - Method for packaging an no/n2 gaseous mixture - Google Patents
Method for packaging an no/n2 gaseous mixture Download PDFInfo
- Publication number
- US20120312417A1 US20120312417A1 US13/482,615 US201213482615A US2012312417A1 US 20120312417 A1 US20120312417 A1 US 20120312417A1 US 201213482615 A US201213482615 A US 201213482615A US 2012312417 A1 US2012312417 A1 US 2012312417A1
- Authority
- US
- United States
- Prior art keywords
- pressure
- bar
- gaseous
- container
- volume
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Abandoned
Links
- 238000000034 method Methods 0.000 title claims abstract description 43
- 238000004806 packaging method and process Methods 0.000 title claims abstract description 10
- 239000008246 gaseous mixture Substances 0.000 title abstract description 3
- IJGRMHOSHXDMSA-UHFFFAOYSA-N Atomic nitrogen Chemical compound N#N IJGRMHOSHXDMSA-UHFFFAOYSA-N 0.000 claims abstract description 48
- 229910052757 nitrogen Inorganic materials 0.000 claims abstract description 23
- 239000000203 mixture Substances 0.000 claims abstract description 22
- 239000007789 gas Substances 0.000 claims description 23
- 238000010926 purge Methods 0.000 claims description 12
- 229910000831 Steel Inorganic materials 0.000 claims description 3
- XAGFODPZIPBFFR-UHFFFAOYSA-N aluminium Chemical compound [Al] XAGFODPZIPBFFR-UHFFFAOYSA-N 0.000 claims description 3
- 229910052782 aluminium Inorganic materials 0.000 claims description 3
- 239000010959 steel Substances 0.000 claims description 3
- 239000000956 alloy Substances 0.000 claims 1
- 229910045601 alloy Inorganic materials 0.000 claims 1
- 125000004122 cyclic group Chemical group 0.000 claims 1
- 238000009434 installation Methods 0.000 description 5
- 239000007788 liquid Substances 0.000 description 2
- GNFTZDOKVXKIBK-UHFFFAOYSA-N 3-(2-methoxyethoxy)benzohydrazide Chemical compound COCCOC1=CC=CC(C(=O)NN)=C1 GNFTZDOKVXKIBK-UHFFFAOYSA-N 0.000 description 1
- 229910000838 Al alloy Inorganic materials 0.000 description 1
- FGUUSXIOTUKUDN-IBGZPJMESA-N C1(=CC=CC=C1)N1C2=C(NC([C@H](C1)NC=1OC(=NN=1)C1=CC=CC=C1)=O)C=CC=C2 Chemical compound C1(=CC=CC=C1)N1C2=C(NC([C@H](C1)NC=1OC(=NN=1)C1=CC=CC=C1)=O)C=CC=C2 FGUUSXIOTUKUDN-IBGZPJMESA-N 0.000 description 1
- 208000004248 Familial Primary Pulmonary Hypertension Diseases 0.000 description 1
- 206010064911 Pulmonary arterial hypertension Diseases 0.000 description 1
- VYPSYNLAJGMNEJ-UHFFFAOYSA-N Silicium dioxide Chemical compound O=[Si]=O VYPSYNLAJGMNEJ-UHFFFAOYSA-N 0.000 description 1
- 229910021536 Zeolite Inorganic materials 0.000 description 1
- PNEYBMLMFCGWSK-UHFFFAOYSA-N aluminium oxide Inorganic materials [O-2].[O-2].[O-2].[Al+3].[Al+3] PNEYBMLMFCGWSK-UHFFFAOYSA-N 0.000 description 1
- 238000007675 cardiac surgery Methods 0.000 description 1
- 239000000356 contaminant Substances 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 229910001873 dinitrogen Inorganic materials 0.000 description 1
- HNPSIPDUKPIQMN-UHFFFAOYSA-N dioxosilane;oxo(oxoalumanyloxy)alumane Chemical compound O=[Si]=O.O=[Al]O[Al]=O HNPSIPDUKPIQMN-UHFFFAOYSA-N 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 239000012530 fluid Substances 0.000 description 1
- 239000012535 impurity Substances 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 239000002808 molecular sieve Substances 0.000 description 1
- 201000008312 primary pulmonary hypertension Diseases 0.000 description 1
- 230000008695 pulmonary vasoconstriction Effects 0.000 description 1
- 238000000746 purification Methods 0.000 description 1
- 239000000741 silica gel Substances 0.000 description 1
- 229910002027 silica gel Inorganic materials 0.000 description 1
- URGAHOPLAPQHLN-UHFFFAOYSA-N sodium aluminosilicate Chemical compound [Na+].[Al+3].[O-][Si]([O-])=O.[O-][Si]([O-])=O URGAHOPLAPQHLN-UHFFFAOYSA-N 0.000 description 1
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 1
- 239000010457 zeolite Substances 0.000 description 1
Images
Classifications
-
- G—PHYSICS
- G05—CONTROLLING; REGULATING
- G05D—SYSTEMS FOR CONTROLLING OR REGULATING NON-ELECTRIC VARIABLES
- G05D11/00—Control of flow ratio
- G05D11/02—Controlling ratio of two or more flows of fluid or fluent material
- G05D11/13—Controlling ratio of two or more flows of fluid or fluent material characterised by the use of electric means
- G05D11/131—Controlling ratio of two or more flows of fluid or fluent material characterised by the use of electric means by measuring the values related to the quantity of the individual components
- G05D11/133—Controlling ratio of two or more flows of fluid or fluent material characterised by the use of electric means by measuring the values related to the quantity of the individual components with discontinuous action
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F17—STORING OR DISTRIBUTING GASES OR LIQUIDS
- F17C—VESSELS FOR CONTAINING OR STORING COMPRESSED, LIQUEFIED OR SOLIDIFIED GASES; FIXED-CAPACITY GAS-HOLDERS; FILLING VESSELS WITH, OR DISCHARGING FROM VESSELS, COMPRESSED, LIQUEFIED, OR SOLIDIFIED GASES
- F17C5/00—Methods or apparatus for filling containers with liquefied, solidified, or compressed gases under pressures
- F17C5/06—Methods or apparatus for filling containers with liquefied, solidified, or compressed gases under pressures for filling with compressed gases
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F17—STORING OR DISTRIBUTING GASES OR LIQUIDS
- F17C—VESSELS FOR CONTAINING OR STORING COMPRESSED, LIQUEFIED OR SOLIDIFIED GASES; FIXED-CAPACITY GAS-HOLDERS; FILLING VESSELS WITH, OR DISCHARGING FROM VESSELS, COMPRESSED, LIQUEFIED, OR SOLIDIFIED GASES
- F17C2201/00—Vessel construction, in particular geometry, arrangement or size
- F17C2201/05—Size
- F17C2201/056—Small (<1 m3)
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F17—STORING OR DISTRIBUTING GASES OR LIQUIDS
- F17C—VESSELS FOR CONTAINING OR STORING COMPRESSED, LIQUEFIED OR SOLIDIFIED GASES; FIXED-CAPACITY GAS-HOLDERS; FILLING VESSELS WITH, OR DISCHARGING FROM VESSELS, COMPRESSED, LIQUEFIED, OR SOLIDIFIED GASES
- F17C2201/00—Vessel construction, in particular geometry, arrangement or size
- F17C2201/05—Size
- F17C2201/058—Size portable (<30 l)
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F17—STORING OR DISTRIBUTING GASES OR LIQUIDS
- F17C—VESSELS FOR CONTAINING OR STORING COMPRESSED, LIQUEFIED OR SOLIDIFIED GASES; FIXED-CAPACITY GAS-HOLDERS; FILLING VESSELS WITH, OR DISCHARGING FROM VESSELS, COMPRESSED, LIQUEFIED, OR SOLIDIFIED GASES
- F17C2203/00—Vessel construction, in particular walls or details thereof
- F17C2203/06—Materials for walls or layers thereof; Properties or structures of walls or their materials
- F17C2203/0634—Materials for walls or layers thereof
- F17C2203/0636—Metals
- F17C2203/0639—Steels
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F17—STORING OR DISTRIBUTING GASES OR LIQUIDS
- F17C—VESSELS FOR CONTAINING OR STORING COMPRESSED, LIQUEFIED OR SOLIDIFIED GASES; FIXED-CAPACITY GAS-HOLDERS; FILLING VESSELS WITH, OR DISCHARGING FROM VESSELS, COMPRESSED, LIQUEFIED, OR SOLIDIFIED GASES
- F17C2203/00—Vessel construction, in particular walls or details thereof
- F17C2203/06—Materials for walls or layers thereof; Properties or structures of walls or their materials
- F17C2203/0634—Materials for walls or layers thereof
- F17C2203/0636—Metals
- F17C2203/0646—Aluminium
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F17—STORING OR DISTRIBUTING GASES OR LIQUIDS
- F17C—VESSELS FOR CONTAINING OR STORING COMPRESSED, LIQUEFIED OR SOLIDIFIED GASES; FIXED-CAPACITY GAS-HOLDERS; FILLING VESSELS WITH, OR DISCHARGING FROM VESSELS, COMPRESSED, LIQUEFIED, OR SOLIDIFIED GASES
- F17C2203/00—Vessel construction, in particular walls or details thereof
- F17C2203/06—Materials for walls or layers thereof; Properties or structures of walls or their materials
- F17C2203/0634—Materials for walls or layers thereof
- F17C2203/0636—Metals
- F17C2203/0648—Alloys or compositions of metals
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F17—STORING OR DISTRIBUTING GASES OR LIQUIDS
- F17C—VESSELS FOR CONTAINING OR STORING COMPRESSED, LIQUEFIED OR SOLIDIFIED GASES; FIXED-CAPACITY GAS-HOLDERS; FILLING VESSELS WITH, OR DISCHARGING FROM VESSELS, COMPRESSED, LIQUEFIED, OR SOLIDIFIED GASES
- F17C2221/00—Handled fluid, in particular type of fluid
- F17C2221/01—Pure fluids
- F17C2221/014—Nitrogen
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F17—STORING OR DISTRIBUTING GASES OR LIQUIDS
- F17C—VESSELS FOR CONTAINING OR STORING COMPRESSED, LIQUEFIED OR SOLIDIFIED GASES; FIXED-CAPACITY GAS-HOLDERS; FILLING VESSELS WITH, OR DISCHARGING FROM VESSELS, COMPRESSED, LIQUEFIED, OR SOLIDIFIED GASES
- F17C2221/00—Handled fluid, in particular type of fluid
- F17C2221/03—Mixtures
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F17—STORING OR DISTRIBUTING GASES OR LIQUIDS
- F17C—VESSELS FOR CONTAINING OR STORING COMPRESSED, LIQUEFIED OR SOLIDIFIED GASES; FIXED-CAPACITY GAS-HOLDERS; FILLING VESSELS WITH, OR DISCHARGING FROM VESSELS, COMPRESSED, LIQUEFIED, OR SOLIDIFIED GASES
- F17C2223/00—Handled fluid before transfer, i.e. state of fluid when stored in the vessel or before transfer from the vessel
- F17C2223/01—Handled fluid before transfer, i.e. state of fluid when stored in the vessel or before transfer from the vessel characterised by the phase
- F17C2223/0146—Two-phase
- F17C2223/0153—Liquefied gas, e.g. LPG, GPL
- F17C2223/0161—Liquefied gas, e.g. LPG, GPL cryogenic, e.g. LNG, GNL, PLNG
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F17—STORING OR DISTRIBUTING GASES OR LIQUIDS
- F17C—VESSELS FOR CONTAINING OR STORING COMPRESSED, LIQUEFIED OR SOLIDIFIED GASES; FIXED-CAPACITY GAS-HOLDERS; FILLING VESSELS WITH, OR DISCHARGING FROM VESSELS, COMPRESSED, LIQUEFIED, OR SOLIDIFIED GASES
- F17C2223/00—Handled fluid before transfer, i.e. state of fluid when stored in the vessel or before transfer from the vessel
- F17C2223/03—Handled fluid before transfer, i.e. state of fluid when stored in the vessel or before transfer from the vessel characterised by the pressure level
- F17C2223/033—Small pressure, e.g. for liquefied gas
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F17—STORING OR DISTRIBUTING GASES OR LIQUIDS
- F17C—VESSELS FOR CONTAINING OR STORING COMPRESSED, LIQUEFIED OR SOLIDIFIED GASES; FIXED-CAPACITY GAS-HOLDERS; FILLING VESSELS WITH, OR DISCHARGING FROM VESSELS, COMPRESSED, LIQUEFIED, OR SOLIDIFIED GASES
- F17C2225/00—Handled fluid after transfer, i.e. state of fluid after transfer from the vessel
- F17C2225/01—Handled fluid after transfer, i.e. state of fluid after transfer from the vessel characterised by the phase
- F17C2225/0107—Single phase
- F17C2225/0123—Single phase gaseous, e.g. CNG, GNC
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F17—STORING OR DISTRIBUTING GASES OR LIQUIDS
- F17C—VESSELS FOR CONTAINING OR STORING COMPRESSED, LIQUEFIED OR SOLIDIFIED GASES; FIXED-CAPACITY GAS-HOLDERS; FILLING VESSELS WITH, OR DISCHARGING FROM VESSELS, COMPRESSED, LIQUEFIED, OR SOLIDIFIED GASES
- F17C2225/00—Handled fluid after transfer, i.e. state of fluid after transfer from the vessel
- F17C2225/03—Handled fluid after transfer, i.e. state of fluid after transfer from the vessel characterised by the pressure level
- F17C2225/036—Very high pressure, i.e. above 80 bars
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F17—STORING OR DISTRIBUTING GASES OR LIQUIDS
- F17C—VESSELS FOR CONTAINING OR STORING COMPRESSED, LIQUEFIED OR SOLIDIFIED GASES; FIXED-CAPACITY GAS-HOLDERS; FILLING VESSELS WITH, OR DISCHARGING FROM VESSELS, COMPRESSED, LIQUEFIED, OR SOLIDIFIED GASES
- F17C2227/00—Transfer of fluids, i.e. method or means for transferring the fluid; Heat exchange with the fluid
- F17C2227/01—Propulsion of the fluid
- F17C2227/0128—Propulsion of the fluid with pumps or compressors
- F17C2227/0135—Pumps
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F17—STORING OR DISTRIBUTING GASES OR LIQUIDS
- F17C—VESSELS FOR CONTAINING OR STORING COMPRESSED, LIQUEFIED OR SOLIDIFIED GASES; FIXED-CAPACITY GAS-HOLDERS; FILLING VESSELS WITH, OR DISCHARGING FROM VESSELS, COMPRESSED, LIQUEFIED, OR SOLIDIFIED GASES
- F17C2227/00—Transfer of fluids, i.e. method or means for transferring the fluid; Heat exchange with the fluid
- F17C2227/03—Heat exchange with the fluid
- F17C2227/0302—Heat exchange with the fluid by heating
- F17C2227/0309—Heat exchange with the fluid by heating using another fluid
- F17C2227/0311—Air heating
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F17—STORING OR DISTRIBUTING GASES OR LIQUIDS
- F17C—VESSELS FOR CONTAINING OR STORING COMPRESSED, LIQUEFIED OR SOLIDIFIED GASES; FIXED-CAPACITY GAS-HOLDERS; FILLING VESSELS WITH, OR DISCHARGING FROM VESSELS, COMPRESSED, LIQUEFIED, OR SOLIDIFIED GASES
- F17C2227/00—Transfer of fluids, i.e. method or means for transferring the fluid; Heat exchange with the fluid
- F17C2227/04—Methods for emptying or filling
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F17—STORING OR DISTRIBUTING GASES OR LIQUIDS
- F17C—VESSELS FOR CONTAINING OR STORING COMPRESSED, LIQUEFIED OR SOLIDIFIED GASES; FIXED-CAPACITY GAS-HOLDERS; FILLING VESSELS WITH, OR DISCHARGING FROM VESSELS, COMPRESSED, LIQUEFIED, OR SOLIDIFIED GASES
- F17C2227/00—Transfer of fluids, i.e. method or means for transferring the fluid; Heat exchange with the fluid
- F17C2227/04—Methods for emptying or filling
- F17C2227/044—Methods for emptying or filling by purging
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F17—STORING OR DISTRIBUTING GASES OR LIQUIDS
- F17C—VESSELS FOR CONTAINING OR STORING COMPRESSED, LIQUEFIED OR SOLIDIFIED GASES; FIXED-CAPACITY GAS-HOLDERS; FILLING VESSELS WITH, OR DISCHARGING FROM VESSELS, COMPRESSED, LIQUEFIED, OR SOLIDIFIED GASES
- F17C2227/00—Transfer of fluids, i.e. method or means for transferring the fluid; Heat exchange with the fluid
- F17C2227/04—Methods for emptying or filling
- F17C2227/048—Methods for emptying or filling by maintaining residual pressure
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F17—STORING OR DISTRIBUTING GASES OR LIQUIDS
- F17C—VESSELS FOR CONTAINING OR STORING COMPRESSED, LIQUEFIED OR SOLIDIFIED GASES; FIXED-CAPACITY GAS-HOLDERS; FILLING VESSELS WITH, OR DISCHARGING FROM VESSELS, COMPRESSED, LIQUEFIED, OR SOLIDIFIED GASES
- F17C2265/00—Effects achieved by gas storage or gas handling
- F17C2265/01—Purifying the fluid
- F17C2265/012—Purifying the fluid by filtering
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F17—STORING OR DISTRIBUTING GASES OR LIQUIDS
- F17C—VESSELS FOR CONTAINING OR STORING COMPRESSED, LIQUEFIED OR SOLIDIFIED GASES; FIXED-CAPACITY GAS-HOLDERS; FILLING VESSELS WITH, OR DISCHARGING FROM VESSELS, COMPRESSED, LIQUEFIED, OR SOLIDIFIED GASES
- F17C2265/00—Effects achieved by gas storage or gas handling
- F17C2265/02—Mixing fluids
- F17C2265/025—Mixing fluids different fluids
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F17—STORING OR DISTRIBUTING GASES OR LIQUIDS
- F17C—VESSELS FOR CONTAINING OR STORING COMPRESSED, LIQUEFIED OR SOLIDIFIED GASES; FIXED-CAPACITY GAS-HOLDERS; FILLING VESSELS WITH, OR DISCHARGING FROM VESSELS, COMPRESSED, LIQUEFIED, OR SOLIDIFIED GASES
- F17C2270/00—Applications
- F17C2270/02—Applications for medical applications
- F17C2270/025—Breathing
Definitions
- Gaseous NO/N 2 mixtures are commonly used to treat pulmonary vasoconstrictions in adults or children, particularly in new born infants suffering from primary pulmonary hypertension or in patients who have undergone cardiac surgery.
- NO/N 2 mixtures are conventionally packaged into steel gas cylinders.
- these cylinders contain, by volume, from 100 to 1000 ppm of NO, the remainder being nitrogen (N 2 ).
- N 2 nitrogen
- These cylinders usually have a water capacity of 2 to 50 litres, which means that a total charge of as much as 15 m 3 of NO/N 2 mixture can be admitted to them.
- the packaging of these mixtures which means the filling of cylinders with these mixtures, is done at gas filling centres.
- the problem is therefore that of providing an improved packaging method that makes it possible to ensure good accuracy and increased reliability of the gaseous mixture thus manufactured and packaged.
- the solution of the invention is therefore a method for packaging a gaseous NO/N 2 mixture into a container, in particular one or more gas cylinders, comprising the following steps:
- the method of the invention may have one or more of the following technical features:
- the pressures quoted are absolute pressures.
- FIG. 1 schematically illustrates one embodiment of the method according to the present invention
- FIG. 2 is the diagram of an installation for implementing the method of the invention.
- FIG. 1 schematically depicts one embodiment of a packaging cycle that can be applied in the context of the method of packaging the gaseous NO/N 2 mixture of the present invention.
- this packaging cycle comprises several successive steps, spaced out over time from T 0 to T 13 , and which are applied to each cylinder and are detailed hereinbelow.
- the flexible hoses of the installation are vented to the open air, which means to say that the internal volume of the flexible filling hoses is placed in fluidic communication with the ambient atmosphere in order to remove any possible residual raised pressure.
- the valve or valves of the gas containers connected to the hoses are closed, so that there is no exchange of gas with the container or containers. This corresponds to step f) of the method.
- a vacuum pump is used to place the inside of the flexible hoses under connected depression, i.e. under a pressure below atmospheric pressure, for example of the order of 0.15 bar, thus making it possible to remove any residual gas and/or air contained therein.
- This phase is therefore also performed with the cylinder valve closed.
- Placing the flexible hoses under vacuum is a safety measure which makes it possible to check that all the hoses are correctly connected and that there are no leaks. Specifically, if there was a leak or if a hose was incorrectly connected, it would not be possible to establish the stable vacuum. This corresponds to step g) of the method schematically illustrated in FIG. 1 .
- the operator opens the valve on each cylinder and the residual pressure present in each cylinder then rises and reaches the pressure sensor, which detects the said rise in pressure.
- the residual pressure in the cylinder is of the order of around 3 to 4 bar absolute.
- each cylinder is vented to the atmosphere, i.e. the gas contained in the cylinder is allowed to escape to the external atmosphere under the simple effect of the difference in pressure between the inside and the outside of the cylinder, so as to decrease the internal pressure of the cylinder to atmospheric pressure.
- the internal pressure of the gas cylinder is therefore more or less equal to atmospheric pressure (1 atm 32 around 1 bar absolute), i.e. of the order of 1 to 1.5 bar abs.
- the cylinder is rinsed with nitrogen while its internal pressure is raised to around 10 bar.
- the addition of nitrogen is performed via a gas line and/or a store of nitrogen under pressure so as to raise the internal pressure of the cylinder to the desired pressure. This corresponds to step d) of the method of the invention.
- the cylinder is purged by placing its internal volume under depression by withdrawing the residual gas contained therein using a vacuum pump until an internal depression of below 0.2 bar abs, preferably of below 0.1 bar, for example of the order of 0.05 bar, is reached. This corresponds to a further step e) of the method of the invention.
- the cylinder undergoes a further rinsing with nitrogen to raise its internal pressure to around 10 bar as between T 4 and T 5 . This corresponds to a further step d) of the method of the invention.
- the cylinder is once again discharged to the ambient atmosphere as during times T 5 and T 6 .
- the residual gas pressure is then kept at around 1.35 bar in order to avoid unwanted ingress of atmospheric contaminants. This corresponds to a further step c) of the method of the invention.
- a gaseous premix formed of NO and N 2 containing an NO content less than 10% by volume is admitted to the cylinder in order to reach a first filling pressure P 1 where P 1 >1 bar, typically a pressure P 1 of the order of 2 to 10 bar abs, preferably of around 3 to 5 bar abs, for example a pressure P 1 of the order of 4 bar.
- the gaseous premix formed of NO and N 2 contains an NO content of the order of 4% by volume. This corresponds to a step a) of the method of the invention.
- gaseous nitrogen is then admitted to the container containing the NO/N 2 premix at the first pressure P 1 in order to obtain a final gaseous NO/N 2 mixture containing an NO content less than or equal to 1200 ppm by volume, for example a final NO content of 200 to 800 ppm, and a second pressure P 2 of between P 1 and 800 bar, for example in this instance a pressure of 180 to 200 bar.
- a step b) of the method of the invention corresponds to a step b) of the method of the invention.
- This method can be implemented via an installation as described in FIG. 2 , fitted with one or more filling systems 14 for filling gas containers, i.e. gas cylinders 11 to 13 , comprising connecting means, in particular flexible pipes, allowing several containers to be filled at once, typically that allow simultaneous filling of 2 to 20 cylinders.
- gas containers i.e. gas cylinders 11 to 13
- connecting means in particular flexible pipes
- the nitrogen is stored in the reservoir 1 in liquid form and then withdrawn in liquid form by a cryogenic pump 2 which compresses it to a pressure of the order of 100 to 300 bar, before sending it to an atmospheric heater 3 where it is vaporized to yield gaseous nitrogen.
- a cryogenic pump 2 which compresses it to a pressure of the order of 100 to 300 bar, before sending it to an atmospheric heater 3 where it is vaporized to yield gaseous nitrogen.
- it comprises a main line or pipe 20 for carrying nitrogen from a reservoir 1 to the filling system 14 .
- the pressure in the line varies between around 100 bar immediately downstream of the outflow from the buffer volume into the cylinders and around 260 bar which corresponds to the threshold at which the pump is stopped.
- the nitrogen gas is then carried by the line 20 to a purification device 6 able to eliminate traces of O 2 and H 2 O, for example using a suitable molecular sieve, for example of the zeolite, silica gel, alumina or similar type, or mixtures thereof.
- a suitable molecular sieve for example of the zeolite, silica gel, alumina or similar type, or mixtures thereof.
- the line 20 is also fluidically connected to a buffer volume 4 capable of storing some of the gaseous nitrogen, and to backup racks 5 , each comprising several nitrogen cylinders.
- the installation also comprises a cabinet 16 comprising several cylinders 9 of an NO/N 2 premix, here containing 4% by volume of NO, which cylinders 9 are fluidically connected to the line 20 by an NO/N 2 premix supply line 22 .
- the NO/N 2 line 22 and the nitrogen line 20 are not connected directly to one another but are connected to the valve unit 8 which is itself connected by the line 21 to the filling system or systems 14 .
- the valves in the valve unit 8 make it possible to select the fluid with which the cylinders 11 to 13 of the system 14 are filled.
- the nitrogen line 20 and the NO/N 2 premix line 22 are therefore fluidically connected firstly by the valve unit 8 then a common section 21 to the filling system 14 .
- the valve unit 8 comprises valves, control elements controlled by the control device 10 , etc.
- Flow meters 7 make it possible to measure the quantity of N 2 and NO flowing through the lines 20 and 22 and to transmit the measured information to a control device 10 , such as a computer or the like.
- the installation also comprises a vent-to-atmosphere line 17 allowing the gases to be discharged to the ambient atmosphere, notably during the purge step or steps during which the internal volume of the container is placed in fluidic communication with the ambient atmosphere.
- a vacuum pump (not shown) allows the container or containers to be evacuated, i.e. allows their internal pressure to be reduced down to a pressure below atmospheric pressure, i.e. ⁇ 1 bar absolute.
Landscapes
- Engineering & Computer Science (AREA)
- Physics & Mathematics (AREA)
- General Physics & Mathematics (AREA)
- Automation & Control Theory (AREA)
- Mechanical Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Filling Or Discharging Of Gas Storage Vessels (AREA)
- Vacuum Packaging (AREA)
Abstract
Description
- This application claims the benefit of priority under 35 U.S.C. §119 (a) and (b) to French Application No. 1155037 filed Jun. 9, 2011, the entire contents of which are incorporated herein by reference.
- Gaseous NO/N2 mixtures are commonly used to treat pulmonary vasoconstrictions in adults or children, particularly in new born infants suffering from primary pulmonary hypertension or in patients who have undergone cardiac surgery.
- These NO/N2 mixtures are conventionally packaged into steel gas cylinders. Typically these cylinders contain, by volume, from 100 to 1000 ppm of NO, the remainder being nitrogen (N2). These cylinders usually have a water capacity of 2 to 50 litres, which means that a total charge of as much as 15 m3 of NO/N2 mixture can be admitted to them.
- The packaging of these mixtures, which means the filling of cylinders with these mixtures, is done at gas filling centres.
- However, given the low NO content in the mixture, which is typically of the order of a few hundred ppm by volume, it is not always easy to package these mixtures on an industrial scale and a sufficient accuracy of the mixture obtained is not always ensured.
- The problem is therefore that of providing an improved packaging method that makes it possible to ensure good accuracy and increased reliability of the gaseous mixture thus manufactured and packaged.
- The solution of the invention is therefore a method for packaging a gaseous NO/N2 mixture into a container, in particular one or more gas cylinders, comprising the following steps:
- a) introducing into a container a gaseous premix formed of NO and N2 containing an NO content less than 10% by volume until a first pressure P1 is reached where P1>1 bar abs;
- b) introducing into the container containing the NO/N2 premix at the first pressure P1 gaseous nitrogen until a final gaseous NO/N2 mixture containing an NO content less than or equal to 1200 ppm by volume and a second pressure P2 of between P1 and 800 bar are achieved.
- Depending on circumstance the method of the invention may have one or more of the following technical features:
-
- The first pressure P1 is between 2 and 10 bar, preferably less than or equal to 5 bar.
- The second pressure is between 100 and 700 bar, preferably at least 200 bar.
- The gaseous premix formed of NO and N2 contains an NO content less than or equal to 8% by volume.
- The gaseous premix formed of NO and N2 contains an NO content less than or equal to 5% by volume.
- The gaseous premix made up of NO and N2 contains an NO content of the order of 4% by volume and the first pressure P1 is of the order of 2 to 10 bar abs, for example of the order of 2 to 5 bar abs.
- Step a) is preceded by at least one step chosen from:
- a step of gaseous rinsing during which nitrogen is introduced into the container,
- a step of purging during which the internal volume of the container is placed in fluidic communication with the ambient atmosphere, and/or
- a step of evacuation during which the internal volume of the container is placed under depression (<atm pressure).
- The gaseous rinsing step comprises the introduction of gaseous nitrogen into the container so as to obtain a rinsing pressure of between 2 and 20 bar, preferably between 2 and 12 bar.
- During the purging step or steps, the internal volume of the container is in fluidic communication with the atmosphere while the internal pressure of the container is greater than a minimum purge pressure (Pmin) such that: 3.5 bar>Pmin>1 bar.
- The minimum purge pressure (Pmin) lies between 1.1 and 3 bar approximately.
- During at least one evacuating step, the internal volume of the container is placed in depression so as to reach a depression of less than 0.5 bar, preferably less than 0.2 bar.
- It comprises, prior to step a), a step of evacuation and a step of purging of at least one hose linking a filling system to a gas container.
- The final gaseous NO/N2 mixture contains an NO content less than or equal to 1000 ppm by volume, preferably the final gaseous NO/N2 mixture contains an NO content of between 200 and 1000 ppm by volume and more preferably still, of between 200 and 800 ppm by volume.
- It is performed using a gas container filling system comprising means of connection allowing several containers to be filled at once.
- The container is a gas cylinder, preferably a gas cylinder with a body made of steel, of aluminum or an aluminum alloy.
- In the context of the present invention, the pressures quoted are absolute pressures.
- The invention will now be better understood by virtue of the description given hereinafter with reference to the attached figures in which:
-
FIG. 1 schematically illustrates one embodiment of the method according to the present invention, and -
FIG. 2 is the diagram of an installation for implementing the method of the invention. -
FIG. 1 schematically depicts one embodiment of a packaging cycle that can be applied in the context of the method of packaging the gaseous NO/N2 mixture of the present invention. - As can be seen, this packaging cycle comprises several successive steps, spaced out over time from T0 to T13, and which are applied to each cylinder and are detailed hereinbelow.
- Between T0 and T1, the flexible hoses of the installation are vented to the open air, which means to say that the internal volume of the flexible filling hoses is placed in fluidic communication with the ambient atmosphere in order to remove any possible residual raised pressure. During this phase, the valve or valves of the gas containers connected to the hoses are closed, so that there is no exchange of gas with the container or containers. This corresponds to step f) of the method.
- Between T1 and T2, a vacuum pump is used to place the inside of the flexible hoses under connected depression, i.e. under a pressure below atmospheric pressure, for example of the order of 0.15 bar, thus making it possible to remove any residual gas and/or air contained therein. This phase is therefore also performed with the cylinder valve closed. Placing the flexible hoses under vacuum is a safety measure which makes it possible to check that all the hoses are correctly connected and that there are no leaks. Specifically, if there was a leak or if a hose was incorrectly connected, it would not be possible to establish the stable vacuum. This corresponds to step g) of the method schematically illustrated in
FIG. 1 . - Between T2 and T3, the operator opens the valve on each cylinder and the residual pressure present in each cylinder then rises and reaches the pressure sensor, which detects the said rise in pressure. Typically the residual pressure in the cylinder is of the order of around 3 to 4 bar absolute. Before T2, no gas rinsing of the container with nitrogen took place. This corresponds to step h) of the method schematically illustrated in
FIG. 1 . - Between T3 and T4, the actual treatment of each cylinder begins. More specifically, each cylinder is vented to the atmosphere, i.e. the gas contained in the cylinder is allowed to escape to the external atmosphere under the simple effect of the difference in pressure between the inside and the outside of the cylinder, so as to decrease the internal pressure of the cylinder to atmospheric pressure. This corresponds to a step c) of the method of the invention. At T4, the internal pressure of the gas cylinder is therefore more or less equal to atmospheric pressure (1 atm 32 around 1 bar absolute), i.e. of the order of 1 to 1.5 bar abs.
- Between T4 and T5, the cylinder is rinsed with nitrogen while its internal pressure is raised to around 10 bar. The addition of nitrogen is performed via a gas line and/or a store of nitrogen under pressure so as to raise the internal pressure of the cylinder to the desired pressure. This corresponds to step d) of the method of the invention.
- Between T5 and T6, the nitrogen contained in the cylinder is again allowed to escape to the atmosphere, which allows any impurities that might be present in the cylinder to be removed. This corresponds to a further purging step c) of the method of the invention.
- Between T6 and T7, the cylinder is purged by placing its internal volume under depression by withdrawing the residual gas contained therein using a vacuum pump until an internal depression of below 0.2 bar abs, preferably of below 0.1 bar, for example of the order of 0.05 bar, is reached. This corresponds to a further step e) of the method of the invention.
- Between T7 and T8, the cylinder undergoes a further rinsing with nitrogen to raise its internal pressure to around 10 bar as between T4 and T5. This corresponds to a further step d) of the method of the invention.
- Between T8 and T9, the cylinder is once again discharged to the ambient atmosphere as during times T5 and T6. The residual gas pressure is then kept at around 1.35 bar in order to avoid unwanted ingress of atmospheric contaminants. This corresponds to a further step c) of the method of the invention.
- Between T9 and T10, the cylinder once again undergoes additional rinsing with nitrogen to raise its internal pressure to around 10 bar, as before. This corresponds to a further step d) of the method of the invention.
- Between T10 and T11, the nitrogen is discharged into the atmosphere, as between T8 and T9 and between T5 and T6, but this time maintaining a residual internal pressure of the order of 3 bar. This corresponds to a step c) of the method of the invention.
- Between T11 and T12, a gaseous premix formed of NO and N2 containing an NO content less than 10% by volume is admitted to the cylinder in order to reach a first filling pressure P1 where P1>1 bar, typically a pressure P1 of the order of 2 to 10 bar abs, preferably of around 3 to 5 bar abs, for example a pressure P1 of the order of 4 bar. Advantageously, the gaseous premix formed of NO and N2 contains an NO content of the order of 4% by volume. This corresponds to a step a) of the method of the invention.
- Between T12 and T13, gaseous nitrogen is then admitted to the container containing the NO/N2 premix at the first pressure P1 in order to obtain a final gaseous NO/N2 mixture containing an NO content less than or equal to 1200 ppm by volume, for example a final NO content of 200 to 800 ppm, and a second pressure P2 of between P1 and 800 bar, for example in this instance a pressure of 180 to 200 bar. This corresponds to a step b) of the method of the invention.
- This method can be implemented via an installation as described in
FIG. 2 , fitted with one or more filling systems 14 for filling gas containers, i.e. gas cylinders 11 to 13, comprising connecting means, in particular flexible pipes, allowing several containers to be filled at once, typically that allow simultaneous filling of 2 to 20 cylinders. - The nitrogen is stored in the
reservoir 1 in liquid form and then withdrawn in liquid form by a cryogenic pump 2 which compresses it to a pressure of the order of 100 to 300 bar, before sending it to anatmospheric heater 3 where it is vaporized to yield gaseous nitrogen. As may be seen, it comprises a main line orpipe 20 for carrying nitrogen from areservoir 1 to the filling system 14. In fact, the pressure in the line varies between around 100 bar immediately downstream of the outflow from the buffer volume into the cylinders and around 260 bar which corresponds to the threshold at which the pump is stopped. - The nitrogen gas is then carried by the
line 20 to a purification device 6 able to eliminate traces of O2 and H2O, for example using a suitable molecular sieve, for example of the zeolite, silica gel, alumina or similar type, or mixtures thereof. - It should be noted that the
line 20 is also fluidically connected to a buffer volume 4 capable of storing some of the gaseous nitrogen, and to backup racks 5, each comprising several nitrogen cylinders. - Moreover, the installation also comprises a cabinet 16 comprising several cylinders 9 of an NO/N2 premix, here containing 4% by volume of NO, which cylinders 9 are fluidically connected to the
line 20 by an NO/N2premix supply line 22. In fact, the NO/N2 line 22 and thenitrogen line 20 are not connected directly to one another but are connected to thevalve unit 8 which is itself connected by theline 21 to the filling system or systems 14. The valves in thevalve unit 8 make it possible to select the fluid with which the cylinders 11 to 13 of the system 14 are filled. Thenitrogen line 20 and the NO/N2 premix line 22 are therefore fluidically connected firstly by thevalve unit 8 then acommon section 21 to the filling system 14. Thevalve unit 8 comprises valves, control elements controlled by thecontrol device 10, etc. - Flow meters 7 make it possible to measure the quantity of N2 and NO flowing through the
20 and 22 and to transmit the measured information to alines control device 10, such as a computer or the like. - The installation also comprises a vent-to-
atmosphere line 17 allowing the gases to be discharged to the ambient atmosphere, notably during the purge step or steps during which the internal volume of the container is placed in fluidic communication with the ambient atmosphere. - A vacuum pump (not shown) allows the container or containers to be evacuated, i.e. allows their internal pressure to be reduced down to a pressure below atmospheric pressure, i.e. <1 bar absolute.
- It will be understood that many additional changes in the details, materials, steps and arrangement of parts, which have been herein described in order to explain the nature of the invention, may be made by those skilled in the art within the principle and scope of the invention as expressed in the appended claims. Thus, the present invention is not intended to be limited to the specific embodiments in the examples given above.
Claims (20)
Applications Claiming Priority (2)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| FR1155037 | 2011-06-09 | ||
| FR1155037A FR2976259B1 (en) | 2011-06-09 | 2011-06-09 | PROCESS FOR CONDITIONING A NO / N2 GAS MIXTURE |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| US20120312417A1 true US20120312417A1 (en) | 2012-12-13 |
Family
ID=45999728
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| US13/482,615 Abandoned US20120312417A1 (en) | 2011-06-09 | 2012-05-29 | Method for packaging an no/n2 gaseous mixture |
Country Status (4)
| Country | Link |
|---|---|
| US (1) | US20120312417A1 (en) |
| EP (1) | EP2533125B1 (en) |
| CN (1) | CN102818115A (en) |
| FR (1) | FR2976259B1 (en) |
Cited By (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US20120312416A1 (en) * | 2011-06-09 | 2012-12-13 | Air Liquide Sante (International) | Method for packaging no/n2 mixtures, with prior purging and rinsing steps |
| US20120312418A1 (en) * | 2011-06-09 | 2012-12-13 | L'air Liquide, Societe Anonyme Pour I'etude Et I'exploitation Des Procedes Georges Claude | Installation for packaging no using mass flow meters |
| JP2015006982A (en) * | 2013-06-12 | 2015-01-15 | エール・リキード・サンテ(アンテルナスィオナル) | Method for producing nitrogen monoxide/nitrogen gaseous mixture intended for medical field |
| US9996090B2 (en) | 2013-05-17 | 2018-06-12 | Entegris, Inc. | Preparation of high pressure BF3/H2 mixtures |
Citations (10)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US5476115A (en) * | 1994-03-10 | 1995-12-19 | Praxair Technology, Inc. | Automatic gas blending system |
| US5540251A (en) * | 1994-02-01 | 1996-07-30 | Mayeaux; Paul H. | Precision gas blender |
| US5826632A (en) * | 1997-05-30 | 1998-10-27 | The Boc Group, Inc. | Dynamic gas cylinder filling process |
| US6152192A (en) * | 1998-02-11 | 2000-11-28 | Welding Company Of America | Controller for system for filling gas cylinders with single gas or gas mixture |
| US6655422B2 (en) * | 2001-09-26 | 2003-12-02 | Atnl, Inc. | Computer controlled apparatus and method of filling cylinders with gas |
| US20060060139A1 (en) * | 2004-04-12 | 2006-03-23 | Mks Instruments, Inc. | Precursor gas delivery with carrier gas mixing |
| US7328726B2 (en) * | 2006-01-20 | 2008-02-12 | Air Products And Chemicals, Inc. | Ramp rate blender |
| US7621302B2 (en) * | 2007-09-28 | 2009-11-24 | Airgas, Inc. | Coriolis dosing system for filling gas cylinders |
| US20100330207A1 (en) * | 2009-06-30 | 2010-12-30 | Ikaria Holdings, Inc. | Methods of treating term and near-term neonates having hypoxic respiratory failure associated with clinical or echocardiographic evidence of pulmonary hypertension |
| US20120312416A1 (en) * | 2011-06-09 | 2012-12-13 | Air Liquide Sante (International) | Method for packaging no/n2 mixtures, with prior purging and rinsing steps |
Family Cites Families (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US5901758A (en) * | 1997-04-30 | 1999-05-11 | The Boc Group, Inc. | Method of filling gas containers |
| FR2863912B1 (en) | 2003-12-17 | 2006-02-03 | Air Liquide Sante Int | DYNAMIC CONDITIONING OF HIGH-PRESSURE GASEOUS MIXTURES, PARTICULARLY OF N2O / O2 MIXTURE |
| US20080029093A1 (en) * | 2004-05-11 | 2008-02-07 | Alex Stenzler | Intermittent Dosing Of Nitric Oxide Gas |
| FR2890761B1 (en) * | 2005-09-12 | 2007-10-19 | Air Liquide | METHOD FOR SUPPLYING A GAS MIXTURE |
| FR2914393B1 (en) * | 2007-03-27 | 2009-07-17 | Air Liquide | METHOD AND DEVICE FOR PREPARING GAS BOTTLES UNDER PRESSURE. |
| CN201711148U (en) * | 2010-06-18 | 2011-01-19 | 大连市铭源全科技开发有限公司 | Convenient nitrogen intake reactor |
-
2011
- 2011-06-09 FR FR1155037A patent/FR2976259B1/en active Active
-
2012
- 2012-05-04 EP EP12166724.0A patent/EP2533125B1/en not_active Revoked
- 2012-05-29 US US13/482,615 patent/US20120312417A1/en not_active Abandoned
- 2012-06-08 CN CN2012101891409A patent/CN102818115A/en active Pending
Patent Citations (10)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US5540251A (en) * | 1994-02-01 | 1996-07-30 | Mayeaux; Paul H. | Precision gas blender |
| US5476115A (en) * | 1994-03-10 | 1995-12-19 | Praxair Technology, Inc. | Automatic gas blending system |
| US5826632A (en) * | 1997-05-30 | 1998-10-27 | The Boc Group, Inc. | Dynamic gas cylinder filling process |
| US6152192A (en) * | 1998-02-11 | 2000-11-28 | Welding Company Of America | Controller for system for filling gas cylinders with single gas or gas mixture |
| US6655422B2 (en) * | 2001-09-26 | 2003-12-02 | Atnl, Inc. | Computer controlled apparatus and method of filling cylinders with gas |
| US20060060139A1 (en) * | 2004-04-12 | 2006-03-23 | Mks Instruments, Inc. | Precursor gas delivery with carrier gas mixing |
| US7328726B2 (en) * | 2006-01-20 | 2008-02-12 | Air Products And Chemicals, Inc. | Ramp rate blender |
| US7621302B2 (en) * | 2007-09-28 | 2009-11-24 | Airgas, Inc. | Coriolis dosing system for filling gas cylinders |
| US20100330207A1 (en) * | 2009-06-30 | 2010-12-30 | Ikaria Holdings, Inc. | Methods of treating term and near-term neonates having hypoxic respiratory failure associated with clinical or echocardiographic evidence of pulmonary hypertension |
| US20120312416A1 (en) * | 2011-06-09 | 2012-12-13 | Air Liquide Sante (International) | Method for packaging no/n2 mixtures, with prior purging and rinsing steps |
Cited By (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US20120312416A1 (en) * | 2011-06-09 | 2012-12-13 | Air Liquide Sante (International) | Method for packaging no/n2 mixtures, with prior purging and rinsing steps |
| US20120312418A1 (en) * | 2011-06-09 | 2012-12-13 | L'air Liquide, Societe Anonyme Pour I'etude Et I'exploitation Des Procedes Georges Claude | Installation for packaging no using mass flow meters |
| US8636040B2 (en) * | 2011-06-09 | 2014-01-28 | L'Air Liquide, Société Anonyme pour l'Etude et l'Exploitation des Procédés Georges Claude | Installation for packaging NO using mass flow meters |
| US9996090B2 (en) | 2013-05-17 | 2018-06-12 | Entegris, Inc. | Preparation of high pressure BF3/H2 mixtures |
| JP2015006982A (en) * | 2013-06-12 | 2015-01-15 | エール・リキード・サンテ(アンテルナスィオナル) | Method for producing nitrogen monoxide/nitrogen gaseous mixture intended for medical field |
| US9526744B2 (en) | 2013-06-12 | 2016-12-27 | L'Air Liquide, Société Anonyme our l'Etude et l'Exploitation des Procédés Georges Claude | Method for producing NO/N2 gaseous mixtures intended for the medical field |
Also Published As
| Publication number | Publication date |
|---|---|
| CN102818115A (en) | 2012-12-12 |
| EP2533125A1 (en) | 2012-12-12 |
| EP2533125B1 (en) | 2016-06-29 |
| FR2976259B1 (en) | 2013-07-05 |
| FR2976259A1 (en) | 2012-12-14 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN104713684B (en) | The ultralow temperature leak test method of accumulator | |
| JP2022539069A (en) | Systems and methods for detecting possible loss of integrity of flexible bags for biopharmaceutical products | |
| US20120312417A1 (en) | Method for packaging an no/n2 gaseous mixture | |
| CN107575731B (en) | Automatic filling system for producing high-purity tungsten hexafluoride and application method thereof | |
| KR101912981B1 (en) | Combination of a container for a liquid foodstuff and a quantity of propellant and use of a propellant | |
| US20120312418A1 (en) | Installation for packaging no using mass flow meters | |
| CN114033965B (en) | Filling control system for single-component or multi-component gas | |
| WO2009066139A2 (en) | Gas supply system | |
| US20120312416A1 (en) | Method for packaging no/n2 mixtures, with prior purging and rinsing steps | |
| JP7473715B2 (en) | Filling method and filling device | |
| CN102628546A (en) | Cold trap system for purifying and filling silane | |
| JP2026001141A (en) | Leak inspection method for a sealed container with a narrow opening and leak inspection device for carrying out the method | |
| CN111777027A (en) | Novel liquid filling equipment | |
| CN105546338B (en) | Residual gas retracting device in a kind of transfer cask | |
| CN219263940U (en) | Xenon cryogenic recovery device | |
| EP3863958B1 (en) | Bag-in-keg containers for filling with a liquid product | |
| CN113418666A (en) | Sealing performance tester containing gas buffering and impact testing structure | |
| JP2007085807A (en) | Gas barrier property evaluation method of plastic bottle and container and apparatus used therefor | |
| CN115015442A (en) | Laboratory gas chromatograph calibration device and method based on gradient oil sample calibration method | |
| CN106969260A (en) | A kind of LNG cold pump sump gas extraction system and control method | |
| JP6658463B2 (en) | Gas tank inspection equipment | |
| JP2015004636A (en) | Method of inspecting inflation of high-pressure tank | |
| CN216612516U (en) | An oil storage tank for hydrophilic lubricating oil | |
| JP2000352539A (en) | Method for correcting measured value of and apparatus for correcting measured value of gas pressure, and method for detecting and apparatus for detecting air leak of sealed container using the same | |
| Schön | Compressed gas cylinders |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| AS | Assignment |
Owner name: L'AIR LIQUIDE SOCIETE ANONYME POUR L'ETUDE ET L'EX Free format text: ASSIGNMENT OF ASSIGNORS INTEREST;ASSIGNORS:DE VILLEMEUR, PIERRE;ZERBINATTI, CELSO;SAMIRANT, JOEL;SIGNING DATES FROM 20120420 TO 20120423;REEL/FRAME:028282/0423 Owner name: AIR LIQUIDE SANTE (INTERNATIONAL), FRANCE Free format text: ASSIGNMENT OF ASSIGNORS INTEREST;ASSIGNORS:DE VILLEMEUR, PIERRE;ZERBINATTI, CELSO;SAMIRANT, JOEL;SIGNING DATES FROM 20120420 TO 20120423;REEL/FRAME:028282/0423 |
|
| STCB | Information on status: application discontinuation |
Free format text: ABANDONED -- FAILURE TO RESPOND TO AN OFFICE ACTION |