[go: up one dir, main page]

DE20200446U1 - Profile rail system - Google Patents

Profile rail system

Info

Publication number
DE20200446U1
DE20200446U1 DE20200446U DE20200446U DE20200446U1 DE 20200446 U1 DE20200446 U1 DE 20200446U1 DE 20200446 U DE20200446 U DE 20200446U DE 20200446 U DE20200446 U DE 20200446U DE 20200446 U1 DE20200446 U1 DE 20200446U1
Authority
DE
Germany
Prior art keywords
skirting board
webs
base rail
rail system
profile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
DE20200446U
Other languages
German (de)
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Herm Friedr Kuenne GmbH and Co
Original Assignee
Herm Friedr Kuenne GmbH and Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Herm Friedr Kuenne GmbH and Co filed Critical Herm Friedr Kuenne GmbH and Co
Priority to DE20200446U priority Critical patent/DE20200446U1/en
Publication of DE20200446U1 publication Critical patent/DE20200446U1/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F19/00Other details of constructional parts for finishing work on buildings
    • E04F19/02Borders; Finishing strips, e.g. beadings; Light coves
    • E04F19/04Borders; Finishing strips, e.g. beadings; Light coves for use between floor or ceiling and wall, e.g. skirtings
    • E04F19/0459Borders; Finishing strips, e.g. beadings; Light coves for use between floor or ceiling and wall, e.g. skirtings characterised by the fixing method
    • E04F19/0463Plinths fixed by snap-action in a direction perpendicular to the wall
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F19/00Other details of constructional parts for finishing work on buildings
    • E04F19/02Borders; Finishing strips, e.g. beadings; Light coves
    • E04F19/04Borders; Finishing strips, e.g. beadings; Light coves for use between floor or ceiling and wall, e.g. skirtings
    • E04F19/0459Borders; Finishing strips, e.g. beadings; Light coves for use between floor or ceiling and wall, e.g. skirtings characterised by the fixing method
    • E04F19/0468Plinths fixed by hooking in a direction parallel to the wall
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G3/00Installations of electric cables or lines or protective tubing therefor in or on buildings, equivalent structures or vehicles
    • H02G3/02Details
    • H02G3/04Protective tubing or conduits, e.g. cable ladders or cable troughs
    • H02G3/0425Plinths
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F19/00Other details of constructional parts for finishing work on buildings
    • E04F19/02Borders; Finishing strips, e.g. beadings; Light coves
    • E04F19/04Borders; Finishing strips, e.g. beadings; Light coves for use between floor or ceiling and wall, e.g. skirtings
    • E04F2019/0404Borders; Finishing strips, e.g. beadings; Light coves for use between floor or ceiling and wall, e.g. skirtings characterised by the material
    • E04F2019/0413Borders; Finishing strips, e.g. beadings; Light coves for use between floor or ceiling and wall, e.g. skirtings characterised by the material of metal
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F19/00Other details of constructional parts for finishing work on buildings
    • E04F19/02Borders; Finishing strips, e.g. beadings; Light coves
    • E04F19/04Borders; Finishing strips, e.g. beadings; Light coves for use between floor or ceiling and wall, e.g. skirtings
    • E04F2019/044Borders; Finishing strips, e.g. beadings; Light coves for use between floor or ceiling and wall, e.g. skirtings with conduits

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Installation Of Indoor Wiring (AREA)
  • Details Of Indoor Wiring (AREA)

Description

ProfilschienensystemProfile rail system

Die Neuerung betrifft ein Profilschienensystem, bestehend aus einer an einer Wand festlegbaren Basisschiene und einer darauf aufsteckbaren Sockelleiste.The innovation concerns a profile rail system consisting of a base rail that can be fixed to a wall and a skirting board that can be attached to it.

Der Neuerung liegt die Aufgabe zugrunde, ein Profilschienensystem der eingangs genannten Art zu schaffen, welches kostengünstig herstellbar, einfach zu montieren ist und eine erhöhte Funktionalität aufweist.The innovation is based on the task of creating a profile rail system of the type mentioned above, which is cost-effective to produce, easy to install and has increased functionality.

Diese Aufgabe wird neuerungsgemäß mit den Merkmalen des Schutzanspruchs 1 gelöst.This problem is solved according to the innovation with the features of claim 1.

Das Profilschienensystem gemäß Anspruch 1 besteht aus einer an einer Wand festlegbaren Basisschiene mit L-förmigem Querschnitt, die von einem horizontalen und einem vertikalen Schenkel gebildet ist. Diese BasisschieneThe profile rail system according to claim 1 consists of a base rail with an L-shaped cross-section that can be fixed to a wall and is formed by a horizontal and a vertical leg. This base rail

ist sehr einfach an der Wand zu montieren, wobei insbesondere daran gedacht ist, diese mit der Wand über Dübel zu verschrauben oder ggf. zu verkleben. Auf die Basisschiene ist eine diese abdeckende Sockelleiste aufsteckbar, so daß im fertig montierten Zustand des Profilschienensystems nur die Sockelleiste von außen sichtbar ist. Es reicht daher aus, nur die Sockelleiste bzw. nur deren Außenseite mit einer ästhetisch ansprechenden Oberfläche zu versehen, zumal die Basisschiene von dieser verdeckt ist. Um die Sockelleiste leicht an der Basisschiene montieren· zu können, sind an dieser Stege angeformt, von denen mindestens einer von einem Steg der Sockelleiste hintergreifbar ist. Durch diese Verbindung wird gewährleistet, daß sich die Sockelleiste nicht in horizontaler Richtung von der Basisschiene lösen kann. Mindestens einer der Stege der Basisschiene dient als Widerlager zur Abstützung der Sockelleiste, so daß die Sockelleiste gegenüber horizontal wirkenden Kräften absolut festgelegt ist. Dies ist insbesondere beim Einsatz des Profilschienensystems an unebenen Wänden wichtig, da nur durch das Widerlager eine paßgerechte Montage der Sockelleiste an der Profilschiene gegeben ist. Mindestens einer der Stege der Sockelleiste bzw. der Basisschiene ist federnd und in Steckrichtung der Sockelleiste betrachtet- hinterschnitten ausgebildet. Dies gewährleistet eine sichere Arretierung der Sockelleiste an der Basisschiene, ohne daß weitere Haltemittel hierzu erforderlich wären. Um die Funktionalität des Profilschienensystems zu erhöhen, ist in der Basisschiene zusätzlich ein Kabelkanal ausgebildet. Dabei wird zur Einsparung von Herstellungskosten und Material einer der bereits vorhandenen Stege der Basis-is very easy to mount on the wall, whereby it is particularly important to screw it to the wall using dowels or, if necessary, to glue it. A skirting board covering the base rail can be attached to it, so that when the profile rail system is fully assembled, only the skirting board is visible from the outside. It is therefore sufficient to provide only the skirting board or only its outside with an aesthetically pleasing surface, especially since the base rail is covered by it. In order to be able to mount the skirting board easily on the base rail, bars are formed on it, at least one of which can be gripped behind by a bar on the skirting board. This connection ensures that the skirting board cannot come loose from the base rail in a horizontal direction. At least one of the bars on the base rail serves as an abutment to support the skirting board, so that the skirting board is absolutely fixed against horizontal forces. This is particularly important when using the profile rail system on uneven walls, since only the abutment ensures that the skirting board can be fitted correctly to the profile rail. At least one of the baseboard or base rail webs is spring-loaded and undercut when viewed in the direction of the baseboard. This ensures that the baseboard is securely locked to the base rail without the need for any additional retaining devices. To increase the functionality of the profile rail system, a cable duct is also provided in the base rail. To save on manufacturing costs and material, one of the existing base rail webs is

;;. &idigr;&idigr;'&iacgr; Ii*!;;. &idigr;&idigr;'&iacgr; II*!

-3--3-

schiene zusammen mit deren vertikalem Schenkel genutzt. Dies läßt sich sehr einfach dadurch bewerkstelligen, daß der entsprechende Steg zumindest im Teilbereich nach oben gebogen ist.rail together with its vertical leg. This can be achieved very easily by bending the corresponding web upwards at least in part.

Um insbesondere die Herstellung des Profilschienensystems nach dem kostengünstigen Extrudierverfahren zu vereinfachen, ist es gemäß Anspruch 2 günstig, den federnden Steg in einem spitzen Winkel zur Aufsteckrichtung der Sockelleiste anzustellen. Damit kann dieser Steg einen konstanten Querschnitt aufweisen, so daß sich für alle Bereiche des Profilschienensystems eine gleichbleibende Abkühlrate ergibt. Dadurch wird eine rasche und folglich kostengünstige Herstellung des Profilschienensystems erreicht.In order to simplify the manufacture of the profile rail system using the cost-effective extrusion process, it is advantageous according to claim 2 to position the resilient web at an acute angle to the direction in which the skirting board is attached. This web can therefore have a constant cross-section, so that a constant cooling rate is achieved for all areas of the profile rail system. This enables the profile rail system to be manufactured quickly and therefore cost-effectively.

Um eine gute Arretierwirkung der Sockelleiste an der Basisschiene zu gewährleisten, ist es gemäß Anspruch 3 günstig, wenn mindestens einer der federnden Stege eine Zahnprofilierung aufweist. Diese Zahnprofilierung ist dabei quer zur Aufsteckrichtung der Sockelleiste ausgerichtet, so daß sich eine vorteilhafte Verrastung der Sockelleiste an der Basisschiene ergibt.In order to ensure a good locking effect of the skirting board on the base rail, it is advantageous according to claim 3 if at least one of the resilient webs has a tooth profile. This tooth profile is aligned transversely to the direction in which the skirting board is attached, so that an advantageous locking of the skirting board on the base rail is achieved.

Um die Montierbarkeit der Sockelleiste an der Basisschiene zu vereinfachen, ist es gemäß Anspruch 4 günstig, wenn mindestens einer der Stege eine Einführschräge aufweist. Diese Einführschräge sorgt dafür, daß selbst bei ungünstiger Lage der Sockelleiste ein exaktes Aufschieben auf die Basisschiene gewährleistet ist.In order to simplify the installation of the skirting board on the base rail, it is advantageous according to claim 4 if at least one of the webs has an insertion bevel. This insertion bevel ensures that even if the skirting board is in an unfavorable position, it is precisely pushed onto the base rail.

Eine besonders einfache und gleichzeitig platzsparende Ausführung des Profilschienensystems ergibt sich aus Anspruch 5. Dabei bildet der den Kabelkanal begrenzende Steg gleichzeitig das Widerlager für die Sockelleiste, so daß nahezu die gesamte lichte Weite zwischen der Sockelleiste und der Basisschiene für den Kabelkanal zur Verfügung steht. Das Profilschienensystem kann in diesem Fall optimal zur Verlegung der Kabel eingesetzt werden.A particularly simple and at the same time space-saving design of the profile rail system results from claim 5. The web that limits the cable duct simultaneously forms the abutment for the skirting board, so that almost the entire clear width between the skirting board and the base rail is available for the cable duct. In this case, the profile rail system can be used optimally for laying the cables.

Um einen kompakten und damit platzsparenden Aufbau des Profilschienensystems zu gewährleisten, ist es gemäß Anspruch 6 vorteilhaft, wenn der den Kabelkanal begrenzende Steg stufenartig geformt ist. Auf diese Weise bildet der Steg einen Freiraum, in den der federnde Steg während der Montage eingreifen kann. Damit kann der zur Verfügung stehende Raum optimal zur Bildung des Kabelkanals ausgenutzt werden. Insbesondere ist daran gedacht, den., im Querschnitt eingeschränkten Bereich des Kabelkanals zur Verlegung entsprechend dünner Kabel zu nutzen.In order to ensure a compact and thus space-saving construction of the profile rail system, it is advantageous according to claim 6 if the web delimiting the cable duct is shaped like a step. In this way, the web forms a free space into which the spring web can engage during assembly. This allows the available space to be used optimally to form the cable duct. In particular, the idea is to use the area of the cable duct with a restricted cross-section to lay correspondingly thin cables.

Ein besonders einfacher Aufbau des Profilschienensystems ergibt sich, wenn gemäß Anspruch 7 einer der Stege der Basisschiene sowohl vom federnden Steg der Sockelleiste hintergriffen ist als auch das Widerlager für die Sockelleiste bildet. Damit wird einer der Stege für zwei Funktionen ausgenutzt, wodurch sich ein besonders kompakter Aufbau des Profilschienensystems ergibt.A particularly simple structure of the profile rail system is achieved if, according to claim 7, one of the webs of the base rail is engaged behind by the spring web of the skirting board and also forms the abutment for the skirting board. This means that one of the webs is used for two functions, resulting in a particularly compact structure of the profile rail system.

Schließlich ist es gemäß Anspruch 8 vorteilhaft, den Kabelkanal zur Aufnahme mehrerer Kabel auszubilden. DamitFinally, according to claim 8, it is advantageous to design the cable duct to accommodate several cables.

läßt sich das Profilschienensystem sehr universell einsetzen. The profile rail system can be used very universally.

Unterschiedliche Ausführungsformen des Neuerungsgegenstandes werden beispielhaft anhand der Zeichnung erläutert, ohne den Schutzumfang zu beschränken.Different embodiments of the innovated object are explained by way of example using the drawing, without limiting the scope of protection.

Es zeigt:It shows:

Figur 1 eine Schnittdarstellung durch ein Profilschienensystem beim Einlegen von Kabeln,Figure 1 is a sectional view of a profile rail system when inserting cables,

Figur 2 das Profilschienensystem gemäß Figur 1 bei der Montage der Sockelleiste,Figure 2 the profile rail system according to Figure 1 during installation of the skirting board,

Figur 3 das Profilschienensystem gemäß Figur 2 in fertig montierter Lage,Figure 3 the profile rail system according to Figure 2 in the fully assembled position,

Figur 4 eine Schnittdarstellung einer ersten alternativen Ausführungsform des Profilschienensystems undFigure 4 is a sectional view of a first alternative embodiment of the profile rail system and

Figur 5 eine Schnittdarstellung durch eine zweite alternative Ausführungsform eines Profilschienensystems .Figure 5 is a sectional view through a second alternative embodiment of a profile rail system.

Figur 1 zeigt eine Schnittdarstellung eines Profilschienensystems 1, welches aus einer Basisschiene 2 und einer Sockelleiste 3 besteht. In der Basisschiene 2 sind Senklochbohrungen 4 zur Aufnahme von Schrauben 5 vorgesehen. Diese dienen zur Festlegung der Basisschiene 2 an einer Wand 6 mittels Dübel 7. Die Basisschiene 2 besitzt einen L-förmigen Querschnitt, wobei ein vertikaler Schenkel 8 an der Wand 6 und ein horizontaler Schenkel 9 an einem Boden 10 anliegt.Figure 1 shows a sectional view of a profile rail system 1, which consists of a base rail 2 and a skirting board 3. Countersunk holes 4 are provided in the base rail 2 for receiving screws 5. These are used to fix the base rail 2 to a wall 6 by means of dowels 7. The base rail 2 has an L-shaped cross-section, with a vertical leg 8 resting on the wall 6 and a horizontal leg 9 resting on a floor 10.

Um die Sockelleiste 3 leicht an der Basisschiene 2 festlegen zu können, weist letztere zwei nach oben leicht zur Wand geneigte Stege 11 auf. Diese Stege 11 sind von Stegen 12 der Sockelleiste 3 hintergreifbar, deren freies Ende 13 zur Wand 6 abgewinkelt ist, um eine Einführschräge 13a zu bilden. Dies gewährleistet einen sicheren· Halt der Sockelleiste 3 an der Basisschiene 2, wobei die Stege 12 der Sockelleiste 3 zwangsweise in ihre korrekte Lage hinter den Stegen 11 der Basisschiene 2 geführt werden. Um eine ausreichende Haltekraft der Stege 12 zu erzielen, sind diese federnd ausgebildet. Außerdem bildet ein weiterer Steg 14 der Basisschiene 2 ein Widerlager 15 .für die Sockelleiste 3. Dieses Widerlager 15 ist mit einer Zahnprofilierung 16 versehen, die passend zu einer Zahnprofilierung 17 der Sockelleiste 3 ausgebildet ist. Diese Zahnprofilierungen 16, 17 sorgen für ein sicheres Verrasten der Sockelleiste 3 an der Basisschiene 2, so daß sich die Sockelleiste 3 nicht selbsttätig von der Basisschiene 2 lösen kann.In order to be able to easily attach the skirting board 3 to the base rail 2, the latter has two webs 11 which are slightly inclined upwards towards the wall. These webs 11 can be gripped behind by webs 12 of the skirting board 3, the free end 13 of which is angled towards the wall 6 in order to form an insertion bevel 13a. This ensures that the skirting board 3 is securely held on the base rail 2, with the webs 12 of the skirting board 3 being forced into their correct position behind the webs 11 of the base rail 2. In order to achieve sufficient holding force of the webs 12, these are designed to be springy. In addition, a further web 14 of the base rail 2 forms an abutment 15 for the skirting board 3. This abutment 15 is provided with a toothed profile 16 which is designed to match a toothed profile 17 of the skirting board 3. These tooth profiles 16, 17 ensure that the skirting board 3 is securely locked to the base rail 2 so that the skirting board 3 cannot detach itself from the base rail 2.

Der Steg 14 der Basisschiene 2 ist stufenförmig nach oben gebogen, so daß zwischen diesem und dem vertikalen Schenkel 8 der Basisschiene 2 ein Kabelkanal 18 ausgebildet ist. Dieser Kabelkanal 18 ist dabei derart ausgebildet, daß Kabel 19, 20 bei abgenommener Sockelleiste 3 problemlos in den Kabelkanal 18 eingelegt werden können. Der Kabelkanal 18 bietet dabei in seinem unteren Bereich ausreichend Platz für ein Flachkabel 19 und im oberen Bereich für ein zusätzliches Rundkabel 20. Auf diese Weise ist eine universelle Einsetzbarkeit des Profilschienensystems 1 gewährleistet.The web 14 of the base rail 2 is bent upwards in a step-like manner so that a cable duct 18 is formed between it and the vertical leg 8 of the base rail 2. This cable duct 18 is designed in such a way that cables 19, 20 can be easily inserted into the cable duct 18 when the skirting board 3 is removed. The cable duct 18 offers sufficient space in its lower area for a flat cable 19 and in the upper area for an additional round cable 20. In this way, universal usability of the profile rail system 1 is ensured.

• ··

-7--7-

Figur 2 zeigt das Profilschienensystem 1 gemäß Figur 1 bei der Montage der Sockelleiste 3. Die Sockelleiste 3 wurde dabei bereits in horizontaler Richtung an die ,,Basisschiene 2 herangeführt, wobei sich die Stege 12 der Sockelleiste 3 noch nicht mit den Stegen 11 der Basisschiene 2 überlappen. Um diese für die Montage wichtige Lage der Sockelleiste 3 einnehmen zu können, ist es entscheidend, daß der L-förmig gebogene Steg 12 der Sockelleiste 2 einen ausreichenden Freiraum 21 erhält. Dies wird durch den stufenförmig nach oben gebogenen Steg 15 der Basisschiene 2 gewährleistet. Alternativ würde der zur Verfügung stehende Querschnitt des Kabelkanals 18 entsprechend eingeschränkt werden.Figure 2 shows the profile rail system 1 according to Figure 1 during the assembly of the skirting board 3. The skirting board 3 has already been brought up to the "base rail" 2 in a horizontal direction, whereby the webs 12 of the skirting board 3 do not yet overlap with the webs 11 of the base rail 2. In order to be able to assume this position of the skirting board 3, which is important for assembly, it is crucial that the L-shaped web 12 of the skirting board 2 is given sufficient free space 21. This is ensured by the web 15 of the base rail 2 which is bent upwards in a step-like manner. Alternatively, the available cross-section of the cable duct 18 would be restricted accordingly.

Figur 3 zeigt das Profilschienensystem 1 gemäß Figur 2 in fertig montierter Lage. Dabei hintergreifen die Stege- 12 der Sockelleiste 3 die Stege 11 der Basisschiene 2. Durch die Schrägstellung der Stege 11 der Basisschiene 2 in bezug auf die Steckrichtung 22 der Sockelleiste 3 um einen spitzen Winkel &agr; und die federnde Wirkung der Stege 12 der Sockelleiste 3 ergibt sich eine ausreichend sichere Haltekraft der Sockelleiste 3 an der Basisschiene 2. Diese muß erst überwunden werden, um die Sockelleiste 3 wieder demontieren zu können, so daß ein selbsttätiges Lösen der Sockelleiste 3 von der Basisschiene 2 vermieden wird. Diese Haltekraft wird durch die Verzahnungen 16, 17 am Widerlager 15 bzw. an der Sockelleiste 3 zusätzlich verstärkt. Figure 3 shows the profile rail system 1 according to Figure 2 in the fully assembled position. The webs 12 of the skirting board 3 engage behind the webs 11 of the base rail 2. The inclination of the webs 11 of the base rail 2 in relation to the plug-in direction 22 of the skirting board 3 by an acute angle α and the spring effect of the webs 12 of the skirting board 3 result in a sufficiently secure holding force of the skirting board 3 on the base rail 2. This must first be overcome in order to be able to dismantle the skirting board 3 again, so that the skirting board 3 does not come loose from the base rail 2 on its own. This holding force is additionally reinforced by the teeth 16, 17 on the abutment 15 and on the skirting board 3.

Die Figur 4 zeigt eine Schnittdarstellung einer ersten alternativen Ausführungsform eines ProfilschienensystemsFigure 4 shows a sectional view of a first alternative embodiment of a profile rail system

-&dgr;&igr;, wobei gleiche Bezugszeichen gleiche Teile benennen. In Abweichung zum vorbeschriebenen Ausführungsbeispiel wird der das Widerlager 15 bildende Steg 14 zusätzlich vom federnden Steg 12 der Sockelleiste 3 hintergriffen, so daß das Widerlager 15 in platzsparender Weise eine vollständige Arretierung der Sockelleiste 3 ermöglicht. Zu diesem Zweck ist am Widerlager 15 beidseitig die Verzahnung- 16 vorgesehen, wobei sowohl an der Sockelleiste 3 als auch am federnden Steg 12 entsprechende Gegenverzahnungen 17 eingeformt sind.-δ&igr;, where like reference numerals designate like parts. In deviation from the previously described embodiment, the web 14 forming the abutment 15 is additionally engaged by the resilient web 12 of the skirting board 3, so that the abutment 15 enables the skirting board 3 to be completely locked in place in a space-saving manner. For this purpose, the teeth 16 are provided on both sides of the abutment 15, with corresponding counter teeth 17 being formed on both the skirting board 3 and the resilient web 12.

Der am horizontalen Schenkel 9 der Basisschiene 2 angeformte vertikale Schenkel 11 dient bei dieser Ausführungsform im wesentlichen zur Anlage der Sockelleiste 3, damit diese nicht verkippen kann. Außerdem bildet der Steg 11 zusammen mit dem vertikalen Schenkel 8 der Basisschiene 2 den Kabelkanal 18 zur Aufnahme der Kabel 19, 20.In this embodiment, the vertical leg 11 formed on the horizontal leg 9 of the base rail 2 serves essentially to support the skirting board 3 so that it cannot tip over. In addition, the web 11 together with the vertical leg 8 of the base rail 2 forms the cable channel 18 for receiving the cables 19, 20.

Figur 5 zeigt schließlich eine weitere alternative Äusführungsform des Profilschienensystems 1, wobei gleiche Bezugszeichen wiederum gleiche Teile benennen. Die Stege 11 sind dabei über Längsnuten 23 an der Basisschiene 2 angeformt, wodurch sich die gewünschte federnde Wirkung der Stege 11 ergibt.Finally, Figure 5 shows another alternative embodiment of the profile rail system 1, wherein the same reference numerals again designate the same parts. The webs 11 are formed on the base rail 2 via longitudinal grooves 23, which results in the desired spring effect of the webs 11.

Die Stege 11 sind in Abweichung zu den vorgenannten Ausführungsbeispielen horizontal ausgerichtet, wobei der einzige Steg 12 der Sockelleiste 3 zwischen die Stege 11 der Basisschiene 2 eingreift. Die Stege 11 der Basisschiene 2 sind dabei jeweils mit zueinander gerichtetenIn contrast to the above-mentioned embodiments, the webs 11 are aligned horizontally, with the only web 12 of the skirting board 3 engaging between the webs 11 of the base rail 2. The webs 11 of the base rail 2 are each provided with mutually directed

• ··

• ··

Verzahnungen 17 ausgerüstet. Diese wirken mit beidseitig vorgesehenen Verzahnungen 16 des Steges 12 der Sockelleiste 3 zusammen.Toothings 17. These interact with toothings 16 provided on both sides of the web 12 of the skirting board 3.

Um ein Verkippen der Sockelleiste 3 zu verhindern, sind außerdem zwei Stege 14 an der Basisschiene 2 angeformt, die als Widerlager 15 für die Sockelleiste 3 dienen. Diese Stege 15 bilden zusammen mit dem vertikalen Schenkel 8 der Basisschiene 2 Kabelkanäle 18 zur Aufnahme der Kabel 19, 20.In order to prevent the skirting board 3 from tipping over, two webs 14 are also formed on the base rail 2, which serve as abutments 15 for the skirting board 3. These webs 15, together with the vertical leg 8 of the base rail 2, form cable channels 18 for accommodating the cables 19, 20.

BezugszeichenlisteList of reference symbols

11 ProfilschienensystemProfile rail system 22 BasisschieneBase rail 33 SockelleisteSkirting board 44 SenklochbohrungCountersunk drilling 55 Schraubescrew 66 Bandtape 7.7. DübelDowel CX)CX) vertikaler Schenkelvertical leg 99 horizontaler Schenkelhorizontal leg 1010 BodenFloor 11 ■11 ■ Steg der BasisschieneBridge of the base rail 1212 Steg der SockelleisteSkirting board web 1313 freies Ende des Stegsfree end of the bridge 13a13a EinführschrägeInsertion bevel 1414 Steg der BasisschieneBridge of the base rail 1515 WiderlagerAbutment 16, 1716, 17 ZahnprofilierungTooth profiling 1818 KabelkanalCabel Canal 1919 FlachkabelFlat cable 2020 RundkabelRound cable 2121 Freiraumfree space 2222 SteckrichtungPlug direction 2323 LängsnutLongitudinal groove &agr;&agr; Winkelangle

Claims (8)

1. Profilschienensystem bestehend aus einer an einer Wand (6) festlegbaren Basisschiene (2) mit L-förmigem Querschnitt mit einem horizontalen (9) und einem vertikalen Schenkel (8), und einer darauf aufsteckbaren, die Basisschiene (2) abdeckenden Sockelleiste (3), wobei an der Basisschiene (2) Stege (11, 14) angeformt sind, von denen mindestens einer von einem Steg (12) der Sockelleiste (2) hintergreifbar ist und mindestens einer ein Widerlager (15) zur Abstützung der Sockelleiste (3) bildet, wobei mindestens einer der Stege (11, 12, 14) der Basisschiene (2) und/oder der Sockelleiste (3) federnd und in Steckrichtung (22) der Sockelleiste (3) betrachtet hinterschnitten ist und mindestens einer der Stege (11, 14) der Basisschiene (2) zusammen mit derem vertikalen Schenkel (8) einen Kabelkanal (18) bildet. 1. Profile rail system comprising a base rail ( 2 ) which can be fixed to a wall ( 6 ) and has an L-shaped cross-section with a horizontal ( 9 ) and a vertical leg ( 8 ), and a skirting board ( 3 ) which can be plugged onto the base rail ( 2 ) and covers the base rail ( 2 ), wherein webs ( 11 , 14 ) are formed on the base rail (2), at least one of which webs can be gripped behind by a web ( 12 ) of the skirting board ( 2 ) and at least one of which forms an abutment ( 15 ) for supporting the skirting board ( 3 ), wherein at least one of the webs ( 11 , 12 , 14 ) of the base rail ( 2 ) and/or the skirting board ( 3 ) is resilient and undercut when viewed in the plug-in direction ( 22 ) of the skirting board ( 3 ), and at least one of the webs ( 11 , 14 ) of the Base rail ( 2 ) together with its vertical leg ( 8 ) forms a cable duct ( 18 ). 2. Profilschienensystem nach Anspruch 1, bei dem der mindestens eine federnde Steg (11, 12) in einem spitzen Winkel (α) zur Steckrichtung (22) der Sockelleiste (3) angestellt ist. 2. Profile rail system according to claim 1, wherein the at least one resilient web ( 11 , 12 ) is set at an acute angle (α) to the insertion direction ( 22 ) of the skirting board ( 3 ). 3. Profilschienensystem nach Anspruch 1 oder 2, bei dem der mindestens eine federnde Steg (11, 12, 14) eine quer zur Aufsteckrichtung (22) der Sockelleiste (3) ausgerichtete Zahnprofilierung (16) aufweist, die mit einer entsprechenden Zahnprofilierung (17) der Sockelleiste (3) zusammenwirkt. 3. Profile rail system according to claim 1 or 2, wherein the at least one resilient web ( 11 , 12 , 14 ) has a tooth profile ( 16 ) aligned transversely to the attachment direction ( 22 ) of the skirting board ( 3 ), which cooperates with a corresponding tooth profile ( 17 ) of the skirting board ( 3 ). 4. Profilschienensystem nach mindestens einem der Ansprüche 1 bis 3, bei dem mindestens einer der Stege (11, 12, 14) eine Einführschräge (13a) aufweist. 4. Profile rail system according to at least one of claims 1 to 3, wherein at least one of the webs ( 11 , 12 , 14 ) has an insertion bevel ( 13a ). 5. Profilschienensystem nach mindestens einem der Ansprüche 1 bis 4, bei dem der den Kabelkanal (18) begrenzende Steg (14) auch das Widerlager (15) für die Sockelleiste (3) bildet. 5. Profile rail system according to at least one of claims 1 to 4, in which the web ( 14 ) delimiting the cable duct ( 18 ) also forms the abutment ( 15 ) for the skirting board ( 3 ). 6. Profilschienensystem nach mindestens einem der Ansprüche 1 bis 5, bei dem der den Kabelkanal (18) begrenzende Steg (14) stufenartig geformt ist, um einen Freiraum (21) für den federnden Steg (12) der Sockelleiste (2) zu schaffen. 6. Profile rail system according to at least one of claims 1 to 5, in which the web ( 14 ) delimiting the cable duct ( 18 ) is shaped like steps in order to create a free space ( 21 ) for the resilient web ( 12 ) of the skirting board ( 2 ). 7. Profilschienensystem nach mindestens einem der Ansprüche 1 bis 6, bei dem einer der Stege (11) der Basisschiene (2) vom federnden Steg (12) der Sockelleiste (3) hintergriffen ist und das Widerlager (15) für die Sockelleiste (3) bildet. 7. Profile rail system according to at least one of claims 1 to 6, in which one of the webs ( 11 ) of the base rail ( 2 ) is engaged behind by the resilient web ( 12 ) of the skirting board ( 3 ) and forms the abutment ( 15 ) for the skirting board ( 3 ). 8. Profilschienensystem nach mindestens einem der Ansprüche 1 bis 7, bei dem der Kabelkanal (18) zur Aufnähme mehrerer Kabel (19, 20) vorgesehen ist. 8. Profile rail system according to at least one of claims 1 to 7, wherein the cable duct ( 18 ) is provided for receiving a plurality of cables ( 19 , 20 ).
DE20200446U 2002-01-11 2002-01-11 Profile rail system Expired - Lifetime DE20200446U1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
DE20200446U DE20200446U1 (en) 2002-01-11 2002-01-11 Profile rail system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
DE20200446U DE20200446U1 (en) 2002-01-11 2002-01-11 Profile rail system

Publications (1)

Publication Number Publication Date
DE20200446U1 true DE20200446U1 (en) 2002-06-06

Family

ID=7966514

Family Applications (1)

Application Number Title Priority Date Filing Date
DE20200446U Expired - Lifetime DE20200446U1 (en) 2002-01-11 2002-01-11 Profile rail system

Country Status (1)

Country Link
DE (1) DE20200446U1 (en)

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2851697A1 (en) * 2003-02-26 2004-08-27 Casanova Cable accommodating electrical baseboard for use in office, has cover portion with fixing units to cooperate with two suspension straps through vertical interlocking by bringing portion vertically on rail parallel to wall
WO2004020755A3 (en) * 2002-08-09 2004-09-10 Roemmler H Resopal Werk Gmbh Kit for a wall-finishing board
WO2005005746A3 (en) * 2003-07-10 2005-03-24 Pavol Matus System for the connection of horizontal areas, particularly floors, to vertical walls
DE102004012316A1 (en) * 2004-03-11 2005-09-22 Alfer-Aluminium Gesellschaft Mbh skirting
DE102004012313A1 (en) * 2004-03-11 2005-09-22 Alfer-Aluminium Gesellschaft Mbh mounting strip
DE10260037B4 (en) * 2001-12-21 2006-11-09 Burhan Dereli Device for attaching objects to wall parts
WO2007055628A1 (en) * 2005-11-14 2007-05-18 Lars Eriksson Cover strip with fastening means
DE202008015223U1 (en) 2008-11-05 2010-03-25 Sondermann, Frank Skirting for covering a lining edge
EP2037056A3 (en) * 2007-09-11 2011-12-21 W. Döllken & Co. GmbH Baseboard
EP2445069A1 (en) 2010-10-21 2012-04-25 Karl Pedross AG Corner profile system
CN112502395A (en) * 2020-11-28 2021-03-16 山东乐缘机械设备有限公司 Skirting line with inside circuit structure of laying

Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US1488090A (en) 1922-03-02 1924-03-25 Charles Woodward Conduit baseboard
DE1870967U (en) 1963-01-29 1963-04-25 Rehau Plastiks CORNER BOARD CONNECTOR FOR SKIRTING BOARDS.
CH379743A (en) 1958-11-15 1964-07-15 Plastopress Ag Multi-part bar
CH429111A (en) 1958-11-15 1967-01-31 Plastopress Ag Multi-part bar
AT269452B (en) 1967-10-19 1969-03-25 Karl Nosek Link between a hollow chair rail and wall-mounted brackets
FR2080558A1 (en) 1970-02-17 1971-11-19 Campen Willy Van
GB2169935A (en) 1985-01-23 1986-07-23 Glidevale Building Prod Retaining device for a covering strip
DE9001715U1 (en) 1990-02-14 1990-04-19 Schock & Co Gmbh, 7060 Schorndorf End piece for a wall connection profile strip
DE9103263U1 (en) 1991-03-18 1991-06-13 Hewing GmbH, 4434 Ochtrup Installation channel for supply lines
DE9103262U1 (en) 1991-03-18 1991-06-13 Hewing GmbH, 4434 Ochtrup Installation channel for supply lines
DE29703744U1 (en) 1997-03-01 1997-04-17 Rehau Ag + Co, 95111 Rehau Installation duct

Patent Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US1488090A (en) 1922-03-02 1924-03-25 Charles Woodward Conduit baseboard
CH379743A (en) 1958-11-15 1964-07-15 Plastopress Ag Multi-part bar
CH429111A (en) 1958-11-15 1967-01-31 Plastopress Ag Multi-part bar
DE1870967U (en) 1963-01-29 1963-04-25 Rehau Plastiks CORNER BOARD CONNECTOR FOR SKIRTING BOARDS.
AT269452B (en) 1967-10-19 1969-03-25 Karl Nosek Link between a hollow chair rail and wall-mounted brackets
FR2080558A1 (en) 1970-02-17 1971-11-19 Campen Willy Van
GB2169935A (en) 1985-01-23 1986-07-23 Glidevale Building Prod Retaining device for a covering strip
DE9001715U1 (en) 1990-02-14 1990-04-19 Schock & Co Gmbh, 7060 Schorndorf End piece for a wall connection profile strip
DE9103263U1 (en) 1991-03-18 1991-06-13 Hewing GmbH, 4434 Ochtrup Installation channel for supply lines
DE9103262U1 (en) 1991-03-18 1991-06-13 Hewing GmbH, 4434 Ochtrup Installation channel for supply lines
DE29703744U1 (en) 1997-03-01 1997-04-17 Rehau Ag + Co, 95111 Rehau Installation duct

Cited By (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE10260037B4 (en) * 2001-12-21 2006-11-09 Burhan Dereli Device for attaching objects to wall parts
WO2004020755A3 (en) * 2002-08-09 2004-09-10 Roemmler H Resopal Werk Gmbh Kit for a wall-finishing board
EP1453167A1 (en) * 2003-02-26 2004-09-01 Casanova Electrical plinth
FR2851697A1 (en) * 2003-02-26 2004-08-27 Casanova Cable accommodating electrical baseboard for use in office, has cover portion with fixing units to cooperate with two suspension straps through vertical interlocking by bringing portion vertically on rail parallel to wall
WO2005005746A3 (en) * 2003-07-10 2005-03-24 Pavol Matus System for the connection of horizontal areas, particularly floors, to vertical walls
DE102004012313A1 (en) * 2004-03-11 2005-09-22 Alfer-Aluminium Gesellschaft Mbh mounting strip
DE102004012316A1 (en) * 2004-03-11 2005-09-22 Alfer-Aluminium Gesellschaft Mbh skirting
EP1725723A2 (en) * 2004-03-11 2006-11-29 alfer-aluminium Gesellschaft mbH Fixing strip
WO2007055628A1 (en) * 2005-11-14 2007-05-18 Lars Eriksson Cover strip with fastening means
EP2037056A3 (en) * 2007-09-11 2011-12-21 W. Döllken & Co. GmbH Baseboard
DE202008015223U1 (en) 2008-11-05 2010-03-25 Sondermann, Frank Skirting for covering a lining edge
EP2184423A2 (en) 2008-11-05 2010-05-12 Frank Sondermann Baseboard for covering the edge of a facing
EA017561B1 (en) * 2008-11-05 2013-01-30 Кюберит Профиле Системз Гмбх Унд Ко.Кг Reversible baseboard for covering a flooring border
EP2445069A1 (en) 2010-10-21 2012-04-25 Karl Pedross AG Corner profile system
CN112502395A (en) * 2020-11-28 2021-03-16 山东乐缘机械设备有限公司 Skirting line with inside circuit structure of laying

Similar Documents

Publication Publication Date Title
DE10107864C2 (en) Holding element for cover strips
DE3214528C2 (en) Device for fixing instrument housings in a carrier plate
EP0199025B1 (en) Fastening arrangement for lamellae of a venetian blind
DE20200446U1 (en) Profile rail system
DE3113679A1 (en) Installation apparatus box for installation in installation channels (ducts)
DE102019122500A1 (en) Wall or floor bar with integrated cable duct and method for installing such a wall or floor bar
DE69308797T2 (en) Attach the equipment rack to a cable duct with opposing projections
AT522814B1 (en) FIXING OF PANEL ELEMENT
DE2610998B2 (en) Bracket for fastening cladding panels in front of a building wall
EP3968817B1 (en) Rear wall connector for drawers
DE3336805A1 (en) SHUTTER BOX
DE4200124A1 (en) FASTENING DEVICE FOR A BUILDING WALL PANELING
EP0362584B1 (en) Furniture corner joint
DE29717135U1 (en) Profile system for mounting cladding panels on walls or ceilings
DE69510627T2 (en) Device support device To be installed on a cable duct body
EP1001103A2 (en) Edge trimming profile for wall cladding
DE2804419A1 (en) cable runway also supporting electrical fittings - has locking grooves along upper edges of side walls to hold cable bridges in position
DE3109885A1 (en) Electric light fixture for installation in prefabricated false sealings
DE10149408C1 (en) Device for fixing border rails comprises a mounting rail and a border rail connected to an intermediate rail using a socket connection designed so that the border rail and the mounting rail are connected in the same insertion direction
DE8707366U1 (en) Office desk
CH445595A (en) Installation duct for laying electrical cables
DE3240895C2 (en)
DE10218128C1 (en) Electrical distributor for lamp fitting secured in opening in wall of lamp fitting housing via cooperating upper and lower clamp parts
DE202023102513U1 (en) Cable carrier for a distributor room for accommodating cables
EP0216150A1 (en) Fixing device for an essentially rigid rail to a room wall, especially a bathroom wall

Legal Events

Date Code Title Description
R207 Utility model specification

Effective date: 20020711

R163 Identified publications notified

Effective date: 20020715

R150 Utility model maintained after payment of first maintenance fee after three years

Effective date: 20050404

R151 Utility model maintained after payment of second maintenance fee after six years

Effective date: 20080408

R152 Utility model maintained after payment of third maintenance fee after eight years

Effective date: 20100331

R071 Expiry of right
R071 Expiry of right